Taylor Morrison of Colo., Inc. v. Bemas Constr., Inc.

411 P.3d 72
CourtColorado Court of Appeals
DecidedJanuary 30, 2014
DocketCourt of Appeals No. 12CA2428
StatusPublished
Cited by3 cases

This text of 411 P.3d 72 (Taylor Morrison of Colo., Inc. v. Bemas Constr., Inc.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor Morrison of Colo., Inc. v. Bemas Constr., Inc., 411 P.3d 72 (Colo. Ct. App. 2014).

Opinion

Opinion by JUDGE GABRIEL

¶ 1 In this construction defect case, plaintiff, Taylor Morrison of Colorado, Inc. f/k/a Morrison Homes of Colorado, Inc. (Taylor), appeals (1) the trial court's order dismissing Taylor's claims against defendant, Terracon Consultants, Inc., with prejudice; and (2) the jury verdict in favor of defendant, Bemas Construction, Inc. As an apparent matter of first impression, we conclude that applying the Homeowner Protection Act of 2007, § 13-20-806(7), C.R.S.2013 (HPA), to invalidate the limitation of liability clauses in Taylor's contracts with Terracon would be unconstitutionally retrospective. We also conclude, however, that further proceedings are necessary to determine whether Taylor should have been permitted to introduce evidence of Terracon's willful and wanton conduct to attempt to overcome Terracon's assertion of the limitation of liability clauses.

*75Finally, we reject Taylor's argument that if it is ultimately entitled to a new trial against Terracon, then it is also entitled to a new trial against Bemas.

¶ 2 Accordingly, we affirm the judgment in favor of Bemas and remand the case for further proceedings concerning Terracon.

I. Background

¶ 3 Taylor was the developer of a residential subdivision known as Homestead Hills (the Project). Pursuant to written contracts with Taylor, Terracon performed certain geotechnical engineering and construction materials testing services at the Project. In addition, Taylor engaged Bemas to perform site grading, including overlot and subexcavation work.

¶ 4 After many of the homes were constructed, Taylor began receiving complaints from homeowners about cracks in the drywall of their homes. Taylor investigated these complaints and incurred significant expense to remedy the defective conditions that it found. It then sued Terracon and Bemas for, among other things, breach of contract and negligence, seeking to recover the expenses that it incurred in conducting its investigation and in making the necessary repairs.

¶ 5 Ten months after the court's deadline to amend pleadings, Taylor moved for leave to amend its complaint to add claims against Terracon for gross negligence, negligent misrepresentation, and fraudulent misrepresentation/ concealment, as well as a demand for exemplary damages. These proffered claims were based on, among other things, allegations that Terracon had willfully and wantonly breached duties to Taylor when it purportedly ignored or concealed inadequate subsurface soils conditions at the Project. The trial court, however, denied Taylor's motion to amend, concluding that (1) the motion was untimely, (2) Taylor had not established good cause for its delay in seeking to amend its complaint, and (3) Terracon would be unduly prejudiced were the court to grant the motion because the new claims would "significantly alter the basic thrust of the relief [Taylor] seeks" and would effect "a drastic change in the character of the case and Terracon's potential exposure to exemplary damages."

¶ 6 In addition to the foregoing motion for leave to amend, Taylor filed a motion pursuant to C.R.C.P. 56(h), asking the trial court to determine whether the HPA invalidated the limitation of liability clauses in its contracts with Terracon. Terracon responded that the HPA applies only to protect residential property owners, not commercial entities like those at issue here. Alternatively, Terracon asserted that the HPA does not apply retroactively to contracts executed and performed prior to its enactment and that applying the HPA retroactively to void Terracon's limitation of liability clauses would be unconstitutionally retrospective. The trial court agreed with Terracon's primary argument and concluded that the HPA did not invalidate the limitation of liability clauses at issue because it applies to protect only residential property owners and not commercial entities.

¶ 7 Thereafter, Terracon moved for leave to deposit into the court's registry $550,000, representing the maximum amount that Taylor could recover from Terracon under the contractual limitation of liability clauses and the above-described court order. In addition, Terracon asserted that upon the court's acceptance of Terracon's deposit, the court should declare Taylor's claims against Terracon moot and should dismiss those claims with prejudice.

¶ 8 Taylor opposed Terracon's motion, arguing, as pertinent here, that Terracon's willful and wanton conduct was not subject to any contractual limitation of liability. Taylor further asserted that its expert reports established such willful and wanton conduct.

¶ 9 The trial court ruled in favor of Terracon, noting that Taylor's operative complaint did not allege or seek to recover exemplary damages for willful and wanton conduct. The court thus authorized Terracon to deposit the $550,000 liability limit into the court's registry. Once Terracon did so, the court found that all of Taylor's claims against Terracon were moot and dismissed those claims with prejudice.

¶ 10 Taylor then proceeded to trial against Bemas. At trial, the parties agreed that *76Terracon was responsible for soils testing at the Project and that Terracon, at the very least, had made mistakes on the Project. The parties disputed, however, whether Bemas bore any responsibility for these mistakes. Taylor argued that (1) Bemas had continued its work at certain sites knowing that Terracon had not properly inspected the soils at those sites, and (2) Bemas was therefore responsible for damages resulting from its work at those sites. Bemas, in contrast, argued that Taylor had not shown that Bemas proceeded without first receiving Terracon's field tests.

¶ 11 Ultimately, the jury returned a verdict in Bemas's favor on all of Taylor's claims against it.

¶ 12 Taylor now appeals.

II. The HPA

¶ 13 The HPA provides, in pertinent part:

In order to preserve Colorado residential property owners' legal rights and remedies, in any civil action or arbitration proceeding described in section 13-20-802.5(1), any express waiver of, or limitation on, the legal rights, remedies, or damages provided by the "Construction Defect Action Reform Act" ... [is] void as against public policy.

§ 13-20-806(7)(a).

¶ 14 Taylor contends that the trial court erred in ruling that this provision did not invalidate the limitation of liability clauses in Taylor's contract with Terracon. We agree with the district court that the HPA did not invalidate the limitation of liability clauses, but we reach this conclusion for reasons different from those employed by the trial court. See Premier Members Fed. Credit Union v. Block, 2013 COA 128, ¶ 9, 312 P.3d 276, 278 ("We may affirm a trial court's ruling on any ground that is supported by the record.").

¶ 15 Specifically, the trial court agreed with Terracon and stated that the HPA applies only to protect residential property owners, not commercial entities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
411 P.3d 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-morrison-of-colo-inc-v-bemas-constr-inc-coloctapp-2014.