Team Contractors, L.L.C. v. Waypoint NOLA, L.L.C.

CourtDistrict Court, E.D. Louisiana
DecidedAugust 2, 2019
Docket2:16-cv-01131
StatusUnknown

This text of Team Contractors, L.L.C. v. Waypoint NOLA, L.L.C. (Team Contractors, L.L.C. v. Waypoint NOLA, L.L.C.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Team Contractors, L.L.C. v. Waypoint NOLA, L.L.C., (E.D. La. 2019).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

TEAM CONTRACTORS, LLC, CIVIL ACTION Plaintiff

VERSUS NO. 16-1131

WAYPOINT NOLA, LLC, ET AL., SECTION: “E”(2) Defendants

ORDER AND REASONS Before the Court is a motion for judgment as a matter of law or alternatively for a new trial, filed by Defendant Waypoint NOLA, L.L.C. (“Waypoint”) under Rule 50(b) of the Federal Rules of Civil Procedure.1 Plaintiff Team Contractors, LLC (“Team”) opposes.2 For the following reasons, the motion is DENIED. BACKGROUND This dispute arises from contracts made in connection with the construction and renovation of Waypoint’s property at 1250 Poydras St. in New Orleans (“the Project”). On September 19, 2014, Waypoint entered a contract with Development Construction Management LLC, represented by Steve Laski (“Laski”), under which Laski agreed to provide project management services for the Project.3 On September 24, 2014, Team and Waypoint entered into a construction contract (“the Prime Contract”), under which Team became the general contractor for the Project.4 Waypoint also entered into a contract with HC Architecture, Inc. (“HCA”), under which HCA agreed to serve as the project’s

1 R. Doc. 601. 2 R. Doc. 604. 3 R. Doc. 477-1. 4 Trial Ex. 88. architect.5 HCA, in turn, subcontracted the mechanical, electrical, and plumbing design work to KLG, L.L.C. (“KLG”).6 On April 13, 2016, Waypoint executed Change Order No. 9.7 Team submitted three lien waivers to Waypoint on July 27, 2016.8 Each lien waiver is labeled “Final Waiver of Liens” and includes an attachment listing outstanding sums owed to subcontractors.9 The attachment to each of the three lien waivers lists different amounts owed to various subcontractors. Waypoint did not pay Team after receiving these first three lien waivers. On June 28, 2017, Team submitted a fourth lien waiver, which also was labeled “Final

Waiver of Liens” and includes an attachment with a different list of outstanding sums owed to subcontractors.10 On July 10, 2017, Waypoint paid Team the final payment amount of $1,023,514.09.11 On July 22, 2016, Team drafted Change Order No. 10, incorporating Change Order Requests 33, 56, 58, 59, and 64–69.12 On February 5, 2016, Team filed a complaint against HCA, KLG, and Waypoint.13 Team alleged there were errors in the plans and specifications provided by Waypoint for the mechanical, electrical, and plumbing systems relating to the construction project, which were prepared by KLG.14 Team also alleged Waypoint directed it to modify the MEP systems, but did not compensate Team for the additional costs Team incurred as a result

5 Trial Ex. 87. 6 R. Doc. 157-18. Defendant KLG informed the Court in its answer that it is now known as Salas O’Brien South, L.L.C. R. Doc. 34. The parties continued to refer to it as KLG. The Court will continue to do so in this order. 7 Trial Ex. 325. 8 Trial Ex. 320. 9 Each lien waiver consists of two pages: the waiver signed by Team and an “Exhibit A” listing sums owed to subcontractors. Trial Ex. 320. 10 Trial Ex. 320 at 7–8. 11 R. Doc. 548 at 11, ¶ 7(5) (uncontested material facts in pretrial order). 12 Trial Ex. 113. 13 R. Doc. 1. 14 Id. at 3, ¶ 16. of the modifications.15 Plaintiff Team brought a breach of contract claim against Waypoint, alleging Waypoint’s failure to compensate Team breached the construction contract.16 Team also brought negligence claims against Waypoint, HCA, and KLG.17 This Court conducted the first jury trial in this matter from February 26, 2018 to March 9, 2018. Three claims were tried: Team’s breach of contract claim against Waypoint and Team’s negligence claims against HCA and KLG.18 Team did not pursue a negligence claim against Waypoint at trial.19 The jury awarded Team $565,979.99 in damages.20 On the negligence claims against HCA and KLG, the jury found HCA and

KLG’s conduct violated their professional duties of care and caused damage to Team.21 The jury also found Waypoint had not breached the contract.22 However, the jury assigned Waypoint and its agent responsibility for damages.23 When assigning “percentages of responsibility for the damages” awarded, the jury assigned 30% to HCA, 60% to KLG, 5% to Waypoint, and 5% to Waypoint’s project manager Steve Laski, who was not a party to the suit.24 On March 19, 2018, the Court entered judgment on the verdict against Defendants HCA and KLG for $509,381.99, representing 90% of the total damages the jury awarded.25 The Court entered judgment in favor of Defendant Waypoint on the breach of contract claim.26 On April 2, 2018, Team filed a motion to amend, arguing the jury’s

15 Id. at 4–5. 16 Id. at 5. 17 Id. at 5–7. 18 R. Doc. 364. 19 Id. 20 Id. at 3, ¶ 8. 21 Id. at 1, ¶ 1–4. 22 Id. at 2, ¶ 6. 23 Id. at 4, ¶ 9. 24 Id. 25 R. Doc. 370. 26 Id. finding that Waypoint did not breach its contract with Team was irreconcilably inconsistent with its assigning Waypoint and its agent responsibility for damages.27 On September 6, 2018, the Court granted Team’s motion.28 The Court found the jury verdict irreconcilably inconsistent, vacated the judgment in favor of Waypoint on Team’s breach of contract claim, and ordered a new trial on the claim.29 The Court conducted the second jury trial in this matter from April 15, 2019 to April 17, 2019.30 The trial was limited to Team’s breach of contract claim against Waypoint.31 Specifically, the Court limited the trial to (1) Team’s breach of contract claim

against Waypoint for Change Order Requests 33, 56, 58, 59, and 65, which were the unpaid change order requests finalized in Change Order No. 10 unrelated to design defects, and (2) Team’s breach of contract claim for contractual interest based on Waypoint’s failure to pay Change Order No. 9 until July 10, 2017.32 On the final day of trial, Waypoint moved for judgment as a matter of law under Rule 50(a) of the Federal Rules of Civil Procedure.33 The Court denied Waypoint’s motion.34 Team sought the following unpaid amounts under Change Order No. 10:35 • Change Order Request 33 (Proposed Change Order 75) $4,812.58 • Change Order Request 56 (Proposed Change Order 108) $8,697.59 • Change Order Request 58 (Proposed Change Order 110) $10,098.02 • Change Order Request 59 (Proposed Change Order 111) $13,000.00 • Change Order Request 65 (Proposed Change Order 117) $28,217.30

These amounts total $64,825.49.

27 R. Doc. 372. 28 R. Doc. 420. 29 Id. at 8–10. 30 R. Docs. 550, 554, 555. 31 R. Doc. 519. 32 Id. at 7–8. 33 R. Doc. 555. 34 Id. 35 R. Doc. 548 at 8; Trial Ex. 113. The jury found Team established by a preponderance of the evidence that Waypoint breached the contract by not paying Team for the amounts in Change Order Requests 33, 56, 58, 59, and 65, and awarded damages in the following amounts:36 • Change Order Request 33 (Proposed Change Order 75) $4,812.58 • Change Order Request 56 (Proposed Change Order 108) $6,000.00 • Change Order Request 58 (Proposed Change Order 110) $10,098.02 • Change Order Request 59 (Proposed Change Order 111) $13,000.00 • Change Order Request 65 (Proposed Change Order 117) $25,835.83

These amounts total $59,746.43. The jury also found that Team established by a preponderance of the evidence that “Waypoint breached the contract by unreasonably deciding not to pay Team for Change Order No. 9, plus retainage,” at two times: “within thirty days of Waypoint’s signing Change Order No. 9” and “after Team’s submission on July 27, 2016.”37 On May 22, 2019, the Court entered an Order and Reasons finding Team was entitled to contractual interest and attorneys’ fees.38 The Court found contractual interest began to accrue on May 13, 2016, which was thirty days after Waypoint signed Change Order No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Team Contractors, L.L.C. v. Waypoint NOLA, L.L.C., Counsel Stack Legal Research, https://law.counselstack.com/opinion/team-contractors-llc-v-waypoint-nola-llc-laed-2019.