Talbot Construction, Inc. v. Triad Drywall, LLC

777 S.E.2d 503, 333 Ga. App. 815
CourtCourt of Appeals of Georgia
DecidedSeptember 21, 2015
DocketA15A1097
StatusPublished
Cited by1 cases

This text of 777 S.E.2d 503 (Talbot Construction, Inc. v. Triad Drywall, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Talbot Construction, Inc. v. Triad Drywall, LLC, 777 S.E.2d 503, 333 Ga. App. 815 (Ga. Ct. App. 2015).

Opinion

Ellington, Presiding Judge.

This case concerns a construction subcontract between Appellee Triad Drywall, LLC (“Triad”) and Appellant Talbot Construction, Inc. (“Talbot”). Alleging Talbot never compensated Triad for services rendered, Triad filed suit in the Superior Court of Forsyth County for breach of contract, unjust enrichment, and quantum meruit. Talbot answered without asserting a related claim against Triad for breach of contract and later sought leave to assert the omitted compulsory counterclaim by amendment. After a hearing, the trial court denied Talbot’s motion for leave to add the counterclaim. Pursuant to this Court’s grant of Talbot’s application for interlocutory review, Talbot appeals, contending Triad made no showing that it would be prejudiced by the addition of the counterclaim, and, therefore, the trial court abused its discretion in denying Talbot leave to assert the omitted compulsory counterclaim under the “when justice requires” *816 provision of OCGA § 9-11-13 (f). 1 For the reasons explained below, we vacate the trial court’s ruling and remand this case for reconsideration of Talbot’s motion for leave to set up its omitted counterclaim.

Talbot avers that on March 2,2011, it entered into a contract with Wal-Mart Stores, Inc. (“Wal-Mart”), whereby Talbot agreed to provide labor, equipment, and materials for a remodeling project at a WalMart store in Snellville. In consideration for Talbot’s remodeling work on the project, Wal-Mart agreed to pay Talbot $924,098. A key component of the project included the removal of old drywall and the installation of new drywall. According to Wal-Mart’s schedule, Talbot had only 60 days to complete all of the remodeling work, and it could only work during specified times when the store was closed to the public. Additionally, Talbot was required to proceed in a very specific sequence because Wal-Mart did not want the remodeling project visible to its customers or for the construction to interfere with its daily store operations.

The project was scheduled to commence on April 17, 2011. On that day or the next, Talbot’s original drywall subcontractor notified Talbot it would not be able to perform the drywall replacement as they had agreed. Talbot’s project manager contacted Triad on April 19, 2011, to discuss having Triad take over the drywall work. Talbot agreed to pay Triad $29,000 and, due to the time constraints, Triad agreed to commence work that night. Talbot sent Triad a written subcontract for the work, and Triad’s project manager executed the subcontract on April 20,2011. Triad did not return the subcontract to Talbot until after April 26, 2011, however, and did not commence the project until that day. According to Talbot, other aspects of the remodeling work, such as priming and painting, trim installation, and other interior finish work, could only proceed efficiently and in accordance with the contract requirements if Triad completed the drywall work in a timely manner, which it failed to do. Triad’s failure to perform the drywall replacement on schedule prevented Talbot from completing the overall remodeling project on time. Because the project as a whole fell behind schedule, Wal-Mart defaulted Talbot, and terminated its contract. Wal-Mart completed the unfinished work and back-charged Talbot $73,763.80 for its costs and expenses.

On January 26, 2012, Triad commenced a suit against Talbot, claiming, inter alia, that Talbot owed it $41,251 under the subcontract. Talbot answered without asserting any counterclaim against *817 Triad. Over two years after filing its answer and defenses, Talbot filed an amended answer to Triad’s complaint and averred as an additional affirmative defense that Triad had materially breached its subcontract by failing to perform all conditions precedent to payment. In addition, Talbot contended Triad’s claims were barred or had to be reduced by a setoff of Talbot’s damages that were directly and proximately caused by Triad’s breach of its subcontract. Talbot then filed a motion for leave to set up its omitted counterclaim pursuant to OCGA § 9-11-13 (f). Talbot argued that Triad would not be prejudiced thereby and that justice required that its amendment be allowed. Triad opposed Talbot’s motion, arguing Talbot was not entitled to belatedly assert its counterclaim because it failed to exercise due diligence in asserting the counterclaim in a timely manner and it (Triad) would be prejudiced by the proposed amendment.

Under the Civil Practice Act, “[c]ompulsory counterclaims, as well as affirmative defenses, must be asserted in a defendant’s answer or responsive pleading.” (Citation omitted.) Riggio v. Lawson, 204 Ga. App. 774, 775 (1) (420 SE2d 613) (1992). See OCGA § 9-11-13 (a). 2 Generally, the failure to plead a compulsory counterclaim bars a party from asserting that claim in a subsequent action. Kitchens v. Lowe, 139 Ga. App. 526, 527 (1) (228 SE2d 923) (1976). OCGA § 9-11-13 (f), however, allows a pleader “by leave of court” to set up a counterclaim that was omitted from its answer “through oversight, inadvertence, or excusable neglect, or when justice requires [.]” As we explained in Blount:

The courts should be very liberal in allowing amendments to include compulsory counterclaims, . . . where the pleader has not been guilty of inexcusable neglect, or has not by reprehensible conduct deprived himself of any claim to special consideration by the court. The motion should be made promptly and may be denied for laches or lack of good faith____Before a delayed filing of a counterclaim is allowed, *818 the court should require the submission of evidence and make a finding therefrom as to whether the delay was occasioned by oversight, inadvertence or excusable neglect____It should appear, too, that the filing of the counterclaim when tendered works no prejudice against the plaintiff.

(Citations and punctuation omitted.) Blount v. Kicklighter, 125 Ga. App. 159, 161-162 (3), (4) (186 SE2d 543) (1971). Because an omitted compulsory counterclaim may be otherwise barred, “as a general rule leave to amend and set up a counterclaim shall be given freely, but this does not dispense with the necessity of showing that justice so requires.” Id. at 161 (4). “The determination of whether justice requires the grant of leave to set up an omitted counterclaim is a matter which addresses itself to the sound discretion of the trial court.” (Citation and punctuation omitted.) Boyd v. JohnGalt Holdings, LLC, 294 Ga. 640, 642 (1) (755 SE2d 675) (2014). We review the trial court’s ruling for abuse of discretion. Id. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MARIA CRISTINA VALLE GALEANA v. ERIN MCCOMMON
Court of Appeals of Georgia, 2025

Cite This Page — Counsel Stack

Bluebook (online)
777 S.E.2d 503, 333 Ga. App. 815, Counsel Stack Legal Research, https://law.counselstack.com/opinion/talbot-construction-inc-v-triad-drywall-llc-gactapp-2015.