Taub v. Woodruff

134 S.W. 750, 63 Tex. Civ. App. 437, 1910 Tex. App. LEXIS 126
CourtCourt of Appeals of Texas
DecidedDecember 22, 1910
StatusPublished

This text of 134 S.W. 750 (Taub v. Woodruff) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taub v. Woodruff, 134 S.W. 750, 63 Tex. Civ. App. 437, 1910 Tex. App. LEXIS 126 (Tex. Ct. App. 1910).

Opinion

PLEASANTS, Chief Justice.

This suit was brought by appellee ■against appellant to recover a balance alleged to be due upon a contract for the construction by appellee of a dwelling house for the appellant, and to recover certain items of special damage alleged to have been sustained by appellee by reason of acts and omissions on the part of appellant in the performance of said contract.

The petition alleges that thete was a balance due plaintiff on the ■contract price of the work, including amount due for extra work as provided in said contract, of $2980.60, and that in addition thereto defendant is liable to plaintiff in the sum of $850 on account of delay and extra expense caused plaintiff in the performance of his contract by reason of the delay of defendant in furnishing plans and specifications for the work, and the errors and mistakes in the plans and specifications furnished, and the failure of the defendant to pay for certain hardware which, under the agreement between the parties, the defendant was required to furnish and for which plaintiff was forced to pay. The several items of damage which went to make up the sum of $850 were alleged.

The defendant answered by general denial, and by special pleas claiming credit for various amounts paid plaintiff and paid for material which, under the contract, plaintiff was required to furnish; and also for amounts averred to be the difference in value between material furnished by the plaintiff and materials which he was required to furnish" under the terms of the contract. He also pleaded that the contract provided that plaintiff should pay to the defendant the sum of, $3.50 per day for each day that the building remained unfinished after the date specified in the contract for its completion, and that the building had remained unfinished for 205 days after said date, and defendant was therefore entitled to recover of plaintiff on account of such delay the sum of $717.50. He further pleaded:

“Defendant further shows to the court that the contract sued on herein by the plaintiff contains the following provisions: ‘Art. Y. Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architect, the owner shall be at liberty, after three (3) days’ written notice to the contractor, to provide any such labor and materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the work, and to enter upon the premises and take pos *439 session, for the purpose of completing the work comprehended under this contract, of all materials, tools and appliances thereon, and to employ any ether person or persons to finish the work and to provide materials therefor; and. in case of such discontinuance of the employment of the contractor, he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor; but if such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the architects, whose certificate thereon shall be conclusive upon the parties.’

“Defendant further shows to the court that the plaintiff neglected to supply a sufficiency of properly skilled workmen, and failed in all respects to prosecute the work with promptness and diligence, which neglect and failure was certified to defendant by the architect, and defendant gave written notice thereof to plaintiff, and said architect certified to defendant that such neglect and failure on the part of the plaintiff was sufficient ground to authorize defendant to terminate the employment of the plaintiff for the said work.

“Defendant further shows to the court that thereafter, towit, about the 7th day of June, 1906, plaintiff, of his own motion, discontinued work under said contract and notified defendant and his architect that he would not do anything further under said contract, claiming that he had completed said building in accordance with said contract.

“Defendant further shows to the court that at the time of the abandonment of the work upon said building by the plaintiff, the same had not been completed in the manner required by the contract sued on herein, and thereupon defendant was compelled to employ and did employ workmen and purchase materials for the finishing and completion of said building in the mannep provided for by the contract sued on herein, at a necessary expense to defendant in the sum of. one thousand and fifty-nine and 11/100 dollars ($1059.11), which expense was audited and certified by the architect and paid by the defendant.”

He further pleaded limitation against plaintiff’s claim for the $850 before mentioned.

In reply to defendant’s answer plaintiff filed a supplemental petition alleging fraud and collusion on the part of the defendant and his architect in the certificates by the architect as to plaintiff’s failure to comply with his contract, and the certificates as to the amounts necessarily expended by defendant in completing the building.

The cause was tried with a jury, and a verdict and judgment was rendered in favor of plaintiff for the sum of $2923.

On motion for new trial filed by the defendant, plaintiff remitted *440 $328.93 of this amount, and thereupon the trial judge overruled the motion.

Having concluded that the judgment of the court below should be reversed because of errors committed upon the trial, we shall only discuss the assignments of error which we think should be sustained, and those which present questions upon which, in view of another trial, we think it best to express our views, and will not state the facts shown by the evidence further than is necessary to understand the questions presented by the assignments discussed in this opinion.

The defendant requested the trial court to instruct the jury to return a verdict in his favor as to all of the items making up the sum of $850, damages claimed by plaintiff before mentioned, on the ground that plaintiff’s right to recover each and all of said items was barred by the statute of limitation at the time plaintiff filed his amended petition in which for the first time he asserted the right to recover said damages.

The record shows that these items of damage accrued more than two years before the filing of the amended petition and that no claim was made therefor in the original petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
134 S.W. 750, 63 Tex. Civ. App. 437, 1910 Tex. App. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taub-v-woodruff-texapp-1910.