Taylor v. Reed

52 A. 579, 68 N.J.L. 178, 39 Vroom 178, 1902 N.J. Sup. Ct. LEXIS 110
CourtSupreme Court of New Jersey
DecidedJune 9, 1902
StatusPublished
Cited by1 cases

This text of 52 A. 579 (Taylor v. Reed) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor v. Reed, 52 A. 579, 68 N.J.L. 178, 39 Vroom 178, 1902 N.J. Sup. Ct. LEXIS 110 (N.J. 1902).

Opinion

The opinion of the court was delivered by

Pitney, J.

This action is founded upon a stop notice given to the owner of a' building by a creditor of the building contractor, under the provisions of the Mechanics’ Lien law. The plaintiff had judgment in the trial court.

The building contract in question was filed April 5th, 1898. At that time the provisions of the supplement of 1895 to the revised Mechanics’ Lien act of 1871- were in force (Pamph. L. 1895, p. 313; Gen. Stat., p. 2073), but the moneys claimed by the plaintiff became due to him, and his stop notice and the other stop notices in question were served, all after the date when the revised Mechanics’ Lien law of 1898 and the accompanying repealer of previous legislation on the subject took effect. Pamph. L. 1898, pp. 538, 553. The pertinent provisions of the act of 1895 are' substantially embodied in the revision of 1898 as sections 3 and 5, and the difference in phraseology has no bearing upon the question in controversy in this case. It is therefore unnecessary, to consider whether the act of 1895 or the. act of 1898 applies, and for the purposes of the present discussion the act of 1898 will be treated as applicable.

The material facts are as follows: The building in question was erected by contract, in writing, made between the defendant, Eeed, as owner, and the firm of Krause Brothers, providing for its construction by that firm under the direction of an architect, and to his satisfaction, to be testified by his written certificate. The contract price for the construction of the building was to be paid in installments of 'which the final one was $1,500, to be paid when the building should be completed, provided a certificate to that effect should be signed by the architect. ’Under employment from Krause Brothers, the plaintiff did certain electrical work, which was a part of the work required to be done by them under the Eeed-Krause contract. Eeed appears to have duly paid to Krause Brothers, [180]*180prior to September 28th, 1898, all moneys called for by the contract, except the final payment of $1,500. On that date the architect delivered to Krause Brothers a certificate to the effect that they had completed their work in accordance with the plans and specifications and were “entitled to the final payment of $1,500 as per contract, reserving, however, the sum of $500 to be retained for one month.” Upon the strength of that certificate Reed paid to Krause Brothers $1,000 on September 28th. The building was not, in fact, finished until October 17th, on which day the architect delivered to Krause Brothers a certificate that they were entitled to the final payment of $500, as per contract.

Taylor, the plaintiff, completed his work on October 1st. Successive stop notices were served upon Reed, the owner, as follows: The first notice was by one Zetton for $105, and was served October 8th, 1898; the next was by the Dodge & Bliss Company for $1,157.52, served October 12th, and on October 21st the plaintiff, Taylor, served a stop notice for the sum of $75.

These several notices were founded upon demands which were, in fact, justly due and owing from Krause Brothers to the respective claimants for work done and materials furnished to Krause Brothei-s in and about the erection and construction of the building, in order to enable them to perform their contract with Reed. The controversy relates to the legal force and effect of Taylor’s stop notice, in view of the fact that before its receipt the defendant had paid to Krause Brothers the whole of the final payment excepting $500, and had received stop notices prior to that of Taylor, more than sufficient to exhaust the $500.

The trial court having found that the building was not, in fact, finished until October 17th, it would seem to follow that the payment of $1,000 made on September 28th was made “in advance of the terms of the contract,” within the meaning of section 5 of the Mechanics’ Lien law, notwithstanding it was made upon, an architect’s certificate. As the contract called for the final payment to be made upon the completion of the building, it seems to result that laborers and materialmen are [181]*181entitled to take it for granted that the final payment will not be made until the building is completed, notwithstanding an architect may prematurely certify it to be completed. But the present case does not require us to decide this point, and we may assume, in favor of the plaintiff, that the payment of $1,000 on September 28th was made in advance of the terms of the contract.

It will be observed, therefore, that the stop notices of Zetton and of the Dodge & Bliss Company were served after that advance payment and before the completion of the building, while the stop notice of the plaintiff was served after the completion of the building, although his work was completed in time to enable him to serve his stop notice before the building was completed.

Section 3 of the Mechanics’ Lien law (Pamph. L. 1898, p. 538) provides in substance that when the contractor shall, upon demand, refuse to pay any materialman, journeyman or laborer any money or wages due for materials furnished or labor performed in the erection or construction of the building, it shall be the duty of the journeyman, laborer or materialman to give notice to the owner of such refusal and of the amount so demanded, and the owner shall thereupon be authorized to retain the amount so due and claimed out of the amount owing by him upon the contract, or that may be thereafter become due from him upon the contract, giving notice to the contractor of such demand; and if not paid by the contractor, the owner, on being satisfied of the correctness of the demand, shall pay it, and the receipt of the journeyman, laborer or materialman shall entitle the owner to an allowance therefor in the settlement of accounts between him and the contractor.

Section 5 provides that if the owner shall, for the purpose of avoiding the provisions of the act, 'w in advance of the terms of the contract, pay any money or other valuable thing upon the contract, and the amount still due to the contractor, after such payment has been made, shall be insufficient to satisfy the notices served in conformity with the provisions of [182]*182the act, the owner shall be liable in the same manner as if no such payment had been made.

The present section 3 is not much different from the third section of the Mechanics’ Lien law of 1853, as amended in 1863. Pamph. L. 1853, p. 437; Id. 1863, p. 275, § 2.

In Craig v. Smith, 8 Vroom 549, it was held by the Court of Errors and Appeals that under the third section of the act of 1853, as thus amended, in order to entitle the workman or materialman to an action against the owner there must be a debt due from the owner to the contractor at the time the notice was given; and if before that time the debt had been legally assigned, so that the contractor had no control over it, or right of action for it, a notice given to the owner by the workman or materialman would create no obligation under the statute as against the owner. This was upon the ground that under the statute law as then existing there was no lien upon the moneys due from the owner to the contractor, in favor of the contractor’s creditor, until service of the notice.

Under section 3 of the revised act of 1874 (Rev. 1877, p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JAS. FALCONE PLUMBING & HEATING CO. INC. v. Pasquale
97 A.2d 720 (New Jersey Superior Court App Division, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
52 A. 579, 68 N.J.L. 178, 39 Vroom 178, 1902 N.J. Sup. Ct. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-v-reed-nj-1902.