Syracuse Capital Corp. v. Pattison Construction Corp.

133 Misc. 894, 234 N.Y.S. 68, 1929 N.Y. Misc. LEXIS 740
CourtNew York Supreme Court
DecidedApril 12, 1929
StatusPublished
Cited by1 cases

This text of 133 Misc. 894 (Syracuse Capital Corp. v. Pattison Construction Corp.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Syracuse Capital Corp. v. Pattison Construction Corp., 133 Misc. 894, 234 N.Y.S. 68, 1929 N.Y. Misc. LEXIS 740 (N.Y. Super. Ct. 1929).

Opinion

Brown, J.

In this action, brought to foreclose six mortgages, motion is made by plaintiff to dismiss the affirmative defense set up in the answer of defendant Dalton, whereby, with respect to the mortgage set up in the fifth cause of action of the complaint,- said defendant seeks to establish the priority of two mechanics’ liens.

[895]*895With the exception of the claim of priority as to the said two mechanics’ liens, all the allegations of the complaint stand admitted by the answer. From the complaint it appears that on April 25, 1928, defendant Pattison Construction Corporation, executed and delivered its bond to the plaintiff for the purpose of securing payment to the plaintiff of such sum or sums of money as the plaintiff might at its option advance to said Pattison Construction Corporation, up to but not exceeding the sum of $100,000, whereby it bound itself in the penal sum of $200,000 to pay to the plaintiff five months from the date thereof, such sums of money up to $100,000 as the plaintiff should have advanced to said defendant Pattison Construction Corporation. As collateral security, said Pattison Construction Corporation executed and delivered a mortgage upon the premises described in the fifth cause of action in the complaint. The said bond and mortgage were recorded in the Onondaga county clerk’s office on the 25th day of April, 1928. Prior to September 25, 1928, the plaintiff advanced to the defendant Pattison Construction Corporation the sum of $93,000 secured by said bond and mortgage, which principal sum and interest thereon defendant Pattison Construction Corporation failed to pay when due, and the plaintiff has declared the whole amount due.

The answer sets up that defendant Dalton performed two jobs for defendant Pattison Construction Corporation in the improvement of the premises described in the mortgage above mentioned. On one job, commencing June 1, 1928, and ending November 27, 1928, a notice of mechanic’s lien in the amount of $5,102.48 was filed on November 7, 1928. On the second job, commencing September 27,1928, and ending November 9, 1928, a notice of mechanic’s lien in the amount of $1,672 was filed on November 9, 1928. No part of the sums of money for which the notices of the mechanics’ liens were filed has been paid.

The defendant’s answer claims that said mechanics’ liens are prior to the mortgage hereinbefore mentioned, by reason of the fact that on the 25th day of April, 1928, the plaintiff and defendant Pattison Construction Corporation entered into a building loan contract, under and pursuant to which the bond and mortgage above mentioned were executed and delivered, which building loan contract was not acknowledged by the plaintiff as required by section 22 of the Lien Law (as amd. by Laws of 1916, chap. 507). The instrument which defendant thus contends is a building loan contract, is attached to the answer and marked “ Schedule C,” and will hereafter be spoken of as such. Schedule C,” entitled “ Building Loan Agreement,” was signed and acknowledged only by defendant Pattison Construction Corporation and was filed in the county clerk’s [896]*896office on April 25, 1928. In the first “ Whereas ” clause there is recited the fact that defendant Pattison Construction Corporation had executed and delivered its bond and mortgage in the amount of $100,000 to the plaintiff, and the second “ Whereas ” clause states that “ first party [defendant Pattison Construction Corporation] is constructing nineteen dwellings upon said premises to cost at least $160,000, and desires to obtain from the second party [the plaintiff herein] advances from the moneys secured by said bond and mortgage during the progress of said construction.” In the body of Schedule C ” defendant Pattison Construction Corporation agrees that it will complete the said dwellings with proper materials and with speed consistent with good workmanship, and the plaintiff agrees' to advance to Pattison Construction Corporation for the construction of said dwellings $9,000 upon the approval of papers and title by the attorneys for the plaintiff, and the balance at the discretion of the ” plaintiff.

If the transaction of April 25, 1928, constituted a building loan contract, which was not properly filed as required by section 22 of the Lien Law, then pursuant to the provisions of said statute, the two mechanics’ hens would be superior to the mortgage set forth in the fifth cause of action of complaint.

What is the meaning of a contract for a building loan ” as used in section 22 of the Lien Law? The statute itself gives us no assistance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
133 Misc. 894, 234 N.Y.S. 68, 1929 N.Y. Misc. LEXIS 740, Counsel Stack Legal Research, https://law.counselstack.com/opinion/syracuse-capital-corp-v-pattison-construction-corp-nysupct-1929.