Tate v. Pollution Control Board

544 N.E.2d 1176, 188 Ill. App. 3d 994, 136 Ill. Dec. 401, 1989 Ill. App. LEXIS 1494
CourtAppellate Court of Illinois
DecidedSeptember 28, 1989
Docket4-89-0061
StatusPublished
Cited by27 cases

This text of 544 N.E.2d 1176 (Tate v. Pollution Control Board) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tate v. Pollution Control Board, 544 N.E.2d 1176, 188 Ill. App. 3d 994, 136 Ill. Dec. 401, 1989 Ill. App. LEXIS 1494 (Ill. Ct. App. 1989).

Opinion

JUSTICE SPITZ

delivered the opinion of the court:

Roger Tate, Lynette Tate, Barbara Kelley, and Joseph Kelley (petitioners), have filed a petition for direct review in the appellate court of a final administrative order of the Illinois Pollution Control Board (IPCB) entered on December 15, 1988, affirming the decision of the Macon County Board (County Board) which granted site-location suitability approval to the Macon County Landfill Corporation (MCL) to expand an existing landfill, with conditions, pursuant to section 39.2 of the Environmental Protection Act (Act) (Ill. Rev. Stat. 1987, ch. 111½, par. 1039.2). MCL filed an initial request on November 9, 1987, and an amended request for site approval for the extension of an existing landfill with the County Board on January 14, 1988. The amended request comprises three pages with two exhibits, one being a legal description and the second being the notice provided to local residents. The request asks permission to extend MCL’s existing landfill facility. This application was later clarified to be a request to accept nonhazardous special waste and to increase the design height of the landfill. No other documents were filed with the request, even though MCL had previously submitted to the Illinois Environmental Protection Agency (IEPA) applications and related documents pertaining to the issuance of a developmental permit to handle nonspecial waste on the expanded site. An operating permit had not yet been issued. In addition, MCL filed an amended petition altering the original petition only insofar as the acreage requested to be approved for the expanded facility was reduced from 42 acres to 25 acres. The amended petition makes brief affirmative assertions regarding each of the six statutory siting criteria, and asserts that, because MCL has filed no request or related documents with the IEPA regarding the application, no other documents are submitted.

The seven-member committee (Committee) of the County Board conducted hearings on April 21 and 22, May 5, 12, 18, and 19, and June 2, 1988. The Committee also took a formal 40-minute tour of the MCL site on May 24, 1988, accompanied by Roger Tate, and Paul McKinney, the site operator. Final arguments were presented on the last hearing day, June 2, 1988. Thereafter, the Committee met on June 9, June 16, June 23, June 30, and July 6, 1988, to deliberate. On July 6, 1988, the Committee voted unanimously to recommend approval. The approval included five numbered conditions and one narrative condition.

On July 12, 1988, the County Board, by resolution, concurred in the Committee’s recommendation that MCL be permitted to accept special nonhazardous waste and to increase the design height of the landfill 40 feet, subject to the following conditions: (1) an increase in the number (from three to nine) and depth of the monitoring wells; (2) a 10-foot clay liner compacted to “a 10 to the minus 7” be placed under and on the sides of the proposed landfill, noting that the present site has no liner; (3) relocation of a gas pipeline and vacation of the present easement; (4) removal of the existing pipeline; and (5) the entire landfill area be out of the flood plain or be flood proofed. The County Board resolution also contained a Committee recommendation that MCL be required “to develop and submit to the Macon County-Board for review, a ten-year plan for waste disposal, including a plan for two years.” The IPCB concluded that, as the resolution is drafted, this narrative recommendation also appears to be a condition.

The facility extension in question encompasses what is called sites 3 and 4. Site 4 encompasses only two acres of the expanded facility. Immediately east of site 3 is an existing active landfill operation of 25 acres, designated site 2. Site 2 has been in operation since 1971 and is permitted to take general and special waste. Further east, on the other side of site 2, is a closed 20-acre facility, site 1, originally opened in 1960.

To the west of sites 3 and 4 are about 30 acres of undeveloped pasture land owned by MCL. To the north, across Hill Road, are homes. To the south is the Sangamon River and, to the east of site 1, across the interstate, are the sludge pits of the Decatur Sanitary District.

At the Committee hearing there was some initial confusion as to what constituted a new regional pollution-control facility at the MCL site. In 1977, 1978, and 1979, MCL had applied for, and received, development permits and supplemental development permits for sites 3. and 4. These development permits allow disposal of general, municipal, solid waste, not special waste, and limit the height of the landfill to 40 feet below what is now requested.

Less than a month after filing the amended application to extend the facility, on February 9, 1988, MCL notified the County Board that it had discovered the statute creating the procedure for approval of new regional pollution-control facilities had a “grandfather clause,” which exempted from the process those facilities which earlier had been issued development permits. The letter sent to the County Board on behalf of MCL states that MCL is “only requesting approval to fill the unpermitted area with nonhazardous special waste and/or liquid waste, and to increase the permitted elevation of this site so as to be the same as the adjoining landfill.” (See Ill. Rev. Stat. 1987, ch. 111½, par. 1003.32.) The letter stated that it hoped to proceed on the existing amended petition with the understanding that MCL was only requesting approval for variance from the existing development permits. In correspondence dated April 14, 1988, addressed to the County Board, petitioners challenged MCL’s February 9, 1988, correspondence and complained that the material change in the location of the site, as well as the other amendment, presented jurisdictional problems such that MCL should be required to withdraw the request and issue new notices.

At the hearing on April 21, 1988, petitioners also asked MCL to disclose technical exhibits. MCL refused to do so. At the hearing on May 5, 1988, MCL submitted to the County Board the technical documents previously submitted to the IEPA. These documents, variously dated September 1977 to October 7, 1979, include descriptions of site characteristics, including hydrology and geology, site development plans; operating plans and procedures; permeability testing results and construction proposals to contain leachate; and the application to the County Board to permit the development of the site submitted in August 1979, with the attachments thereto. When MCL produced the exhibits at the May 5, 1988, hearing, petitioners objected and moved to dismiss the proceedings on the ground that the failure to file the documents with the request for site approval made to the County Board constituted a jurisdictional defect under section 39.2(c) of the Act. (Ill. Rev. Stat. 1987, ch. 111½, par. 1039.2(c).) This issue was also raised before the IPCB, and it was rejected. However, it is precisely on this point that three members of the IPCB dissented, suggesting that the failure to include this information with the request is a violation of fundamental fairness.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re M.S.
2026 IL App (4th) 251081-U (Appellate Court of Illinois, 2026)
In re E.L.
2026 IL App (4th) 251159-U (Appellate Court of Illinois, 2026)
In re: K.G.
2026 IL App (4th) 250996-U (Appellate Court of Illinois, 2026)
In re: Autumn S.
2025 IL App (5th) 250040-U (Appellate Court of Illinois, 2025)
In re Ka.F.
2023 IL App (4th) 230496-U (Appellate Court of Illinois, 2023)
The Carle Foundation v. Department of Revenue
2023 IL App (4th) 200121 (Appellate Court of Illinois, 2023)
In re B.E.
2023 IL App (4th) 230075-U (Appellate Court of Illinois, 2023)
In re Tal. B.
2023 IL App (4th) 221082-U (Appellate Court of Illinois, 2023)
In re L.S.
2023 IL App (4th) 220757-U (Appellate Court of Illinois, 2023)
Will County v. Village of Rockdale
2018 IL App (3d) 160463 (Appellate Court of Illinois, 2018)
Fox Moraine v. United City of Yorkville
960 N.E.2d 1144 (Appellate Court of Illinois, 2011)
Fox Moraine, LLC v. United City of Yorkville
2011 IL App (2d) 100017 (Appellate Court of Illinois, 2011)
Town of Sugarloaf v. IEPA
Appellate Court of Illinois, 1999
Town of Sugar Loaf v. Environmental Protection Agency
712 N.E.2d 393 (Appellate Court of Illinois, 1999)
Concerned Adjoining Owners v. Pollution Control Board
680 N.E.2d 810 (Appellate Court of Illinois, 1997)
Board of Educ. of City of Chicago v. Weed
667 N.E.2d 627 (Appellate Court of Illinois, 1996)
Southwest Energy Corp. v. Pollution Control Board
655 N.E.2d 304 (Appellate Court of Illinois, 1995)
Daly v. Pollution Control Board
637 N.E.2d 1153 (Appellate Court of Illinois, 1994)
City of Elgin v. County of Cook
629 N.E.2d 86 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
544 N.E.2d 1176, 188 Ill. App. 3d 994, 136 Ill. Dec. 401, 1989 Ill. App. LEXIS 1494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tate-v-pollution-control-board-illappct-1989.