Teeny v. Haertl Constructors, Inc.

842 P.2d 788, 314 Or. 688, 1992 Ore. LEXIS 230
CourtOregon Supreme Court
DecidedDecember 4, 1992
DocketCC 8808-04655; CA A63888; SC S39122
StatusPublished
Cited by9 cases

This text of 842 P.2d 788 (Teeny v. Haertl Constructors, Inc.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Teeny v. Haertl Constructors, Inc., 842 P.2d 788, 314 Or. 688, 1992 Ore. LEXIS 230 (Or. 1992).

Opinion

*691 GILLETTE, J.

In this lien foreclosure case, several construction subcontractors involved in renovating a commercial building in downtown Portland sought to foreclose construction liens on the property after the general contractor had failed to pay them amounts due under their subcontracts. The property owner contested the liens. The trial court held, among other things, that the liens of two of the subcontractors — Enterprise Fabricators Co., Inc. (Enterprise), and Microflect, Inc. (Microflect) — were invalid, because neither subcontractor had given the property owner a notice of right to a lien pursuant to ORS 87.021, set out infra. The Court of Appeals reversed and remanded, holding in part that Enterprise and Microflect were exempt from the notice requirement under ORS 87.021(3)(b). Teeny v. Haertl Constructors, Inc., 111 Or App 543, 826 P2d 1029 (1992). We allowed review and now reverse the Court of Appeals on this issue. 1

In 1987 and 1988, Haertl Constructors, Inc. (Haertl), served as general contractor on a construction project to renovate part of a multi-story retail and office building in downtown Portland. In 1987, Haertl subcontracted with Enterprise to do custom steel fabrication for the project. Almost all of Enterprise’s work occurred off-site at its shop, where Enterprise fabricated various items. Enterprise then delivered those items to the construction site for others to install. In addition to approximately 22 delivery trips, Enterprise’s president, Mel Haldors, made approximately 19 other *692 trips to the construction site, where he took measurements and met with various people to work out problems related to Enterprise’s fabrication tasks.

In May 1988, Microflect provided aluminum grating for the project under a subcontract with Haertl. John Robertson, a general manager at Microflect, spent four hours at the construction site taking measurements for the grating. The grating was then cut to size at Microflect’s shop in Salem and delivered to the construction site by an independent trucking company.

In August 1988, Gary and Richard Teeny, who were also subcontractors on the project, filed this action, seeking recovery against Haertl for the amount due on their subcontract and also seeking to foreclose a construction lien on the property. All other subcontractors and the property owner were joined as defendants in the action. By counterclaim and cross-claim, Enterprise and Microflect each sought to recover against Haertl and to foreclose construction liens on the property. 2

In January 1990, the trial court entered judgment in the action, ruling in part that the liens of Enterprise and Microflect were invalid, because neither subcontractor had provided the property owner a notice of right to a lien, as required by ORS 87.021. That statute provides, in part:

“(1) Except when material, equipment, services or labor described in ORS 87.010(1) * * * is furnished at the request of the owner, a person furnishing any materials, equipment, services or labor described in ORS 87.010(1) * * * for which a lien may be perfected under ORS 87.035 shall give a notice of right to a lien to the owner of the site. The notice of right to a lien may be given at any time during the *693 progress of the improvement, but the notice only protects the right to perfect a lien for material, equipment and labor or services provided after a date which is eight days, not including Saturdays, Sundays and other holidays as defined in ORS 187.010, before the notice is delivered or mailed. * * *
C<$ * * * *
“(3)(a) Except as provided in paragraph (b) of this subsection, a lien created under ORS 87.010(1) * * * may be perfected under ORS 87.035 only to the extent that the notice required by subsection (1) of this section is given.
“(b) A person who performs labor upon a commercial improvement or provides labor and material for a commercial improvement * * * need not give the notice required by subsection (1) of this section in order to perfect a lien created under ORS 87.010. As used in this paragraph:
“(A) ‘Commercial improvement’ means any structure or building not used or intended to be used as a residential building, or other improvement to a site on which such a structure or building is to be located.”

Enterprise and Microflect conceded that they had not provided the property owner with notices of right to a lien, and the trial court concluded that neither Enterprise nor Micro-flect fell within the exception of ORS 87.021(3) (b) for a person who “performs labor upon a commercial improvement or provides labor and material for a commercial improvement.” It is this ruling that is at issue before us.

Enterprise and Microflect appealed the trial court judgment, arguing to the Court of Appeals that a person who provides material for a project after performing custom work on that material away from the construction site “provides labor and material for a commercial improvement” within the meaning of ORS 87.021(3)(b). In response, the property owner argued that only a person who labors on-site, either by installing material or by working on material at the construction site, “performs labor upon a commercial improvement or provides labor and material for a commercial improvement” within the statute’s meaning. The Court of Appeals rejected the owner’s argument, stating: “To agree with that conclusion, we would have to ignore the plain language of the statute. When the legislature uses different language for similar statutory provisions, we assume that it intended different meanings. * * * ‘Performs labor upon’ must mean *694 something different than ‘provides labor * * * for.’ ” Teeny v. Haertl Constructors, Inc., supra, 111 Or App at 548. Consequently, the Court of Appeals held in favor of Enterprise and Mieroflect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A-C Construction, Inc. v. Bakke Corp.
956 P.2d 219 (Court of Appeals of Oregon, 1998)
Portland General Electric Co. v. Bureau of Labor & Industries
859 P.2d 1143 (Oregon Supreme Court, 1993)
State v. Person
853 P.2d 813 (Oregon Supreme Court, 1993)
State v. King
852 P.2d 190 (Oregon Supreme Court, 1993)
State Ex Rel. Kafoury v. Jones
843 P.2d 932 (Oregon Supreme Court, 1992)
Blanchard ex rel. Blanchard v. Kaiser Foundation Health Plan
844 P.2d 248 (Court of Appeals of Oregon, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
842 P.2d 788, 314 Or. 688, 1992 Ore. LEXIS 230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teeny-v-haertl-constructors-inc-or-1992.