Taylor v. Burlington, C. R. & M. Ry. Co.

23 F. Cas. 737, 4 Dill. 570
U.S. Circuit Court for the District of Iowa·Decided May 15, 1877·Published·Cited by 3 cases

Opinion

DILLON, Circuit Judge.

In the various railway foreclosure cases in this court, there are probably forty intervening petitions filed seeking to establish, on behalf of the claimants, mechanic’s lien on the property covered by the railway mortgages. The trustees, in these mortgages, resist the right to any lien whatever, in many eases, and particularly resist the establishment of a mechanic’s lien in any case where the labor was done, or the materials were furnished, rfter the recording of the mortgage, which shall have priority over the mortgage. There are also questions as to the lien for repairs after the road has been completed, as distinguished from the right to a lien for original construction; and questions, also, as to limitation of the lien of the mechanic.

The most important of these questions are presented in the case of Wells, French & Co., and that has, therefore, been selected as the one in which to state the conclusions at which the court has arrived. In many respects nothing is more unlike than the erection of an ordinary building and the construction and equipment of a line of railway, and much of the difficulty in construing the legislation of the state has arisen out of the grouping of the two by the leg[739]*739islature and making an uniform or single provision for both. The duty of the court is to feel its way to the legislative intent and give that intent effect as far as it may. Wherever the statute has been construed by the supreme court of the state, that construction will be accepted as a rule of decision by this court. While we have considered every decision of the state supreme court which bears upon the questions before us, and also the full and exhaustive discussions of counsel, it is not proposed to go into an elaborate exposition of the different provisions of the statute, but mainly to state the results to which our examination has brought us.

The mechanic’s lien statute (Code, §§ 2130, 2132) extends, inter alia, to all persons “who construct or repair any work of internal improvement,” including railways, and gives a lien “for labor done, or materials, machinery, or fixtures furnished,” upon “such building, erection, or improvement, and upon the land belonging to the owner, on which the same is situated.” Section 2130.

Another section provides for the filing of the claim with the county clerk within ninety days after the work is done, and declares what shall be the effect of a failure to file. Section 2137.

Section 2139 first provides for the priority of mechanics’ liens as among themselves, making the same depend upon the order of filing, and then proceeds to exact that such liens “shall be preferred to all other liens and incumbrances which may be attached to or upon such building, erection, or other improvement, and to the land on which the same is situated, or either of them, made subsequent to the commencement of said building, erection, or improvement.” The lien extends to the entire land to the extent of the interest of the person for whom the mechanic did the work or furnished materials, and to a leasehold interest, as to which the provision is that the forfeiture of the lease shall not impair the mechanic’s lien as to the buildings, but the same may be sold to satisfy the lien and be moved off within thirty days after the sale. Section 2140.

Section 2141 provides for still another case in these words: “The lien for the things aforesaid, or work, shall attach to the buildings, erection, or improvements for which they were furnished or done, in preference to any prior lien, or incumbrance, or mortgage upon the land upon which the same is erected or put, and any person enforcing such lien, may have such building, erection, or other improvement sold under execution, and the purchaser may remove the same within a reasonable time thereafter.” The suit to enforce a mechanic’s lien must be in e'quity. Section 2510.

We hold as follows:

1.Section 2139 contemplates and provides for a case where, at the time of the commencement of the building or railway, there is no recorded lien or incumbrance thereon, and where such lien or incumbrance is created subsequent to the commencement of the building or railway; in which case the mechanic has a lien which relates back to the commencement of the building or railway, although the particular work of that mechanic was done, or his materials were furnished, after a mortgage was recorded, or lien created.

As to an ordinary building, the proposition just stated admits of no doubt; indeed, it has been expressly decided to be correct by the supreme court of the United States, in respect of an enactment copied from the Iowa statute. Davis v. Bisland, 18 Wall. [85 U. S.] 659.

As to the application of this principle to railways, the decision of the supreme court of Iowa is conclusive. Neilson v. Iowa Eastern R. Co. (Sept, term, 1870) 44 Iowa, 71.

Construing section 1853 (the same as section 2139 of the Code of 1873), it was decided, in the case last cited, that the lien of the mechanic dates from the commencement of the railway, treating it as an entirety, and has priority over a mortgage executed after the work of constructing some portion of the railway has been commenced, and before the particular work was done, or materials furnished, for which the mechanic’s lien is claimed.

2. Section 2141 makes provision for a still different case. This section contemplates and provides for a case where there is ». mortgage, lien, or incumbrance upon the land prior to the time when the owner commences “a building, erection, or other improvement thereon.” What, then, are the relative rights of such prior incumbrancers and the mechanic? This is plainly determined by the section itself. As to the lana, the mortgage is declared to retain its priority; but as to the buildings, erections, or improvements put upon the land subsequent to the mortgage, the mechanic has priority over the mortgage — may enforce his lien accordingly, and have the building, erection, or improvement sold on execution, and remove the same within a reasonable time.

The mechanic has, in such a case, the same right as against the mortgagee that he has as against the lessor under the preceding section.

This view, to the extent just stated, is in accordance with the decision of the supreme court of the state in Getchell v. Allen, 34 Iowa, 559, which case, so far as it relates to an “independent erection on the land,” is undoubtedly correct, and is approved, at least to this extent, by the same court in the subsequent case of Neilson v. Iowa Eastern R. Co., supra.

3. But suppose the prior mortgage attaches not only to land, but to a completed house, or other erection or improvement thereon, and the house or other improvement is re[740]*740paired by the mechanic, at the instance of the owner — what, then, are the relative rights of the mortgagee and the mechanic? This was the question which gave so much trouble to the state supreme court, as will be seen by reference to Getchell v. Allen, and the first opinion of that court in the Neilson Case. Under section 2130, undoubtedly the mechanic has a lien for repairs to a building erected and completed before the repairs were begun. That section uses the word “repairs.” and reparations by a mechanic are within the remedial purpose of the legislature. But when does such a lien attach, and how is it to be enforced? As against the owner, the lien attaches from the time the repairs are begun. This is plain enough, and just.

Free access — add to your briefcase to read the full text and ask questions with AI

Taylor v. Burlington, C. R. & M. Ry. Co., 23 F. Cas. 737, 4 Dill. 570 (circtdia 1877).

23 F. Cas. 737 (Taylor v. Burlington, C. R. & M. Ry. Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Colonial Trust Co. v. Vale-Oregon Irr. Co.
265 F. 393 (D. Oregon, 1920)
Greenwood, A. & W. Ry. v. Strang
77 F. 498 (U.S. Circuit Court for the District of South Carolina, 1896)
James River Lumber Co. v. Danner
57 N.W. 343 (North Dakota Supreme Court, 1893)