Tarleton State University v. K.A. Sparks Contractor, Inc.

695 S.W.2d 362, 27 Educ. L. Rep. 399, 1985 Tex. App. LEXIS 11956
CourtCourt of Appeals of Texas
DecidedAugust 8, 1985
Docket10-85-015-CV
StatusPublished
Cited by6 cases

This text of 695 S.W.2d 362 (Tarleton State University v. K.A. Sparks Contractor, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tarleton State University v. K.A. Sparks Contractor, Inc., 695 S.W.2d 362, 27 Educ. L. Rep. 399, 1985 Tex. App. LEXIS 11956 (Tex. Ct. App. 1985).

Opinion

OPINION

JAMES, Justice.

This appeal arises out of a contractual dispute between Appellant and Appellee over water damage to the gymnasium floor of the Physical Education Building at Tarleton State University. Plaintiff-Appellant Tarleton State University sued Defendant-Appellee K.A. Sparks Contractor, Inc. in contract and tort to recover the cost of repairing the damaged gymnasium floor plus pre-judgment interest and attorney’s fees. The contractor defended by general denial, and on the theories of comparative negligence, acts of God and unavoidable accident.

On or about April 5, 1976, the Board of Directors of the Texas A & M University System, acting on behalf of Tarleton State University, entered into a contract with K.A. Sparks Contractor, Inc. for the construction of Home Economics and Physical Education facilities at Tarleton State University. This work entailed an addition to the existing gymnasium facility on two of the four sides of the building. During the course of construction, specifically twice on May 25, 1976, and again on August 28, 1976, and on August 80, 1976, the wooden floor in the existing gymnasium was flooded from rain water. After the August 30, 1976, flooding, the wooden gymnasium floor started swelling and buckling from the accumulation of water to the point where the floor was beyond repair and required replacement.

After the flooding the parties entered into negotiations for the repair of the gym floor, as a result of which Change Order No. 1 to the original contract was negotiated. A Memorandum of Agreement was signed by the parties which specifically provided that neither party would waive its rights or remedies to recover under the original contract, and wherein the contractor agreed, to repair the gym floor for $46,259.52, for which the contractor was paid.

Plaintiff-Appellant Tarleton brought this suit against Defendant-Appellee contractor to recover the cost of the repair in the amount of $46,259.52, for interest and attorney’s fees.

The case was tried to a jury which found in answer to Special Issues as follows:

No. 1: that Sparks Contractor breached its contract by failing to protect the gymnasium from damage in the event of rain.
No. 2: which was a proximate cause of Plaintiff Tarleton’s damages.
No. 3: that Sparks Contractor breached its contract by failing to properly supervise the construction work to protect the gymnasium from rains.
No. If which was a proximate cause of Plaintiff Tarleton’s damages.
No. 5: $23,129.76 would fairly and adequately compensate Tarleton for damages as a result of breach of contract by Sparks Contractor.
No. 6: to compensate Tarleton for legal services rendered on its behalf by the Texas Attorney General’s office, the jury found zero dollars for trial of the case, zero dollars for appeal to the Court of Appeals, and zero dollars for writ of error to the Supreme Court of Texas.
No. 7A: that Sparks Contractor failed to adequately protect in advance the existing facility against rain, which failure was negligence and a proximate cause of the damages in question.
No. 7B: that Sparks Contractor failed to adequately and properly supervise the construction work being performed, which failure was negligence, and a proximate cause of the damages in question.
No. 7C: that Sparks Contractor failed to hire and appoint competent personnel to oversee its construction work, which failure was negligence and a proximate cause of the damages in question.
*365 No. 8: $23,129.76 would reasonably compensate Tarleton for the actual damages it has suffered.
No. 9: Tarleton failed to adequately and timely inspect the gymnasium as a person of ordinary care would have done so as to prevent damage to the building in the event of rains.
No. 10: which was a proximate cause of Plaintiff Tarleton’s damages in question.
No. 11: Tarleton failed to adequately maintain the condition of the gymnasium as a person of ordinary care would have done to prevent damage to the building in the event of rains.
No. 12: which was a proximate cause of Plaintiff Tarleton’s damages in question.
No. 13: Tarleton, acting through its agents, servants, and employees, failed to warn Sparks Contractor that the condition and placement of the pipes in the gymnasium would allow water to enter onto the gymnasium floor in the event of rains.
No. 1⅛: which failure was a proximate cause of Plaintiff Tarleton’s damages in question.
No. 15: 50% of the negligence that caused the damage to the gym floor was attributed to Plaintiff Tarleton, and 50% of the negligence was attributed to Defendant Sparks.

After verdict, both Plaintiff and Defendant filed motions to disregard the jury’s answers to special issues and motions for judgment notwithstanding the verdict, all of which were denied by the trial court.

Judgment was entered in favor of Plaintiff Tarleton State University against Defendant K.A. Sparks Contractor, Inc. in the amount of $23,129.76 plus $11,102.28 prejudgment interest, or a total amount of $34,232.04 plus costs, from which Plaintiff Tarleton appeals on eight points of error. Appellee Sparks files six cross-points of error. We overrule all of Appellant’s points of error and all of Appellee’s cross-points and affirm the trial court’s judgment.

Appellant’s points one, two, and three assert the trial court erred in submitting Special Issue No. 5 because (Appellant says) the amount of breach of contract damages was established as a matter of law at $46,259.52; Appellant further asserts that there is no evidence to support the jury’s answer of $23,129.76. We do not agree.

We will treat these points as asserting the evidence conclusively establishes that the damages are $46,259.52, as opposed to a “no evidence” point, since Plaintiff-Appellant had the burden of proof. See O’Neil v. Mack Trucks, Inc., (Tex.1976) 542 S.W.2d 112.

The damages sustained by Plaintiff as a result of water damage to the gymnasium floor were not established as a matter of law. There was conflicting evidence as to the cause of the damage thereby creating a fact issue for the jury, which found the damage at $23,129.76 or one-half of the cost of replacing the gym floor. As the Plaintiff-Appellant is entitled only to those damages caused by Defendant-Appellee’s breach, it is proper for the jury to determine under the evidence for what, if any, portion of Plaintiff-Appellant’s damages the Defendant-Appellee is responsible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garden Ridge, L.P. v. Clear Lake Center, L.P.
Court of Appeals of Texas, 2015
Petco Animal Supplies, Inc. v. Schuster
144 S.W.3d 554 (Court of Appeals of Texas, 2004)
Petco Animal Supplies, Inc. v. Carol Schuster
Court of Appeals of Texas, 2004
Brown v. Bank of Galveston, National Ass'n
930 S.W.2d 140 (Court of Appeals of Texas, 1996)
Mandell v. Hamman Oil and Refining Co.
822 S.W.2d 153 (Court of Appeals of Texas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
695 S.W.2d 362, 27 Educ. L. Rep. 399, 1985 Tex. App. LEXIS 11956, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tarleton-state-university-v-ka-sparks-contractor-inc-texapp-1985.