Tampa Shipbuilding & Engineering Co. v. General Const. Co.

43 F.2d 309, 85 A.L.R. 1178, 1930 U.S. App. LEXIS 3872
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 6, 1930
Docket5677
StatusPublished
Cited by8 cases

This text of 43 F.2d 309 (Tampa Shipbuilding & Engineering Co. v. General Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tampa Shipbuilding & Engineering Co. v. General Const. Co., 43 F.2d 309, 85 A.L.R. 1178, 1930 U.S. App. LEXIS 3872 (5th Cir. 1930).

Opinion

SIBLEY, District Judge.

Upon a suit at law for breach of contract to deliver certain base rock, the appellee recovered judgment against appellant for $28,-689.67. A new trial was refused, and this appeal taken. The assignments of error relate to the overruling of demurrers to the declaration, rulings on evidence, and the refusal of a new trial.

The declaration alleged that appellant agreed to sell and appellee to buy “a certain pile of base rock containing approximately 25,000 tons at a price of $1 per cubic yard,” which was not delivered, “and plaintiff alleges that it was necessary for it to expend in purchasing said rock to replace the rock covered by the contract with defendant, and which the defendant failed and refused to deliver, the sum of $59,290, thereby damaging the plaintiff in the sum of $29,754.56 as per bill of particulars hereto attached and made a part of the declaration.” The bill of partie--ulars shows $28,904.20 paid out for rock “for 22nd Street Causeway,” and $30,385.86 for freight and demurrage, making the total of $59,290.06, offset by contract price of $1 per ton on 29,535.5 tons, and leaving a balance of $29,754.56. The cause of action thus stated is that a particular pile of rock, containing about 25,000 tons was sold and not delivered. The damage would properly be measured by the number of tons actually in the pile, and by the excess over the contract price of the market price for such rock as that was. The declaration makes no allegation as to number of tons actually in the pile, estimated at 25,-000 at the time of the contract, and leaves to inference that that bought on the market was the same sort of rock. The bill of particulars indicates that 29,535.5 tons were bought and used in “22nd St. Causeway,” a fact really irrelevant to the’ cause of action above set forth.

There are exhibited, however, as constituting the contract declared on, four letters between the parties, the material parts of which follow: Letter from appellee to appellant dated November 2, 1925: “Order No. 643. * * * This will be your order for base rock for 22nd St. Causeway, the price for same to be $1 per cubic yard as measured in our trucks. We to load same. Rock to be delivered to us at your property between Flagler and Grant. Yia our trucks. Terms 30 days. Date wanted: as desired.” On November 9, 1925, appellant replied: “This letter acknowledges your order of Nov. 2, No. 643. With regards to rock for General Construction Company I am enclosing copy of the letter which I have written Mr. Kreiss. * * * _ Hoping that all is clear now,” etc. The inelosure to Kreiss shows that certain rock had also been sold to Kreiss, and stipulates to him “that the General Construction Company has priority for the rock needed for 22nd Street Bridge and Causeway.” Ap-pellee also wrote appellant under date of November 3d seeking assurance that the rock will not be sold to others until appellee gets “sufficient quantity for the base rock course of 22nd St. Causeway.” Appellant replied on November 10th by referring to its letter of November 9th, above quoted from, adding : “I have arranged priority for you with Mr. Kreiss and you kindly see that you get the rock you want.” These letters constitute a sufficient memorandum under the statute of frauds. Those signed by the appellant, who is the person sought to be charged, do not contain any of the terms of the contract, *311 but they refer specifically to the letters of the appellee which do contain them, thereby incorporating them. Appellants letter of November 9th only “acknowledges” instead of “accepting” the order of November 2d, but that acceptance was meant plainly appears from the absolute direction given Kreiss to give the order priority, and from the expression of hope that all is “clear” in concluding the letter of November 9th, and “satisfactory” in that of November 10th. The memorandum required by the statute may thus be supplied by papers explicitly referred to in that signed by the person sought to be charged. Salmon Falls Co. v. Goddard, 14 How. 447,14 L. Ed. 493; Ryan v. United States, 136 U. S. 68,10 S. Ct. 913, 34 L. Ed. 447. The contract made by the order of November 2d and its acceptance by the letter of November 9th, is clear and unambiguous. It sells no pile of rock of about 25,000 tons size, and mentions none. It sells sufficient rock for “22nd Street Causeway,” at the price and on the terms stated in the order. Under this contract appellant was bound to deliver and appellee to buy what was required for that causeway, whether appellant had it on hand or not. The amotat in the pile was immaterial. A contract for one’s needs for a particular enterprise is sufficiently definite, and is not unilateral. Mc-Caw Mfg. Co. v. Felder, 115 Ga. 408, 41 S. E. 664; Pittsburgh Plate Glass Co. v. Neuer Glass Co. (C. C. A.) 253 F. 161; Manhattan Oil Co. v. Richardson Lubricating Co. (C. C. A.) 113 F. 923; Williston on Sales (2d Ed.) par. 464. The letters of November 3d and November 10th indicate that the parties intended that the rock would come from a stock on hand, but they hardly suffice to add that term to the agreement. The contract alleged is thus vitally different from that shown by the exhibits.

As to quantity, under a contract for the sale of a pile, the amount actually in the pile sold would be important. Under the contract to sell rock for the causeway, the amount on hand would be immaterial, and the amount necessary for the causeway would control. As to quality, in a sale of a particular pile, it being at hand and capable of inspection, and not being the manufacture or product of the seller, there would be no implied warranty, but caveat emptor would apply. Barnard v. Kellogg, 10 Wall. 383, 19 L. Ed. 987. But, if unascertained rock were sold for a particular use known to the seller, he would be held to furnish rock suitable for that use. See Kellogg Bridge Co. v. Hamilton, 110 U. S. 108, 3 S. Ct. 537, 28 L. Ed. 86; Dushane v. Benedict, 120 U. S. 630, 7 S. Ct. 696, 30 L. Ed. 810. The exMbits thus contradict the declaration, and there results confusion as to the exact sort of case to be tried, the thing which declarations and demurrers were intended to avoid. Therefore the grounds of demurrer that no valid contract is shown, and that the writings are insufficient under the statute of frauds, were properly overruled. That no time is fixed for delivery is meritless. The expression, “Date wanted — as desired,” means “on demand,” a usual stipulation in mercantile contracts. The ground that no quantity of rock to be delivered is stated cannot be sustained, for, as above pointed out, two measures in this respect are set forth. This fault of duplicity is reached by the fourth ground that the declaration is “vague, indefinite and uncertain in that it alleges that the defendant agreed to sell and the plaintiff to buy certain rock mentioned in said declaration on November 2nd, 1925, but the exhibits attached to said declaration are inconsistent' therewith and contradictory thereto.” The inconsistency and contradiction has been pointed out above. This ground of the demurrer ought to have been sustained. The error in overruling it would not necessarily be reversible, if no prejudice resulted to the losing party; but we think it led to embarrassment in the rulings on evidence, and probably surprise in the trial and'injustice in the verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cavrok Products Co. v. Dacor Inc.
1980 Mass. App. Div. 181 (Mass. Dist. Ct., App. Div., 1980)
Teigen Construction, Inc. v. Pavement Specialists, Inc.
267 N.W.2d 574 (South Dakota Supreme Court, 1978)
Matthews v. Lawnlite Company
88 So. 2d 299 (Supreme Court of Florida, 1956)
W. C. Shepherd Co., Inc. v. Royal Indemnity Co
192 F.2d 710 (Fifth Circuit, 1951)
McCall v. Texas Dragline Service Co.
188 S.W.2d 243 (Court of Appeals of Texas, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
43 F.2d 309, 85 A.L.R. 1178, 1930 U.S. App. LEXIS 3872, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tampa-shipbuilding-engineering-co-v-general-const-co-ca5-1930.