Taxi Service Co. v. Gulf Refining Co.

252 Mass. 314
CourtMassachusetts Supreme Judicial Court
DecidedMay 20, 1925
StatusPublished
Cited by11 cases

This text of 252 Mass. 314 (Taxi Service Co. v. Gulf Refining Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taxi Service Co. v. Gulf Refining Co., 252 Mass. 314 (Mass. 1925).

Opinion

Sanderson, J.

The plaintiff in this action seeks to recover damages for breach of a contract for the purchase and sale of gasoline. The first count is based upon a written contract; and the second upon the same contract with a [317]*317waiver or modification of some of its terms. The answer is a general denial and an allegation of performance by the defendant.

The contract provided that the defendant was to sell and deliver and the plaintiff to purchase and receive gasoline for use in its plant at 51 Lansdowne Street, Boston. The terms were in part as follows: “quantity — Gallons maximum 500,000 gallons minimum 500,000;” “delivery — By Tank Car in lots of not less than One tank car nor more than One tank car unless otherwise agreed upon. Deliveries to be in approximately equal monthly quantities ”; ‘' time— Between April 21-1915 and April 21-1916 Five days’ written notice to be given representative of first party [the defendant] at 185 Devonshire- St. Boston-Mass. before each shipment is required.” The contract was dated April 21, 1915, to become effective only when approved by the defendant’s sales manager. The approval required was given at a later date.

John H. McCarthy, the only witness called in the case, testified in substance that he was president of the plaintiff company during the entire period covered by the contract in question; the gasoline was ordered by the plaintiff and deliveries made by the defendant in accordance with the' orders, and a tank car averages about eighty-one hundred gallons; that there was a difference of twelve and three fourths cents a gallon between the contract price and the market price of gasoline at the date of expiration of the contract; and the storage capacity of the plaintiff’s plant was about ten thousand gallons; that he could not estimate the average daily use of gasoline but that it was ordered as fast .as it was consumed; that the defendant’s district sales manager asked him if the Clearing House Parcel Company still came in for gasoline and when told that it did, said, “That is good.” He testified on cross-examination that the defendant’s district sales manager told him the provision in the contract for “approximate equal monthly quantities” was for the protection of the defendant and that the gasoline could not be ordered in the last month, saying: “You might make a contract with me for half a million gallons of gasoline, and go on during the year buying it from anybody [318]*318and everybody if they gave you a lower price, and come on to me the last week of the term here and demand the half million gallons, and I could not give it to you.”

The first delivery of gasoline was on April 24, 1915, and the last on April 22,1916, the day after the expiration of the contract according to its terms. The total amount delivered was four hundred and four thousand, one hundred and forty-seven gallons, and the plaintiff is seeking damages for the defendant’s refusal to deliver the balance of the five hundred thousand called for by the contract. Assuming that the months should be held to run from the twenty-first of one month to the twenty-first of the next, the total amount delivered at the end of the eleventh month was about three hundred and sixty-two thousand gallons. In no month during that period except one had the plaintiff ordered as much as one twelfth of five hundred thousand gallons. Except for the conversation hereinbefore stated, the date of which did not appear, neither party mentioned the fact that the amounts being delivered were substantially less than one twelfth of five hundred thousand gallons.

Between March 18, 1916, and April 17, 1916, the defendant in letters to the plaintiff stated that the plaintiff was entitled to forty-one thousand six hundred and sixty-seven gallons during the last month the contract was in force; that on April 13 there was a balance due the plaintiff of one thousand two hundred and three gallons; that the defendant had been willing to furnish the plaintiff with the full monthly quota due under the contract for use in its plant; and that the contract never contemplated the entry by the plaintiff into the wholesale business. During the same period the plaintiff wrote that it assumed the defendant would send gasoline as the plaintiff ordered it under the contract; that the minimum purchased was five hundred thousand gallons, and the provision for approximately equal monthly deliveries was for the accommodation of the parties only and did not in any way require a regular amount per month; that it would hold the defendant responsible for any failure to furnish the entire five hundred thousand gallons purchased if the plaintiff ordered them; and that it would [319]*319accept deliveries in tank wagons. On April 14 the plaintiff requested the defendant to ship the balance due under the contract, stating that it had arranged for storage and that the defendant might if more convenient ship two cars a week.

It must be assumed that all issues of fact have been decided in the plaintiff’s favor; and the exceptions must be overruled unless there was error in refusing to allow the defendant’s motion for a directed verdict or in refusing to grant one or more of his requests numbered nine, ten and eleven. The question in request numbered one for a ruling upon the whole evidence is more properly raised by the motion for a directed verdict; and request numbered twelve is not substantially different .from that numbered eleven. No questions can be considered except those raised and passed upon by rulings in the trial court. Bond v. Bond, 7 Allen, 1, 6. The motion for a directed verdict, being general, was properly denied if the case should have been submitted to the jury on either count. Kearns v. South Middlesex Street Railway, 181 Mass. 587.

The balance of gasoline which by admission of the defendant in its letter was due under the contract was not delivered until the day after the contract had expired. The defendant contends that on April 14,1916, when the plaintiff demanded the balance due under the contract, no gasoline was due except this balance of the last month’s quota, which was delivered April 22. The question whether the plaintiff, by ordering less than it was entitled to in any month, waived its right to require gasoline to make up for this deficiency in a later month, was not set up in the answer and is not raised by the bill of exceptions except as it may be included in the motion for a directed verdict and in the request for a ruling that the damages assessed must be nominal. The questions of waiver and modification of the terms of a contract are to be left to the jury to decide when they depend upon a series of transactions in which the significance of the conduct of parties is to be interpreted and their intention as indicated by their acts or words is to be determined. Fox v. Harding, 7 Cush. 516. West v. Platt, 120 Mass. 421, 423. National Coal Tar Co. v. Malden & Melrose Gas Light Co. 189 Mass. [320]*320234. National Contracting Co. v. Vulcanite Portland Cement Co. 192 Mass. 247. O’Brien v. Peck, 198 Mass. 50. Glines v. Berry Box & Package Co. Inc. 248 Mass. 518. Parties may waive the right to treat the nonperformance in the original time as a breach. Tyers v. Rosedale & Ferryhill Iron Co. Ltd. L. R. 10 Ex. 195. Thomson v. Poor, 147 N. Y. 402.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cumberland Farms, Inc. v. Marchese
12 Mass. L. Rptr. 436 (Massachusetts Superior Court, 2000)
Urbinati v. Simplex Wire & Cable Co.
409 N.E.2d 243 (Massachusetts Appeals Court, 1980)
A. Leo Nash Steel Corp. v. Southern New England Steel Erection Co.
402 N.E.2d 71 (Massachusetts Appeals Court, 1980)
Lee v. Connolly Buick Co.
55 Mass. App. Dec. 72 (Mass. Dist. Ct., App. Div., 1974)
Silva v. Stamatos
54 Mass. App. Dec. 55 (Mass. Dist. Ct., App. Div., 1974)
Aerostatic Engineering Corp. v. Szczawinski
294 N.E.2d 521 (Massachusetts Appeals Court, 1973)
Masse v. Smitherman Cotton Mills, Inc.
9 Mass. App. Dec. 31 (Mass. Dist. Ct., App. Div., 1955)
Hurwitz v. Lakson
6 Mass. App. Div. 350 (Mass. Dist. Ct., App. Div., 1941)
William C. Atwater & Co. v. Terminal Coal Corp.
32 F. Supp. 178 (D. Massachusetts, 1940)
Commonwealth v. Brown
20 N.E.2d 478 (Massachusetts Supreme Judicial Court, 1939)
H. D. Watts Co. v. American Bond & Mortgage Co.
166 N.E. 713 (Massachusetts Supreme Judicial Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
252 Mass. 314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taxi-service-co-v-gulf-refining-co-mass-1925.