T. L. James & Co. v. Galveston County

74 F.2d 313, 1934 U.S. App. LEXIS 3949
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 13, 1934
DocketNo. 7494
StatusPublished
Cited by2 cases

This text of 74 F.2d 313 (T. L. James & Co. v. Galveston County) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. L. James & Co. v. Galveston County, 74 F.2d 313, 1934 U.S. App. LEXIS 3949 (5th Cir. 1934).

Opinions

HUTCHESON, Circuit Judge.

Appellant, a contractor disputing three items with the county of Galveston in the final settlement of its contract for the construction of a sea wall, brought this suit to recover them. One, a force account for $174.-74, was conceded to and refiovered by it. It lost the other two. To have the judgment it got reformed to include them, it prosecutes this appeal. One of these items for $2,893.-90 is a claim for under-measurement of the piling driven under the wall. It is based on the contention that the contract calling for piles 3”x8"xl0' to bo paid for at $65 M. F. B. M., i. e., per 1,000 feet board measure, requires payment for them as containing the twenty board feet which they did contain as the contractor bought them in the rough at the mill, instead of, as appellee claims it does, at the lesser footage obtained by measuring them when reduced by tonguing, grooving, and pointing, they stood in the piling wall. Appellee concedes that the amount sued for is due appellant if the piles are to be measured as appellant claims they should be. It concedes further that if the word “actual” were not in the measurement clause of the specifications, appellant’s construction should prevail. It insists, however, that being in, it conclusively rebuts appellant’s contention that payment should be made for them by the county upon the same basis the contractor has paid for them, the conventional 20 feet to the pile, doing away with the conventional measurement by substituting actual measurement for it. The other item is a claim for $569.40 for 438 dressed piles, 3"x8''xl0' containing 20 board feet each, at $65 per thousand. These were driven as side piling to close gaps not intended nor provided by the specifications to be in the piling wall.

As in the case of the first item, the dispute here is not over the amount, but over the theory of recovery. To recover this item, which eoncededly was not originally contemplated or contracted for, appellant claims that when it was found out how difficult it was to drive the piles forming the piling wall so that there would be no gaps between them, the engineer in charge agreed that instead of pulling the piles out and redriving them, [314]*314appellant could fill the gaps by driving side piles. It also claims that the engineer definitely agreed as to the first 50 that they would be paid for, and that they supposed and believed, since all were accepted, all would be paid for. As presenting merely a question of fact, and that not a difficult one, we take this item up first.

The District Judge found, on ample supporting evidence, that in violation of the contract obligation to drive the piles so as to form a solid wall, appellant in some instances in driving them allowed space between; that instead of requiring appellant, as he could have done, to draw these pilings and redrive them, the engineer permitted it to close the spaces by driving side piling. He found, too, that the driving of this piling was the result of appellant’s want of care, and that since it was, appellee could not be made to pay for them. The correctness of this finding as to all but the 50 piles, which it is claimed the engineer told appellant he would pay for, cannot, we think, be doubted. We think it was right as to these too, for the evidence shows not an absolute and unconditional agreement to pay for these piles, but, on the contrary, a conditional agreement that if the side piling driven did not run over 50, they would be paid for. Appellant having breached his part of the understanding by driving tenfold the side piling allowed, is in no position to hold the engineer, if it could hold the county, to his part of the bargain. The judgment as to this item is affirmed.

The other item, the measurement of the sheet piling forming the piling wall, is by no means so easily disposed of. In the court below its solution was made to turn on the meaning and force of the single word “actual” appearing in the last sentence of parágraph 38 of the specifications, “Piling”; “The measurement of piling shall be the actual number of board feet of accepted piling in place under the wall.”

The District Judge agreed that the terms “Board Feet” “number of Board Feet,” are technical trade terms having a definite and accepted meaning among manufacturers of, dealers in, and those having to do with and handling, lumber. That this accepted meaning is that a board, which comes from the sawmill in the rough 3 inches thick, 8 inches wide, and 10 feet long 3"x8''xl0', containing 20 board feet of lumber, is still regarded after being reduced in thickness, width, and quantity by dressing, or as in this case by hewing tongued, grooved, and sharpened at one end for driving, and is sold and paid for as, a 3x8x10 containing 20 board feet. He thought, however, that the board feet so ascertained, according to the accepted usage and custom, should be regarded as the nominal board feet in the piles as actually prepared for driving and driven. He thought that the introduction into the specifications of the word “actual” was for the purpose of, and that the whole expression must in law be regarded as, intended to have, and as having, the effect of providing for the actual, instead of the nominal, measurement. He thought this apparent from the face of the contract. He thought, too, that this view was strengthened by the testimony of the engineer as to his intention in writing the word “actual” in and by the testimony and conduct of some of the bidders. He therefore rejected appellant’s demand that it be paid by the county on the conventional basis for the 20 board feet in each pile it had paid the manufacturer for, and held the payment to it to the actual cubic contents of the piling wall. He thus permitted the county to pay appellant not as it had paid the manufacturer for the 20 board feet in each pile used, but for the considerably less number of board feet arrived at by measuring the piles as they stood, lessened in the wall, by tonguing, grooving, and sharpening.

Appellant argues that by focusing attention on and bringing this controversy within the compass of the single word “actual” the District Judge has, by the intensity of this restricted regard, so foreshortened the view he took of the ease as to prevent his seeing it in whole. It insists that to do this is to bring about a solution by verbalistie interpretation rather than by construction of the contract. It insists that a construction searching for the real understanding on which the minds of the parties met would find it not in this word or in that, but in the whole instrument in the light of the ruling trade practices and understandings imported into it, in respect of which the parties must in law be supposed to 'have contracted. It argues that sueh construction makes it clear that the word “actual” was inserted in the specifications for a wholly different purpose, and has a wholly different effect from that ascribed to it by the trial court. It was used, appellant says, not in opposition to nominal or conventional, to import a different basis of measurement into the contract than that universally applying, but to qualify “in place under the wall,” and to emphasize that only piling actually in place there would be paid for. It points to the overwhelming testi[315]*315mony of the witnesses as to the commonly accepted meaning and significance in the trade the disputed clause in the specifications has as written, ándito the testimony of the county engineer that but for his having put the word “actual” in he would have allowed appellant’s claim. -Pointing out too, in how many other places “actual” is used in the specifications 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deep South Oil Co. of Texas v. Texas Gas Corp.
328 S.W.2d 897 (Court of Appeals of Texas, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
74 F.2d 313, 1934 U.S. App. LEXIS 3949, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-l-james-co-v-galveston-county-ca5-1934.