Tamarac Utilities, Inc. v. Hawkins

364 So. 2d 437, 1978 Fla. LEXIS 4909
CourtSupreme Court of Florida
DecidedSeptember 14, 1978
DocketNo. 52488
StatusPublished
Cited by1 cases

This text of 364 So. 2d 437 (Tamarac Utilities, Inc. v. Hawkins) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tamarac Utilities, Inc. v. Hawkins, 364 So. 2d 437, 1978 Fla. LEXIS 4909 (Fla. 1978).

Opinion

HATCHETT, Justice.

Tamarac Utility Company applied with the Public Service Commission for a rate increase for the operation of its water and sewer treatment services. An interim rate increase was granted to the utility pending disposition on the merits of the rate increase application. Public Service Commission auditors encountered numerous problems with regards to the lack of primary data supporting the amount of contributions in aid of construction (CIAC). The Commission issued an order allowing the utility to provide clarification, in the form of a schedule, certified by a Certified Public [438]*438Accountant, setting forth by year and contributor, all contributions in aid of construction received by the company in any form and from any source.1 Finally, the Commission issued an order dismissing the application and ordering a refund of monies collected under the interim rate increase previously approved. Tamarac Utility filed a Petition for Writ of Certiorari with this court.2 After oral argument and consideration of the briefs, we conclude that there has been no departure from the essential requirements of law in. the Commission’s dismissal of the application for a rate increase.3

In its final- order,4 the Public Service Commission noted that petitioner’s application and its supporting exhibits were seriously deficient with regards to proof of contributions in aid of construction which had been received by the utility company.5 In addition, the Commission concluded that more CIAC existed than was shown in the company’s audit. Such CIAC receipts are essential to a proper determination of a utility’s rate base.6 The Administrative Rules and Regulations of the Public Service Commission, Rule 25-10.176, require that each application by a water and sewer utility company for a rate adjustment must provide an accounting schedule showing total contributions in aid of construction.7 Rule 25-10.177 requires that:

In each instance, the utility must be able to support any schedule submitted, as well as any adjustments or allocations relied on by the utility. The work sheets, etc., supporting the schedules and data [439]*439submitted must be organized in a systematic and rational manner so as to enable Commission personnel to verify the schedules in an expedient manner and minimum amount of time. The supporting work sheets, etc., shall list all reference sources necessary to enable Commission personnel to track to original source of entry into the financial and accounting system and, in addition, verify amounts to the appropriate schedules.

The utility in this case did not comply with these regulations and provide the original source records in a readily accessible manner in support of its amount of CIAC receipts. Further, the utility audit did not attempt to establish the CIAC amount through independent original source records. Instead, the utility chose to rely upon an audit which was based upon a CIAC schedule prepared by the utility company. The Commission recognized that any errors made by the utility company when it made its original entries in this schedule also would be present in the recent audit.

In Deltona Corp. v. Mayo, 342 So.2d 510 (Fla. 1977), we held that the Public Service Commission improperly denied a utility’s application for a rate increase, in spite of its finding that the utility’s accounts were both accurate and in conformity with prescribed regulatory accounting procedures. The Commission in that case denied the application based upon argument by the public counsel, but which was unsupported by any evidence, that additional CIAC amounts existed which had not been reported by the utility in its account books.8 There, this court stated that the Public Service Commission cannot reject a CIAC amount proven by competent and substantial evidence offered by the utility, nor can the Commission assume there exists some additional indefinite amount of contributions in aid of construction which is not supported by competent substantial evidence. We hold, conversely, that any utility applying for a rate increase must support its CIAC valuation by competent substantial evidence in establishing its rate base.9

Accordingly, the order of the Public Service Commission in dismissing the utility’s application for a rate increase is affirmed.

It is so ordered.

BOYD, Acting C. J., and OVERTON, SUNDBERG and ALDERMAN, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rolling Oaks Utilities, Inc. v. Public Service Commission
418 So. 2d 356 (District Court of Appeal of Florida, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
364 So. 2d 437, 1978 Fla. LEXIS 4909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tamarac-utilities-inc-v-hawkins-fla-1978.