Tampas Site Plan Application (Amend)

CourtVermont Superior Court
DecidedFebruary 13, 2009
Docket45-3-08 Vtec
StatusPublished

This text of Tampas Site Plan Application (Amend) (Tampas Site Plan Application (Amend)) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tampas Site Plan Application (Amend), (Vt. Ct. App. 2009).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} In re: Tampas, et al. } Docket No. 45-3-08 Vtec } }

Decision and Order on Cross-Motions for Summary Judgment

Appellant-Applicants (Appellants) John Tampas, Richard Hee, Donald Thomas,

Richard Bertolino, Chandler Nims, Steve Barclay, and Thomas Brennan appealed from a

decision of the Development Review Board (DRB) of the Town of Colchester, denying

site plan approval to an as-built stone-and-rip-rap berm on the shore of Lake

Champlain. Appellant-Applicants are represented by Thomas F. Heilmann, Esq.; the

Town of Colchester is represented by Thomas G. Walsh, Esq.

The parties have moved for summary judgment. At the request of the parties, a

site visit was taken by Judge Wright together with both attorneys, to provide an

illustration of and context for the materials and photographs submitted in connection

with the motions for summary judgment. The following facts are undisputed unless

otherwise noted.

Appellants each own property with frontage on Lake Champlain, on the

southwesterly shore of Colchester Point, in the Laurel Hill North development. The

developer was obligated by the 1969 Planning Commission’s approval of the

subdivision (carried out in the properties’ covenants obligating Appellants), to employ

“a suitable means of shore protection to insure that each lot has a useable depth of 150

feet during all water conditions.” Planning Commission Minutes, May 5, 1969,

Appellants’ Attach. 1. In approximately 1975, a 700-foot-long concrete seawall was

1 constructed on Appellants’ properties (the 1975 Concrete Seawall) to accomplish the

required shoreline protection.

The 1975 Concrete Seawall is approximately ten inches in thickness, and stands

with the top of the wall at elevation 104.5 feet above sea level, approximately nine feet

in height above the original lake bed elevation of 95.5 feet above sea level. The ground

level of Appellants’ properties is close to the elevation of the top of the wall; many of

those properties are fenced close to the top of the wall, due to the drop off.

The 1975 Concrete Seawall was built onto an approximately five-foot-wide

concrete footing, which is approximately one foot thick. Approximately a foot-and-a-

half of the footing extends lakeward of the lake side face of the wall. As originally

designed, a three-and-a-half foot mound of sand was to be placed in front (on the lake

side) of the base of the 1975 Concrete Seawall, entirely covering the footing and a

portion of the base. As of 2007, none of this material remained in place, due to erosion

by the action of the lake.

Over time, and particularly as a result of high winter and spring water levels in

Lake Champlain in the years just prior to 2007, the sand beach or lake floor on the lake

side face of the 1975 Concrete Seawall had eroded, increasing the likelihood of damage

to or partial collapse of the 1975 Concrete Seawall. A portion of the 1975 Concrete

Seawall had begun to bow outwards.

Appellants applied for and, on October 10, 2007, received approval1 from the

DRB for the placement of a stone block and rip-rap berm (the 2007 Berm) on the

lakeside face of the 1975 Concrete Seawall, to reinforce and protect the 1975 Concrete

Seawall. Such a berm is designed to reduce erosion by dissipating the energy of the

water and wave action, thereby protecting the 1975 Concrete Seawall.

1 The application was filed for and approved in two segments, one in front of three properties and the other in front of four properties. This decision will discuss the berm as a single 700-foot-long unit. 2 As approved (the approved design), the 2007 Berm was designed to consist of

large2 quarry blocks of stone set at a shallow 21° slope, from a point eight feet into the

lake beyond the base of the concrete footing, extending up to a height of 3½ feet

(elevation 99 feet above sea level) at the wall, infilled with smaller shot rock or rip-rap

material behind the quarry blocks (that is, in the area formed by the underneath surface

of the quarry blocks, the lake bed, and the 1975 Concrete Seawall). The approved

design would have resulted in a berm with an essentially triangular cross-section. See

Ex. C to Appellants’ Attach. 2.

There are only limited periods during the year when the lake level is low enough

to allow construction of projects such as this one. During construction of the project

during such a period in October of 2007, the engineer and contractor made field

changes to the project. The parties dispute facts as to the necessity for the field changes

to be completed without prior notice to the DRB and without prior application under

§ 8.05(I)(1)(b); these disputed facts may not be material, as discussed below.

As redesigned and constructed in the field (the as-built design), the berm

remained 3½ feet in height (elevation 99 feet above sea level) at the wall, and with the

lowest quarry block being set in the lake bed also at a point eight feet into the lake

beyond the base of the concrete footing. However, in the as-built design, the quarry

blocks were set at a steeper angle, resulting in a slope of about 70° and leaving an area

about five feet in width to be filled in with the shot rock rip-rap material. The as-built

design resulted in a berm that is essentially trapezoidal in cross section, with an

irregular horizontal surface of one-foot-diameter shot rock. See Ex. P to Appellants’

Attach. 2.

After the project’s certificate of compliance was denied due to the discrepancy

between the approved design and the as-built design, Appellant-Applicants applied for

2 Two feet by two feet by four feet in size. 3 approval of the as-built design on or about October 22, 2007 (the date of the as-built

engineering drawing).3 At some time during the proceedings, the DRB requested that

an alternative proposal be developed with a sloped rather than a horizontal upper

surface. That alternative design, dated December 17, 2007, adds a sloped surface of

quarry blocks at a slope of 30°, resulting in a berm angled up towards the lake side face,

with a maximum height of approximately 5.7 feet above the lake bed. Town’s Ex. 6.

Material facts are in dispute, or at least have not been provided to the Court, as to

whether Appellant-Applicants also applied, formally or informally, for this alternative

proposal, and therefore whether it is before the Court in this proceeding. The minutes4

of the January 23, 2008 DRB hearing state that Appellant-Applicants’ engineer “outlined

the work that would be done if the Board approves the revised drawings that have been

submitted that will provide a sloping surface that can’t serve as a landing of any type.”

As neither the application nor the DRB’s written decision has been provided, the Court

cannot determine whether both the as-built design and the alternative design are before

the Court for decision.

Discussion

It is important to keep in mind that all that is before the Court in the present

application and appeal is whether the as-built design (and possibly also the alternative

design, see preceding paragraph) should be approved. No Notice of Violation appeal

or enforcement action is before the Court in this proceeding that would relate to any

3 The parties have not provided the application, only the engineering drawing.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
Tampas Site Plan Application (Amend), Counsel Stack Legal Research, https://law.counselstack.com/opinion/tampas-site-plan-application-amend-vtsuperct-2009.