Tamara Agassi v. Holiday Hospitality Franchising, LLC
Opinion
SECOND DIVISION
DOYLE, P. J.,
DAVIS, J., and SENIOR JUDGE FULLER
NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed.
https://www.gaappeals.gov/rules
June 22, 2026
In the Court of Appeals of Georgia A26A0341. DARGEY v. HOLIDAY HOSPITALITY FRANCHISING, LLC.
A26A0342. AGASSI v. HOLIDAY HOSPITALITY FRANCHISING, LLC.
DOYLE, Presiding Judge.
Holiday Hospitality Franchising, LLC, (“HHFL”) sued Lobsang Dargey and Tamara Agassi (collectively, “the Appellants,”) for breach of a guaranty. Following the trial court’s grant of HHFL’s motion for summary judgment, the Appellants filed these appeals,1 arguing in two related enumerations that the grant of summary judgment to HHFL was erroneous because its claims were barred by the statute of
1 Both of the above-styled cases are based on the same record, arise from the same order, and involve the same two parties. The issues presented in both cases are duplicative and do not require us to address the parties’ arguments individually. Thus, we have consolidated our analysis of both cases.
limitation. For the reasons that follow, we affirm in both cases.
Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law.
We review a grant or denial of summary judgment de novo and construe the evidence in the light most favorable to the nonmovant.
Vaughn v. Windfield Homeowners Ass’n, Inc., 375 Ga. App. 18 (913 SE2d 74) (2025) (quotation marks omitted).
So viewed, the record reflects that HHFL and Potala Tower Seattle, LLC, (“PTSL”) executed a “Hotel Indigo New Development License Agreement” (the “License Agreement”) on July 31, 2014. Dargey signed the License Agreement as manager on behalf of PTSL. Under the License Agreement, PTSL was to develop, open, and operate a Hotel Indigo-branded hotel (the “Hotel”) in Seattle, Washington, for 20 years.
The License Agreement prohibited PTSL from selling, assigning, transferring, or otherwise encumbering the Hotel in the absence of express permission from HHFL. Such conduct would be considered a material breach of the License Agreement and give HHFL the right to terminate the Agreement. The License Agreement also authorized HHFL to terminate in the event that “any case ... seeking appointment of a receiver” was filed against PTSL or in the event that PTSL
“voluntarily or involuntary los[t] possession” of the Hotel.
The License Agreement further provided that if HHFL terminated the Agreement as a result of PTSL’s breach prior to the Hotel’s opening, PTSL would owe HHFL liquidated damages as calculated using an agreed-to formula. PTSL also agreed to pay attorney fees and court costs incurred by HHFL in remedying any defaults or enforcing any of its rights under the Agreement.
The Appellents signed a guaranty in which they personally guaranteed all of PTSL’s obligations under the License Agreement (the “Guaranty”). The Guaranty provided that upon PTSL’s default of the License Agreement and notice from HHFL, the Appellants would “immediately make each payment and perform each obligation required of [PTSL] under the [License Agreement].” The Guaranty would be effective even if PTSL’s obligations under the License Agreement were “rescinded or otherwise [had to] be restored or returned” as a result of PTSL’s “insolvency, bankruptcy[,] or reorganization.” The Appellants also agreed to pay attorney fees and court costs incurred by HHFL in remedying any defaults or enforcing any of its rights under either the Guaranty or the License Agreement.
In August 2015, the United States Securities and Exchange Commission (“SEC”) sued Dargey and PTSL, and on October 22, 2015, PTSL was placed into
receivership. Included among PTSL’s assets was the Hotel, of which the receiver obtained possession. It is undisputed that the receivership appointment constituted a material breach of the License Agreement.
On September 23, 2016, the receiver executed a sale agreement with a third party to purchase the Hotel. Despite Dargey’s recommendations, the purchaser did not keep the Hotel as a Hotel-Indigo-branded hotel. HHFL did not consent to the sale. On December 8, 2016, HHFL terminated the License Agreement based on the receivership sale of the Hotel.
The premature termination of the License Agreement prior to the Hotel’s opening and as a result of PTSL’s breach triggered PTSL’s obligation under the License Agreement to pay liquidated damages, which were calculated pursuant to the License Agreement to total $1,879,828.73. HHFL sent a demand letter to PTSL for payment of the liquidated damages, which PTSL failed to pay.
Pursuant to the Guaranty, the Appellants were also liable to HHFL for the liquidated damages. On August 18, 2021, HHFL notified the Appellants of PTSL’s default of the License Agreement and demanded payment of the liquidated damages. The Appellants failed to make any payments to HHFL for the liquidated damages.
On August 31, 2022, HHFL sued the Appellants for breach of the Guaranty
based on their nonpayment of the liquidated damages owed by PTSL and sought reimbursement for attorney fees. Discovery ensued, and Dargey moved for summary judgment, arguing that HHFL’s claims were barred by the applicable statute of limitation. Agassi later joined in Dargey’s motion. Thereafter, HHFL moved for summary judgment.
After a hearing, the trial court entered an order denying the Appellants’
motions for summary judgment and granting HHFL’s motion for summary judgment. In particular, the trial court rejected the Appellants’ argument that the statute of limitation for HHFL’s claim for breach of the Guaranty had begun to run on October 22, 2015, when PTSL’s assets, including the Hotel, were placed into receivership. Instead, the trial court found that the statute of limitation for this claim had started no earlier than December 8, 2016, when HHFL terminated the License Agreement. Accordingly, the trial court found that HHFL’s August 31, 2022 complaint for breach of guaranty was timely filed within the applicable six-year statute of limitation. The Appellants now appeal.
In two related enumerations of error, the Appellants contend that the trial court erred by denying their motions for summary judgment and granting HHFL’s motion for summary judgment because HHFL’s complaint was not filed within the applicable
statute of limitation. We disagree.
“All actions upon simple contracts in writing shall be brought within six years after the same become due and payable.” OCGA § 9-3-24. “When the question is raised as to whether an action is barred by a statute of limitations, the true test to determine when the cause of action accrued is to ascertain the time when the plaintiff could first have maintained his action to a successful result.” Wallace v. Bock, 279 Ga. 744, 747(2) (620 SE2d 820) (2005) (punctuation and quotation marks omitted). “[W]ith respect to a breach of contract claim, the statute of limitation runs from the time the contract is broken rather than from the time the actual damage results or is ascertained.” Hamburger v. PFM Cap. Mgmt., Inc., 286 Ga. App. 382, 385(1) (649 SE2d 779) (2007) (quotation marks omitted).
Free access — add to your briefcase to read the full text and ask questions with AI
Tamara Agassi v. Holiday Hospitality Franchising, LLC (Tamara Agassi v. Holiday Hospitality Franchising, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.