T. Brady Mechanical Services Inc. v. F.E. Moran, Inc. (In Re T. Brady Mechanical Services Inc.)

129 B.R. 559, 1991 Bankr. LEXIS 1082, 1991 WL 143931
CourtUnited States Bankruptcy Court, N.D. Illinois
DecidedAugust 1, 1991
Docket19-05261
StatusPublished
Cited by4 cases

This text of 129 B.R. 559 (T. Brady Mechanical Services Inc. v. F.E. Moran, Inc. (In Re T. Brady Mechanical Services Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. Brady Mechanical Services Inc. v. F.E. Moran, Inc. (In Re T. Brady Mechanical Services Inc.), 129 B.R. 559, 1991 Bankr. LEXIS 1082, 1991 WL 143931 (Ill. 1991).

Opinion

MEMORANDUM OPINION

RONALD S. BARLIANT, Bankruptcy Judge.

The Debtor/Plaintiff is a contractor. Among the assets of this estate are the interest of the Debtor in a payment bond covering a construction project in which the Debtor did work and the rights to payment for that work. The Debtor and the issuer of the payment bond, Reliance Insurance Company, which is a named defendant, have moved for summary judgment declaring that only the Debtor has any right to payment on the bond, and that the Debtor’s sub-contractors have no such right. One of those sub-contractors, G & 0 Thermal Supply Company, has moved for summary judgment declaring that it is covered by the bond. Another sub-contractor, Baltimore Aircoil (“BAC”), opposes the Debtor’s and Reliance’s motions, arguing that there are genuine issues of material fact.

If the Debtor and Reliance win, the Debt- or will be paid the entire remaining balance due for the work and the sub-contractors will be left with claims against the estate. 1 If the sub-contractors win, they will be paid. This is a core matter under 28 U.S.C. § 157(b)(2).

The Court finds that there is no genuine issue of material fact and that motions of the Debtor and Reliance should be granted, while G & O’s motion should be denied.

BACKGROUND

James H. Anderson, Inc., was the principal mechanical contractor for the Downers Grove Office Building Project. Anderson refused to sign a sub-contract with the Debtor for piping until the Debtor obtained labor and material payment and performance bonds. Because the Debtor could not obtain such a bond on its own, it asked F.E. Moran, Inc., to be an accommodation party to the bond. The Debtor paid Reliance Insurance Company for the bond directly; on November 29, 1988 F.E. Moran signed it as principal. All the work was performed by the Debtor pursuant to an oral contract with F.E. Moran. The Debtor used various sub-contractors, including BAC, G & 0, and Maram Corp. F.E. Moran, however, has withheld payment to the Debtor until this Court determines which parties are covered under the bond.

The bond obligates F.E. Moran and Reliance to pay “claimants” up to $1,492,130. “Claimant” is defined in the bond as “one having a direct contract with the Principal for labor, material, or both, used or reasonably required for use in the performance of the contract, labor and material being construed to include that part of water, gas, power, light, oil, gasoline, telephone services or rental of equipment directly applicable to the subcontract.”

The question here is whether there is any legal theory under which the sub-contractors may recover on the bond. BAC advances five affirmative defenses as to why it is entitled to payment under the bond: 1) the provisions of the bond itself entitle the sub-contractors to payment; 2) the subcontractors are the intended beneficiaries of the bond; 3) the Debtor and F.E. Moran entered into an agreement with the intent to protect the sub-contractors; 4) the bond creates a constructive trust of which the sub-contractors are the intended beneficiaries; and 5) the sub-contractors have equitable liens against the Debtor’s assets. G & 0 makes similar arguments, and also states that the Debtor and F.E. Moran are joint venturers, and therefore under partnership law the sub-contractors are in privity with F.E. Moran.

DISCUSSION

A. The Bond

The bond itself does not entitle the subcontractors to payment. The explicit language of the bond allows only a party *561 having a “direct contract with the Principal” to be a claimant. F.E. Moran is the only principal. The Debtor is the only party that had a direct contract with F.E. Moran.

B. Joint Venture

G & 0 alleges that the Debtor and F.E. Moran were joint venturers, and that therefore privity exists between F.E. Moran and the sub-contractors. However, even the case that G & 0 relies on shows that there was no joint venture. Aigner v. Bell Helicopters, Inc., 86 F.R.D. 582 (N.D.Ill.1980), states that to establish a joint venture it is necessary that there be a contract (express or implied), a community of interests, the parties must have some right to direct and govern each other’s conduct, profits and losses must be shared, and the parties must have a proprietary interest in the subject matter. G & 0 makes several assertions supporting its joint venture theory. First, “The Court can fairly imply [sic] that F.E. Moran and Brady controlled each other’s actions to some degree,” because F.E. Moran was liable on the contract while Brady did all they work. Second, profits and losses were shared because F.E. Moran would have been compensated for its role on future construction jobs.

These assertions do not establish the elements of a joint venture. The connection between the Debtor and F.E. Moran does not imply that they had the right to direct and govern each others’ conduct. Nor does any future compensation for F.E. Moran on other jobs, if it could be shown, constitute a sharing of profits and losses.

C. Third Party or Intended Beneficiary

The problem regarding the third party beneficiary argument was set out over 60 years ago in Carson Pirie Scott & Co. v. Parrett, 346 Ill. 252, 257, 178 N.E. 498 (1931). “The rule is settled in this State that if a contract be entered into for a direct benefit of a third person not a party thereto, such third person may sue for breach thereof. The test is whether the benefit to the third person is direct to him or is but an incidental benefit to him arising from the contract. If direct he may sue on the contract; if incidental he has no right of recovery thereon.” The Illinois Supreme Court went on to explain that in doing such an analysis, “Each case must depend upon the intention of the parties as that intention is to be gleaned from a consideration of all of the contract and the circumstances surrounding the parties at the time of its execution.” Id. at 258, 178 N.E. 498. Having said that, however, the court then appeared to withdraw from the “circumstances” approach. “This liability must affirmatively appear from the language of the instrument when properly interpreted and construed. The liability so appearing cannot be extended or enlarged on the ground, alone, that the situation and circumstances of the parties justify or demand further or other liability.” Id. “It is a cardinal rule of construction of written contracts that the court will look at the entire contract and construe it according to the intention of the parties as the same appears from the language of the instrument.” Id. at 259, 178 N.E. 498.

More recent cases support the proposition that the court should not look beyond the bond itself. As in our situation, the bond in Young v. General Insurance Co. of America, 33 Ill.App.3d 119, 337 N.E.2d 739 (1975), limited rights to Transco and its successors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
129 B.R. 559, 1991 Bankr. LEXIS 1082, 1991 WL 143931, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-brady-mechanical-services-inc-v-fe-moran-inc-in-re-t-brady-ilnb-1991.