Taylor v. Facility Constructors, Inc.

360 F. Supp. 2d 887, 2005 U.S. Dist. LEXIS 4063, 2005 WL 580521
CourtDistrict Court, N.D. Illinois
DecidedMarch 8, 2005
Docket02 C 7097
StatusPublished
Cited by1 cases

This text of 360 F. Supp. 2d 887 (Taylor v. Facility Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor v. Facility Constructors, Inc., 360 F. Supp. 2d 887, 2005 U.S. Dist. LEXIS 4063, 2005 WL 580521 (N.D. Ill. 2005).

Opinion

MEMORANDUM OPINION AND ORDER

SHAD UR, Senior District Judge.

While working at a warehouse owned by Jewel Food Stores (“Jewel”), Charles Taylor (“Taylor”) fell through an elevated wire grid and was injured. This action reflects Taylor’s effort to obtain recovery from Facility Constructors (“Facility”), the general contractor 1 that built the warehouse some five years before the accident.

After this action was originally filed in the Circuit Court of Cook County, Facility timely removed it to this District Court on diversity-of-citizenship grounds. Following the completion of discovery, Facility has moved for summary judgment under Fed.R.Civ.P. (“Rule”) 56, claiming that it cannot be held liable through any negligence theory because it owed no duty to Taylor. For the reasons set forth in this memorandum opinion and order, Facility’s motion is granted and this action is dismissed.

Rule 56 Standards

Every Rule 56 movant bears the burden of establishing the absence of any genuine issue of material fact (Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986)). For that purpose courts consider the evidentiary record in the light most favorable to non-movants and also draw all reasonable inferences in their favor (Lesch v. Crown Cork & Seal Co., 282 F.3d 467, 471 (7th Cir.2002)). But to avoid summary judgment a nonmovant “must produce more than a scintilla of evidence to support his position” that a genuine issue of material fact exists (Pugh v. City of Attica, 259 F.3d 619, 625 (7th Cir.2001)) and “must set forth specific facts that demonstrate a genuine issue of triable fact” (id.). Ultimately summary judgment is warranted only if a reasonable jury could not return a verdict for the nonmovant (Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986)).

What follows is a brief summary of the facts, viewed of course in the light most favorable to nonmovant Taylor. Other facts will follow as and when necessary to the legal discussion. Because the parties have complied with this District Court’s LR 56.1, adopted to implement Rule 56 by identifying the existence or nonexistence of disputes regarding material (that is, outcome-determinative) factual issues, this opinion will refer to the parties’ LR 56.1 *890 statements as “F. St. ¶ —” or “T. St. ¶ —” (only the former need be cited when its assertions are not in dispute).

Factual Background

Construction plans for the warehouse called in part for the installation of large storage racks to hold pallets for produce (F.St-¶ 25). Facility entered into a subcontract with Warehouse Equipment, Inc. (“Warehouse Equipment”) for the construction of those racks (id.). At some point during the design and construction process, Jewel raised a concern about the possibility of fruit falling from the pallets, 2 and a decision was made to address that possibility by installing a wire grid system to catch any produce that happened to fall (id. ¶ 26). Warehouse Equipment’s project engineer Andrew Strelec (“Strelec”) designed the wire grids and developed the installation plan, but a subcontractor hired by Warehouse Equipment actually performed the installation (id. ¶¶ 29-30). Construction of the Jewel warehouse project began around 1993 and was completed by 1995, although the precise completion date of the wire grid system is not clear from the record (Strelec Dep. 14).

Taylor sustained his injuries on April 25, 1998 while working for Jewel in the completed warehouse. Taylor stepped onto the wire grid system to remove accumulated food debris, but the grid would not sustain his weight (F.St-¶¶ 20-21). Instead it collapsed, and Taylor fell 15-20 feet to the main floor, sustaining various injuries (id.). Taylor filed his state court action on July 27, 2002, and Facility removed the action to this District Court on October 3 of that year.

Statute of Limitations

Before this opinion turns to the substantive issues that separate the parties, it must consider a threshold issue raised by Fidelity in an attempt to achieve a quick win. That issue stems from the odd procedural history of the dispute between the present parties, best explained by a review of the bidding.

Taylor’s first lawsuit in the Circuit Court of Cook County was against Warehouse Equipment as the subcontractor that had installed the wire grid. After some third-party activity, Taylor sought to add Facility as a direct defendant through an emergency motion filed just one day before the four-year statute of limitations established by 735 ILCS 5/13-214 was set to expire on April 25, 2002 (F.St.lHf 5-6).

Initially the state court granted that emergency motion. But when the court then granted a later motion to reconsider on June 10, 2002, the result was that Taylor was not permitted to add Facility to the existing action against Warehouse Equipment. By that time, of course, the statute of limitations had run, so that Taylor would have been unable to file a timely new lawsuit against Facility. To avoid that result, the state court simultaneously granted Taylor leave to file such a separate action nunc pro tunc April 24, 2002— the date that the original motion to add Facility had been filed.

Because that nunc pro tunc order could perhaps be viewed as simply putting Taylor in the same position that he would have occupied on April 24, Facility claims that Taylor could stay within 'the statute of limitations only by filing his separate action within a day after the June 10 entry (on the ground that the April 25 expiration *891 date of the limitations period was just one day after the motion’s filing date of April 24). And because it appears that Taylor did not get his new Complaint against Facility on file until June 27, 3 Facility now seeks to assert that Taylor’s action is time-barred.

Summary judgment may be granted based on a statute of limitations defense if “(1) the statute of limitations has run, thereby barring the plaintiffs claim as a matter of law, and (2) there exist no genuine issues of material fact regarding the time at which the plaintiffs claim has accrued and the application of the statute to the plaintiffs claim which may be resolved in the plaintiffs favor” (Massey v. United States, 312 F.3d 272, 276 (7th Cir.2002), quoting earlier caselaw).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
360 F. Supp. 2d 887, 2005 U.S. Dist. LEXIS 4063, 2005 WL 580521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-v-facility-constructors-inc-ilnd-2005.