T. B. Wright & Sons v. Cleveland, Cincinnati, Chicago & St. Louis Railway Co.

169 Ill. App. 246, 1912 Ill. App. LEXIS 991
CourtAppellate Court of Illinois
DecidedMarch 21, 1912
StatusPublished

This text of 169 Ill. App. 246 (T. B. Wright & Sons v. Cleveland, Cincinnati, Chicago & St. Louis Railway Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. B. Wright & Sons v. Cleveland, Cincinnati, Chicago & St. Louis Railway Co., 169 Ill. App. 246, 1912 Ill. App. LEXIS 991 (Ill. Ct. App. 1912).

Opinion

Mr. Justice Shirley

delivered the opinion of the court.

Appellees filed a bill in equity against appellant to enforce a lien for material furnished a corporation named Widell Finley Company, a contractor, to perform concrete work for appellant upon its line of railway. The court found appellees entitled to a lien upon all the property of appellant, real, personal and mixed, for the payment of the sum of $1,839.90 and so decreed.

The evidence disclosed that on July 17, 1905, the Widell Finley Co., hereinafter called the contractors, entered into an agreement with the Cairo, Vincennes & Chicago Railway Co., hereinafter called the railway company, to construct certain tracks and bridges and to reduce grades along the line of said railway between Allendale and Harrisburg, Illinois. The masonry to be used in the construction was to be of concrete and the contract provided the work should be accepted by appellant and certified by it in writing. It further appears that in the year 1889 the said railway company entered into an operating contract with appellant whereby the said railway company leased to appellant the line of railway upon which the work of said contractor was to be performed for a period of forty-nine years, and at the time of entering into the contract for the work by the railway company and during the time appellees furnished material, appellant was operating said railway under said lease.

The lease among other things provided appellant should maintain the entire railway property in as good condition as it then was. The answer of appellant admits that it determined as such lessee to reconstruct and rebuild the said railway in the name of the railway company, and for that purpose the railway company entered into the contract with the said contractor for the construction of bridges and culverts; that the work was to be done under the control and direction of appellant’s engineers and appellant was to pay for the work.

The evidence shows that appellees furnished to the contractor a lot of material of the value of $1,796.68, which was reduced by credits to the sum of $1,455> being the amount due at the time of the trial not including any interest. The evidence shows the material so furnished was used in constructing buildings for housing laborers and in making concrete forms for bridges and culverts. After the contractor had been for some time engaged in the work it failed and appellant took up the work and finished it.

It is contended by appellant that the contractor hav- ■ ing failed to complete the contract the suit should have been brought under section 7 of the railroad lien law instead of section 2 which is relied upon by appellees, and that appellees mistook the remedy in not proceeding under section 7.

The act of 1872 entitled “Liens Upon Railroads” contains eight sections. The purpose of the act as shown in the title was “to protect contractors, subcontractors and laborers in their claims against railroads, contractors and subcontractors.” The first section provides for a lien in favor of persons who contract directly with the railroad company and who furnish material, supplies or labor necessary for the construction, maintenance, operation or repair of the road. The lien is given against all the property of the railroad and is superior to all mortgages or other liens which accrue after the commencement of the delivery of the material or of the labor furnished.

Section 2 relates to subcontractors and those who furnish material and labor to the contractor and reads as follows:

“Every person who shall hereafter as subcontractor, material man or laborer furnish to any contractor with any such railroad corporation any fuel, ties, materials, supplies or any other article or thing or who shall do and perform any work or labor for such contractor in conformity with any terms of any contract express or implied which such contractor may have made with any such railroad corporation, shall have a lien upon all the property real, personal and mixed, of said railroad corporation: Provided such subcontractor, material man or laborer shall have complied with the provisions of this act; but the aggregate of all liens hereby authorized shall not in any case exceed the price agreed upon in the original contract to be paid by such corporation to the original contractor:

“And provided further, that no such lien shall take priority over any existing lien.”

Sections 3 and 4 provide for notice by the subcontractor to the railroad company. Section 5 provides for a suit at law (after the above notice) against the corporation, or the corporation and original contractor jointly, and for judgment and execution. And section 6 for attorneys’ fees in such cases to be taxed as costs.

Section 7 provides that if the original contractor fails to complete his contract any person entitled to a lien may file a petition in a court of record in any county through which the road may be constructed against the corporation and the contractors, setting forth the nature of his claim, the amount due as near as may be, and that the contractor has failed to complete his contract. This section then requires notice by publication of the filing of the petition and when the writ issued thereon is made returnable and then provides that all persons entitled to liens may enter their appearance, interplead and have their claims adjudicated. It further provides that all persons who establish their claims shall have a decree against the corporation and the contractor for the respective amounts to which they are entitled and the decree shall have the same force and effect as in other cases. Section 8 is a limitation section not material to be considered.

It is an elementary rule in the interpretation of statutes that construction should be made of all the parts together, and not of one part by itself, to determine the object and purpose of the enactment and they should be so construed if possible that the whole may stand and every part may have force and meaning. Endlich Interp. of Statutes, 35; 4th Gil. 221; Chatham v. Mason, 53 Ill. 411; Decker v. Hughes, 68 id. 33.

After an examination of the several sections referred to we conclude it was the purpose of the act to give a subcontractor three different remedies by said sections two, five and seven, either of which he may pursue. It is true section 2 provides no specific remedy to enforce the lien which the section gives the subcontractor after complying with the provisions of sections 3 and 4 which provide for notice and service thereof, but it in plain terms furnishes the lien and as it does not furnish a remedy one is implied. “When a statute creates a new obligation * * * a corresponding right is thereby impliedly given either to the public or to the individual injured by the breach of the enactment,” (Endlich Interp. of Statutes, 463) and as the enforcement of a lien is an equitable remedy he may have his remedy by filing a bill in equity. Pom. Eq. Jur. 112, 171:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Chatham v. Mason
53 Ill. 411 (Illinois Supreme Court, 1870)
St. Louis & Peoria Railroad v. Kerr
38 N.E. 638 (Illinois Supreme Court, 1894)
Weidle v. Elgin, Joliet & Eastern Railway Co.
152 Ill. App. 292 (Appellate Court of Illinois, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
169 Ill. App. 246, 1912 Ill. App. LEXIS 991, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-b-wright-sons-v-cleveland-cincinnati-chicago-st-louis-railway-illappct-1912.