Talge Mahogany Co. v. New Albany Veneering Co.

147 N.E. 781, 84 Ind. App. 93, 1925 Ind. App. LEXIS 161
CourtIndiana Court of Appeals
DecidedMay 20, 1925
DocketNo. 12,280.
StatusPublished
Cited by1 cases

This text of 147 N.E. 781 (Talge Mahogany Co. v. New Albany Veneering Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Talge Mahogany Co. v. New Albany Veneering Co., 147 N.E. 781, 84 Ind. App. 93, 1925 Ind. App. LEXIS 161 (Ind. Ct. App. 1925).

Opinion

McMahan, J.

This cause was tried on an amended complaint in. one paragraph alleging: That in December, 1917, appellant entered into a contract with the Signal Corps of the United States Army for the manufacture of certain plywood to be used in constructing aeroplanes; that appellant was engaged in manufacturing the thin sheets of wood or veneer used in making plywood, but was not engaged in the business of, or equipped to manufacture plywood and was not prepared to manufacture the plywood called for in said contract; that thereafter appellant and appellee entered into a written contract whereby appellee agreed to manufacture the plywood called for in the contract, appellant agreeing to furnish the veneer for that purpose, such plywood to be three-ply construction, with poplar core .and mahogany face and back, appellant to cut the veneer to size and deliver the same to appellee at New Albany, and to pay appellee ten and one-fourths cents a foot for making the plywood, $5.16 per thousand surface feet of all mahogany which had to be jointed and taped and $2.42 per thousand for poplar core which had to be jointed and taped; that the contract of appellant with the signal corp called for pieces of plywood of smaller dimensions than the contract between appellant and appellee, and that the cost of making plywood in sizes named in the contract between *95 appellant and appellee was much less than the cost of making the same area in sizes named in the said contract with the signal corps, the time required to make the large sizes being substantially less than that required to make the small sizes.

That after the execution of the contract with appellant, appellee proceeded to prepare to execute the same, and installed special equipment for that purpose at a cost of $2,932.88, which cost had been figured into the cost of manufacturing the entire order covered by the contract and to be absorbed in the completion of the contract. That appellee manufactured and delivered to appellant under said contract 404,577 feet of plywood, 340,497 feet of which passed government inspection and was of the sizes required by the contract between appellant and the government, but 64,080 feet was rejected by the government because of defects in the veneer furnished by appellant; that later, said rejected pieces of plywood were, at the request of appellant, cut so as to eliminate the defects and the part of such plywood remaining was made into other sizes called for in the contract between appellant and the signal corps, and the pieces so cut off delivered to appellant; that said rejection was not due to any fault of appellee. That because of the failure of appellant to furnish veneer of proper sizes and of the required quality, appellee was required to cut the veneer into smaller sizes, and had to make and handle 70,863 pieces, whereas under the contract appellee would have made only 30,324 pieces, and that it cost appellee $7,190.74 more to make the 70,863 pieces than it would have cost to have made the 30,324 pieces in the sizes called for in the contract between appellant and appellee.

That if appellant had furnished veneer of the proper size, thickness and quality, appellee would have been required to handle 1,300,000 feet of veneer, but, be *96 cause of appellant’s failure to furnish proper veneer, appellee was. required to handle 2,000,000 feet of veneer, and to tape, patch, rip, dry, sort, inspect and handle the same, at a cost of $980.75, more than what it would have cost if the proper veneer had been furnished. That appellant agreed to furnish veneer of certain sizes and that, in addition to the labor of ripping and taping last above referred to, it was necessary for appellee to joint and tape 75,558 feet of mahogany face stock and 48,838 feet of poplar core at a total cost of $508.07.

That appellant agreed to pay the freight on all veneer shipped and returned but that it failed so to do and that appellee was required to and did pay $825.41 for freight, demurrage, and draying because of such failure; that after using all of the veneer shipped to appellee, it' was, by reason of appellant’s failure to furnish the proper sizes and quality, required to pack and return a large amount of veneer which could not be used, and that the cost of packing and crating the same was $72.12.

That in April, 1918, when the contract between appellant and appellee had been eighty-eight per cent, executed, the same was, by mutual consent, discontinued and that of the special equipment installed by appellee at a cost of $2,932.88 but eighty-eight per cent, thereof had been absorbed and that, by reason of the discontinuance of the contract, a balance on account of the unabsorbed special equipment, or $351.96, remained and that appellee was damaged in that sum by reason of such discontinuance.

That in the course of the manufacturing of said plywood, appellee, at the request of appellant, purchased certain poplar lumber, and when the contract was discontinued, the parties agreed that appellee should, retain such lumber so purchased and not used and that appel *97 lant should pay $137.03 for a named amount of lumber so purchased.

That the total amount so charged against appellant on account of said contract is $51,522.04, on which appellant is entitled to a credit of $32,784.53, as per itemized statement filed with the complaint, leaving $18,737.51 due and owing appellee for which it asked judgment.

Appellant filed a motion asking that appellee be required to separate this amended complaint into paragraphs, separating the written contract sued on from the oral contract for the purchase of the poplar lumber. It also filed a motion to make the complaint more specific by pleading the facts on which it. predicated the statement that it cost $7,190.74 more to make the small pieces of plywood than it would have cost to have made the larger pieces. These motions being overruled with exceptions, appellant filed an answer of denial, after which there was a trial by jury, which resulted in a verdict and judgment in favor of appellee for $16,000.

Appellants’ motion for a new trial being overruled, it appeals.

Appellant's first contention is that the court erred in overruling its motion to separate. By this motion, appellant asked that the complaint be separated into paragraphs; in this, that the written contract sued on be separated from the oral contract for the purchase of the poplar lumber. While this motion should have been sustained, it does not appear that appellant was harmed by the action of the court in overruling it. The claim for the $137, alleged to be due on account of the lumber purchased should have been stated in a separate paragraph of complaint. But appellant made no defense to that item, and fails to make any showing that it was harmed by reason of *98 the overruling of this motion. And it has been many times held by this court and the Supreme Court that the overruling of a motion to separate is not reversible error. Huntington Light, etc., Co. v. Spell (1916), 185 Ind. 30, 111 N. E. 311 ; Adams v. Antles (1914), 57 Ind. App. 594, 105 N. E. 931; Terre Haute, etc., Traction Co. v. McDermott (1924), 82 Ind. App. 134, 144 N. E. 620.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pittsburgh, Cincinnati, Chicago & St. Louis Railroad v. Rushton
148 N.E. 337 (Indiana Court of Appeals, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
147 N.E. 781, 84 Ind. App. 93, 1925 Ind. App. LEXIS 161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/talge-mahogany-co-v-new-albany-veneering-co-indctapp-1925.