Tarkington Prairie Lodge, A. F. & A. M., No. 498 v. George W. Smyth Lumber Co.

214 S.W. 588
CourtCourt of Appeals of Texas
DecidedApril 26, 1919
DocketNo. 431.
StatusPublished
Cited by1 cases

This text of 214 S.W. 588 (Tarkington Prairie Lodge, A. F. & A. M., No. 498 v. George W. Smyth Lumber Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tarkington Prairie Lodge, A. F. & A. M., No. 498 v. George W. Smyth Lumber Co., 214 S.W. 588 (Tex. Ct. App. 1919).

Opinions

On August 12, 1916, one J. T. Key, a building contractor, entered into a written contract with Tarkington Prairie Lodge, A. F. A. M., No. 498, of Liberty county, Tex., the latter acting through its building committee, by the terms of which contract the said Key agreed and bound himself to erect in the town of Cleveland, in said county, a two-story building, to be constructed of brick and hollow tile, which building was desired for use as a Masonic lodge building by said lodge. This building was to be in accordance with certain plans and specifications agreed upon by the parties, and was to be completed within 90 days from the date of said contract. By the terms of the contract, Key was to furnish all material and labor necessary for the erection of the building, and he was to receive for the building complete the total consideration of $5,120. The contract further provided that, in the event the building was not completed within 90 days from the date of the contract, Key would pay to said lodge $10 per day per each working day after expiration of the 90 days and until said building should be completed. It was further provided in the contract that said lodge, *Page 589 through its building committee, should advance to Key sufficient funds to cover 80 per cent. of the cost of all material going into said building, and also 80 per cent. of the cost of all labor used in its construction, as the work progressed; but the contract stipulated that no further advances should be made to Key until said building should be completed by Key and accepted by the lodge. In other words, this provision of the contract was substantially to the effect that the lodge should retain 20 per cent. of the contract price of the building until Key should complete said building in accordance with his contract.

To secure performance of this contract by Key, he was required to and did execute a bond in the sum of $2,600, payable to the building committee, acting for said lodge, and the following named person signed said bond as Key's sureties, to wit: W. W. King, W. C. Arthur, J. W. Lewis, C. A Howard, T. B. Morgan, M. V. Whitfield, J. S. Meador, W. T. Jones, A. J. Hartel, and L Wilkinson. Key never completed or performed his contract for the erection of said building, after having entered upon performance of same, but refused to do so, and abandoned and left the building in an incompleted state. After Key abandoned and breached his contract, said lodge, acting through its building committee, notified the sureties on Key's bond to that effect, and requested them to complete the building according to Key's contract, which they refused to do. The lodge then, acting through its building committee, went ahead with the construction of said building according to plans and specifications in the contract, and completed the building at a necessary and reasonable expense to the lodge for material and labor of $1,710.60 over and above the contract price. Counting from the date when Key should have completed the building, it required the lodge 90 days to complete same, and such time was reasonably and necessarily required.

During the time Key was engaged in the erection of said building, and before he abandoned his contract, he purchased from the George W. Smyth Lumber Company, a manufacturer of lumber and building material, several items of material that went into the building, aggregating something over $1,300 in value, and at the time he abandoned the building Key owed George W. Smyth Lumber Company for said material a balance of $768.75, which balance has never been paid. The George W. Smyth Lumber Company, as plaintiff, brought this suit against the said Key, contractor, and also against the above-named sureties on his bond, to recover said balance, with interest thereon, and also made said lodge a party defendant, and sought recovery against it for said balance. Defendant Key made no answer to the suit, but said sureties on his bond as contractor all answered, and denied liability to George W. Smyth Lumber Company in any sum whatever. Said lodge also denied any liability to George W. Smyth Lumber Company.

Said lodge, by way of cross-action against Key and said sureties on his bond, sought to recover the amount which said lodge had expended over and above the contract price for said building, to wit, $1,710.60, and also sought to recover against them $900 as damages provided for in Key's contract for delay in the completion of said building. Key made no answer to the lodge's cross-action, but said sureties all answered thereto, and denied any liability to the lodge in any sum whatever.

The case was tried by the court without a jury, and resulted in a judgment in favor of the plaintiff, George W. Smyth Lumber Company, as against Key and said sureties on his bond, in the sum of $830.25, being the principal amount and interest thereon claimed by said plaintiff against said defendants; but as between said Smyth Lumber Company, plaintiff, and said lodge, it was decreed that said plaintiff take nothing. As to the cross-action by the lodge against Key and his said sureties, the court rendered judgment in favor of the lodge against Key for the sum of $2,878.73, which sum represents the amount which was found by the court to have been reasonably and necessarily expended by the lodge in completing said building, and which was in excess of the contract price for said building, and which also includes $900 awarded by the court as damages sustained by the lodge and provided for in the contract in consequence of Key's failure to complete the building within the time stipulated in the contract; but as to said sureties on Key's bond the court denied any recovery in favor of said Lodge.

From the judgment so rendered and entered, the sureties on Key's bond appealed from that part thereof allowing recovery against them in favor of the George W. Smyth Lumber Company, and said lodge appealed from that portion of the judgment denying it a recovery on its cross-action against said sureties on Key's bond. The trial court filed findings of fact and conclusions of law, and all such findings of fact, as far as they are material, are substantially stated above.

We shall first dispose of the contention made by King and others, sureties on Key's bond, complaining of the judgment against them in favor of the George W. Smyth Lumber Company. Their first assignment of error is as follows:

"The trial court erred in failing and refusing to sustain the general demurrer and general exception filed in said cause as to the petition of the plaintiff, George W. Smyth Lumber Company, because of the action of the defendant Tarkington Lodge in violating the terms of the contract for said building in paying to the *Page 590 contractor, J. T. Key, the full amount of the contract price, and in failing to hold back 20 per cent. of the contract price of said building as provided in said contract. The contract provided that said lodge should hold back 20 per cent. of the contract price until the building was completed, and the undisputed evidence shows that in violation of this provision of the contract said lodge paid Key the full contract price before said building was ever completed, and that this was done without the knowledge or consent of these defendant bondsmen; and the action of said lodge in so breaching said contract released these bondsmen of all liability to said lodge, not only to said lodge, but to the said plaintiff, George W. Smyth Lumber Company, and the court erred in failing and refusing to sustain the general demurrer and general exception of these defendant bondsmen to the petition and plea of the plaintiff, George W. Smyth Lumber Company, for the reason here set out, as more fully shown in their bill of exception No. 1, which is here referred to."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wright v. A. G. McAdams Lumber Co.
218 S.W. 571 (Court of Appeals of Texas, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
214 S.W. 588, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tarkington-prairie-lodge-a-f-a-m-no-498-v-george-w-smyth-lumber-texapp-1919.