T. S. McShane Co. v. Great Lakes Pipe Line Co.

57 N.W.2d 778, 156 Neb. 766, 1953 Neb. LEXIS 48
CourtNebraska Supreme Court
DecidedApril 10, 1953
Docket33237
StatusPublished
Cited by3 cases

This text of 57 N.W.2d 778 (T. S. McShane Co. v. Great Lakes Pipe Line Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. S. McShane Co. v. Great Lakes Pipe Line Co., 57 N.W.2d 778, 156 Neb. 766, 1953 Neb. LEXIS 48 (Neb. 1953).

Opinion

Carter, J.

This is an action at law upon two contracts alleged to have been entered into by the defendant, Great Lakes Pipe Line Company, with the plaintiff, T. S. McShane Co., Inc., for the rental of a dragline and a clamshell bucket. The jury returned a verdict for $1,887.50 for rentals found to be due under the provisions of the dragline contract and for $222 for the rentals due under the clamshell-bucket contract. Judgment was entered for these amounts and the defendant appeals.

The evidence shows that the defendant undertook to. extend and enlarge its pipe-line terminal in Omaha at an estimated cost of more than $2,000,000. The construction work was being performed- by three prime contractors and subcontractors to whom portions of the work were sublet. The evidence also shows that all ordinary and usual construction materials were provided by the contractors. Certain technical equipment and materials, including pipe used in the construction of pipe lines, were provided by the defendant and stockpiled in its material yard at the terminal for use by contractors when needed. It was necessary when this material arrived that it be unloaded from freight or gondola cars into defendant’s material yard. This unloading was handled by short-form contracts made from time to time by the defendant as the material arrived. The general construction headquarters of the defendant were in Kansas City, Missouri, from which point the *768 general direction and supervision of the Omaha project, and many others as well, were handled. One R. D. Williamson was supervisor of construction of stations and terminals, which designation included the Omaha project which is here involved. The record shows that Williamson directed and supervised the construction of the terminal at Omaha, insofar as the interests of the defendant were concerned, through a subordinate located at that point, who was designated as resident engineer. Prior to June 12, 1950, the resident engineer had no authority to contract on behalf of the defendant except upon approval by Williamson, or certain officers superior to him who were located in Kansas City. After June 12, 1950, the resident engineer was authorized to enter into contracts on behalf of the defendant without specific approval where the amount did not exceed $100.

The position of resident engineer on the Omaha terminal project was held by one W. J.' Lank, Jr., from November 16, 1949, to September 8, 1950. He occupied a temporary building on the property and was the highest officer of the defendant on the ground insofar as construction was concerned. It was his duty to assist the contractors in the interpretation of plans and specifications and see to it that the construction work was performed in accordance therewith. He also entered into contracts for additional work resulting from changes in plans and specifications and for the unloading and handling of technical materials and pipe from railroad cars into defendant’s material, yard, ordinarily with approval by telephone or letter from Kansas City. For this purpose he was supplied with two forms of contract blanks, one a mimeographed form, the other a printed form bound together in lots of 50 and 100. When contracts involving $100 or less were required, Lank would execute the appropriate form contract with which he was supplied. If more than $100 was involved he could execute the contract only on approval from Kansas City, but the forms were left in his pos *769 session in order that the proposed work could be promptly contracted without the necessity of sending them in to Kansas City for formal approval. It is important to note here that all construction work being performed on the Omaha terminal project was being done by contract with one exception. The defendant did employ from one to five men as the need required, to work in defendant’s material yard to maintain material» and equipment there stockpiled, and to handle them in and out of the yard as the work progressed. At no time did the defendant own, rent, or purchase heavy construction equipment for its use on this project.

In the latter part of May 1950, Lank called Hugh M. Saxton, the manager of the contractor’s equipment department of the plaintiff company, and inquired if his company had a dragline to rent. The conversation resulted in a meeting of the two at plaintiff’s equipment yard the next morning. Terms of the rental were agreed upon and Saxton was requested to prepare the rental agreement and bring it to Lank’s office where he said he would sign it on behalf of the defendant company. Under date of June 1, 1950, the agreement was executed, Lank signing as the authorized agent of the defendant company. The contract was made up on the forms used by the plaintiff company and it provided generally for the rental of the dragline for a minimum of 3 months for $943.75 per month. Purchase order agreements were made out on forms provided by the Great Lakes Pipe Line Company for each monthly payment as it became due. This was necessary, according to Lank, in order that a copy could be attached to the invoice for the monthly rental payment. While the rental contract provided for the payment of rentals in advance, plaintiff agreed to bill the defendant at the end of the month to meet the alleged requirements of the defendant company. All billings were sent to the Omaha post-office box of the defendant, which was under the control of Lank. No invoice was ever sent to the office at Kansas *770 City. The rental for June was paid on July 20, 1950, by a check drawn on the Valley Coal Company. No other payments were made on the dragline contract.

The evidence further shows that on or about June 1, 1950, the dragline was hauled by a carrying company from plaintiff’s equipment yard to 18th and Vinton Streets in Omaha upon Lank’s order. It was consigned to one Forst, a contractor, who used it in constructing a Safeway Store at 21st or 22nd and Vinton Streets under a rental agreement with Lank. A week or 10 days later it was used on 13th Street in loading trucks with dirt. A salesman for the plaintiff company, one John M. Fruhwirth, reported that 2 or 3 days after it left plaintiff’s equipment yard the dragline was working at the Safeway Store site. Some days later Saxton saw it working on the 13th Street job. Saxton inquired of Lank why the dragline was working so far from the terminal and was told that, because of plaintiff’s delay in getting the dragline serviced for use, he had lost the dirt he intended to use and had to come to 13th Street to get the dirt for the fill to be made in the terminal area. No further inquiry was made of anyone concerning the use of the dragline, or the authority of Lank to make the rental agreement. There is evidence that Forst later obtained contracts on the terminal project and used the dragline there. He received his pay, for the use of the dragline in this work, from the defendant in the ordinary manner. Saxton and other employees of the plaintiff saw the dragline working at the terminal during this period. They testified that they had no knowledge that the dragline had been rented to Forst by Lank. On September 8, 1950, Williamson discovered the nature of the transactions made by Lank with the plaintiff. Plaintiff was immediately notified and the employment of Lank terminated. Plaintiff repossessed its dragline from a dredging contractor at Plattsmouth, Nebraska, to whom it had been leased by Lank.

*771

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCurry v. School District of Valley
496 N.W.2d 433 (Nebraska Supreme Court, 1993)
Oddo v. Speedway Scaffold Co.
443 N.W.2d 596 (Nebraska Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
57 N.W.2d 778, 156 Neb. 766, 1953 Neb. LEXIS 48, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-s-mcshane-co-v-great-lakes-pipe-line-co-neb-1953.