Taber Partners I v. Merit Builders, Inc.

CourtCourt of Appeals for the First Circuit
DecidedJuly 31, 1997
Docket96-1465
StatusUnpublished

This text of Taber Partners I v. Merit Builders, Inc. (Taber Partners I v. Merit Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taber Partners I v. Merit Builders, Inc., (1st Cir. 1997).

Opinion

[NOT FOR PUBLICATION]

No. 96-1465

TABER PARTNERS I, A NEW YORK GENERAL PARTNERSHIP,

Plaintiff, Appellant,

v.

MERIT BUILDERS, INC., A PUERTO RICO CORPORATION, ET AL.,

Defendants, Appellees.

No. 96-1466

No. 96-1467

Plaintiff, Appellee,

Defendants, Appellees,

DESARROLLOS METROPOLITANOS, S.E.,

Third Party Defendant, Appellant.

APPEALS FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF PUERTO RICO

[Hon. Jaime Pieras, Jr., U.S. District Judge]

Before

Selya, Circuit Judge,

Coffin and Bownes, Senior Circuit Judges.

Arch Y. Stokes with whom Stokes & Murphy, Ruben T. Nigaglioni and McConnell & Valdes were on brief for plaintiff, appellant Taber Partners I. Eric A. Tulla with whom Rivera, Tulla & Ferrer, Woods & Woods, Raffle F. Ojeda-Colon were on brief for defendants, appellees and cross- appellants, Merit Builders, Inc., and Merit Builders, S.E., Harold D. Vincente, with whom Vincente & Cuebas, was on brief for appellee Insurance Company of North America. Humberto Guzman-Rodriguez with whom Fiddler, Gonzalez & Rodriguez were on brief for third-party defendant, appellant Desarrollos Metropolitanos, S.E.

JULY 31, 1997

BOWNES, Senior Circuit Judge. This breach of

contract case is a product of the renovation and expansion of

the Ambassador Plaza Hotel and Casino (formerly a Howard

Johnson Hotel) in San Juan, Puerto Rico. Plaintiff-appellant

Taber Partners I is the owner of the hotel. Its two partners

are A. Eugene Romano and his daughter, Linda Romano.

Defendant-appellee and cross-appellant Merit Builders, Inc. was

the general contractor. John Schlump, one of the two owners of

Merit, directed the construction and reconstruction work on the

hotel.

On January 18, 1989, Taber entered into a "cost-plus"

construction contract with Merit whereby Merit became the

general contractor for the renovation and expansion of the

hotel. Prior to this, Schlump had been retained as a

consultant by Eugene Romano to advise him how to proceed with

the proposed reconstruction and expansion. The "cost-plus"

contract was followed by a fixed price contract; both contracts

were collectively called the Tower contract. A third contract

was entered into by the parties for finish work on the casino,

two restaurants, and the hotel lobby.

On February 20, 1991, Taber filed a complaint in the

federal district court of Puerto Rico alleging breach of

contract by reason of delay, defective performance, and

negligent workmanship. There was also a claim for fraud and

deceit. The complaint was amended twice; the causes of action

-3- 3

remained essentially the same. At some point, it is not clear

from the record just when, Taber sued the Insurance Company of

North America under the performance bond INA issued for the

Tower contract.

Merit brought a counterclaim against Taber alleging

multiple breaches of contract, a claim based on Taber's alleged

delays and changes in the scope and nature of the work

contracted for, and fraud. Merit also brought a third-party

action against Desarrollos Metropolitanos, S.E., the concrete

subcontractor. It brought another third-party complaint

against Victor Torres and Associates, the inspectors of the

work, alleging breach of duty and tortious interference with

the performance of the contracts between Taber and Merit.

After a fourteen-week trial, the jury returned a

verdict finding that Merit was not liable to Taber. It further

found that Taber owed Merit $1,597,414.00 for breach of

contract. We consider Taber's appeal first.

At the close of the evidence, the district court

dismissed Merit's claim against Victor Torres and Associates.

TABER'S APPEAL

Taber forwards two issues on appeal: The ruling of

the district court excluding evidence of the loss of value of

the hotel due to defective construction work; and improper jury

instructions.

-4- 4

The Exclusionary Ruling

We start with the exclusionary ruling. In a pre-

trial order the court ruled that it would not allow evidence as

to the loss of value of the hotel. Taber had two expert

witnesses who would have testified that the reconstruction and

renovation work by Merit was done so incompetently and

defectively that the hotel's value was considerably less than

what it would have been had it been done properly.

At the start of its specific instructions the court

told the jury:

Taber Partners I claims that Merit Builders, Inc. breached all contracts entered into for the renovation and expansion of the Ambassador Plaza Hotel and Casino by failing to properly construct the building and by failing to complete the project in time. As a result, plaintiff claims that it suffered damages suffered [sic] due to alleged construction defects and time delays for which it seeks to recover the total sum of $3,730,995 from Merit.

This was an accurate statement of Taber's claims.

The jury answered the following questions on Merit's

liability:

PART A: Taber's claim against Merit for breach of contract

Question 1A.

Do you find that under the Lump Sum Tower Contract Merit failed to perform its duties and obligations or in any other way breached its contract with Taber by failing to comply with the plans and specifications?

-5- 5

. . .

Question 3A.

Do you find that under the Specialty Contract Merit failed to perform its duties or in any other way breached its contract with Taber by failing to comply with the plans and specifications?

Question 5A.

Do you find that under the Cost Plus Contract Merit failed to perform its duties or in any other way breached its contract with Taber by failing to follow the plans and specifications?

These jury findings establish beyond peradventure

that Merit was not liable to Taber for breach of contract,

which was the basis of Taber's claims against Merit.

We have read the transcript testimony of all

witnesses who testified on behalf of Taber. The record shows

that there was a plethora of evidence from which the jury could

have found liability, if it believed any of the witnesses. But

it chose not to do so. If any principle is embedded firmly in

our law it is that the jury is the final arbiter of the facts

and credibility decisions are exclusively within its domain.

Another firmly established legal rule is that a

finding of liability must precede any finding of damages.

-6- 6

Taber seeks to avoid this rule by arguing that "the Judge

erroneously forced Taber to argue liability without being

permitted to prove damages; it is the rare jury that will find

liability when it cannot appreciate that the plaintiff has

suffered damage." Taber's Brief at 20. This argument is

belied by the record. The court allowed in evidence all

damages claimed by Taber except that of the value of the hotel

and those that were duplicative.

Randall Redman, an expert witness called by Taber,

testified that, after inspecting the project, he told Eugene

Romano that the only way to achieve a quality building that

would last would be to tear the building down and start all

over.

During the testimony of Eugene Romano it was

stipulated as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Senra v. Cunningham
9 F.3d 168 (First Circuit, 1993)
Transnational Corp. v. Rodio & Ursillo, Ltd., Etc.
920 F.2d 1066 (First Circuit, 1990)
Tarek H. Elgabri, M.D. v. Mary D. Lekas, M.D.
964 F.2d 1255 (First Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Taber Partners I v. Merit Builders, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/taber-partners-i-v-merit-builders-inc-ca1-1997.