Teal Construction Company/Hillside Villas Ltd. v. Darren Casey Interests, Inc. Hillside Villas Ltd./Teal Construction Company
This text of Teal Construction Company/Hillside Villas Ltd. v. Darren Casey Interests, Inc. Hillside Villas Ltd./Teal Construction Company (Teal Construction Company/Hillside Villas Ltd. v. Darren Casey Interests, Inc. Hillside Villas Ltd./Teal Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
BACKGROUND
Hillside is a San Antonio limited partnership engaged in property development in Texas. Teal is a construction contractor based in Houston. Teal entered into a contract with Hillside in January 1999 to construct Phase II of the Hillside Ranch Apartments, located in San Marcos. Phase II consisted of three buildings containing sixty apartment units. The apartments were to be used primarily for housing students at a local university.
In the fall of 1999, during the latter stages of the project, a dispute arose between the parties regarding performance and payment under the contract. Teal had submitted unpaid change orders totaling over $700,000, for which it sought payment. Hillside refused payment, contending that the construction contract contained a guaranteed maximum price of $2.28 million and that Teal's change orders would exceed the construction budget by approximately thirty-three percent. Teal sought to mediate the dispute pursuant to the terms of the contract. Hillside refused to mediate unless Teal withdrew its claim for change orders. Teal refused and on November 16 Hillside filed this lawsuit.
In its original petition, Hillside alleged claims of fraud, fraudulent inducement, and negligent misrepresentation. Although Hillside filed several amended petitions, its basic contentions have remained the same. Hillside claimed that it entered into the contract with the understanding that it was a guaranteed maximum price contract, subject only to additions and deductions made by valid change orders. Hillside alleged that after execution of the contract, Teal fraudulently deleted a term that protected Hillside from charges that would exceed the guaranteed maximum price. In other words, Hillside alleged that the parties negotiated a guaranteed maximum price of $2.28 million, and that after the contract was executed Teal deleted a term, changing the contract into a cost-plus contract without a guaranteed maximum price. In addition, Hillside alleged that during construction Teal missed deadlines, performed in a substandard manner, and submitted change orders that were not approved by Hillside or the architect. In response, Teal filed a general denial and a motion to stay the litigation and compel arbitration.
After several hearings and a failed court-ordered mediation, the trial court entered a final order that is the subject matter of this appeal. First, the court found that the arbitration clause contained in the general conditions was validly incorporated into the parties' contract. Second, the court severed Hillside's claim for fraudulent inducement and retained it for trial. Finally, the court ordered that all disputes arising out of performance of the contract were compelled to arbitration after judgment was entered in the fraudulent inducement trial. From this order, Teal brought both an interlocutory appeal and a mandamus action. (1) Hillside cross appeals, challenging the trial court's determination that the arbitration clause was validly incorporated within the contract.
DISCUSSION
The Arbitration Clause
Hillside argues that the trial court erred in finding a valid agreement to arbitrate between Teal and Hillside. An unmodified, American Institute of Architects ("AIA"), standard-form contract does not contain an arbitration clause within its four corners. The AIA, standard-form, general-conditions document does contain an arbitration clause. Hillside and Teal, however, signed a modified, AIA, standard-form contract that incorporated by reference the general-conditions document.
An unsigned paper may be incorporated by reference in the contract signed by the party sought to be charged. Owen v. Hendricks, 433 S.W.2d 164, 166 (Tex. 1968). The specific language used is not important so long as the contract signed by the defendant plainly refers to another writing. Id. An arbitration agreement is not invalid or unenforceable merely because it is contained in a document incorporated into the contract by reference. D. Wilson Constr. Co. v. McAllen Indep. Sch. Dist., 848 S.W.2d 226, 230 (Tex. App.-Corpus Christi 1992, writ dism'd w.o.j.).
Page one of the contract signed by Hillside states that "AIA Document A201-1997, General Conditions of the Contract for Construction, is adopted in this document by reference." This statement plainly refers to the general conditions containing the arbitration clause. The trial court correctly determined that the arbitration clause was validly incorporated within the contract. Hillside's cross appeal is overruled.
Enforcement of the Arbitration Clause
We next address Teal's contention that the trial court erred by not ordering the entire dispute to arbitration. The Texas Supreme Court has expressed a strong policy preference for enforcing arbitration clauses. Capital Income Properties-LXXX v. Blackmon, 843 S.W.2d 22, 23 (Tex. 1992). A party seeking to compel arbitration must establish the existence of an arbitration agreement and show that their claims fall within the scope of that agreement. In re Oakwood Mobile Homes, Inc., 987 S.W.2d 571, 573 (Tex. 1999).
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Teal Construction Company/Hillside Villas Ltd. v. Darren Casey Interests, Inc. Hillside Villas Ltd./Teal Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teal-construction-companyhillside-villas-ltd-v-dar-texapp-2001.