Syndoulos Lutheran Church of Fairbanks v. A.R.C. Industries, Inc.

662 P.2d 109, 1983 Alas. LEXIS 404
CourtAlaska Supreme Court
DecidedApril 1, 1983
Docket6789, 6941
StatusPublished
Cited by9 cases

This text of 662 P.2d 109 (Syndoulos Lutheran Church of Fairbanks v. A.R.C. Industries, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Syndoulos Lutheran Church of Fairbanks v. A.R.C. Industries, Inc., 662 P.2d 109, 1983 Alas. LEXIS 404 (Ala. 1983).

Opinion

OPINION

COMPTON, Justice.

There are two issues raised in this appeal: first, whether a defendant against whom a default has been entered may disprove a material allegation of the plaintiffs complaint at the trial on damages and thereby avoid liability, and second, whether an owner of real property may directly sue a subcontractor for his defective workmanship. For the reasons set forth below, we conclude that under the circumstances of this case the superior court erred in denying judgment to the plaintiff on the basis that a material allegation of the complaint had been disproven at the trial on damages. We further conclude that the superior court erred in holding that the plaintiff could not recover directly from a subcontractor for his defective workmanship in the construction of the plaintiff’s building. 1

I. FACTUAL AND PROCEDURAL BACKGROUND

This is an appeal taken by the Syndoulos Lutheran Church of Fairbanks and the Wisconsin Evangelical Lutheran Synod (“the Church”) from the decision of the superior court denying it any relief against A.R.C. Industries, Inc. (“A.R.C.”) and Thomas Farr, who is allegedly the sole or principal stockholder of A.R.C. The Church had entered into a contract with Bradley & Associates in 1978 to have Bradley & Associates construct a building for it in Fairbanks. Bradley & Associates agreed to design, plan and construct the building for $175,000.00, which sum was paid in full by the Church. A.R.C. subcontracted with Bradley & Associates to perform the foundation work.

Without cause, Bradley & Associates abandoned the construction of the church before it was completed. The Church paid approximately $26,000.00 to have the construction completed by another contractor. Furthermore, the work performed and the materials used by A.R.C. were faulty and will cost approximately $2,000.00 to correct.

The Church filed a complaint against Bradley & Associates in July of 1979. The complaint was amended once in November. In December, the Church filed a Second Amended Complaint, naming as defendants for the first time A.R.C. and Farr. A.R.C. and Farr were properly served with the complaint, but neither filed an answer or entered an appearance. Defaults were entered against A.R.C. and Farr on February 15, 1980.

Briefly, the allegations in the Church’s complaint against A.R.C. and Thomas Farr are that Farr is an associate or partner of Bradley & Associates and is also the sole or principal stockholder of A.R.C., that Bradley & Associates subcontracted with A.R.C. to perform foundation work, and that the work was defective. The relief prayed for was that the Church be awarded the same damages from Farr as it recovers from Bradley & Associates and that the Church also be awarded damages from Farr and A.R.C. for the defective work on the foundation.

The Church amended its complaint once again in July of 1981. A.R.C. and Farr attempted to file an answer to that complaint and demand a jury trial. A.R.C. and Farr contended that the amendment of the complaint operated to vacate the defaults entered against them. A.R.C. and Farr subsequently withdrew from this position, upon concluding that the law is that if an amendment does not materially affect the allegations against the defendant, it does not operate to vacate the default. The amendment to the complaint after the defaults had been entered only added the allegation that the Church was a duly formed corporation.

*111 Counsel for A.R.C. and Farr appeared in court at the time of the trial against the remaining defendants, which included Bradley & Associates. Neither A.R.C. nor Farr ever moved to have the default set aside. They conceded that the issue of their liability had been determined by the entry of default, but nonetheless contended that they had the right to contest the amount of damages sought by the Church.

The superior court held that the Church had complied with the rules governing the entry of defaults against defendants and, thus, A.R.C. and Farr could not contest their liability. It further held, however, that A.R.C. and Farr were entitled to defend against the damages portion of the action against them. The validity of these holdings is not contested in this appeal. During the course of the trial, Farr attempted on several occasions to introduce evidence that he was not a partner of Bradley & Associates. On each occasion, the court ruled that this evidence was inadmissible because it did not relate to the issue of damages, but related instead to an allegation of the Church’s complaint that was deemed proven upon the entry of default.

After the trial was completed, counsel submitted proposed findings of fact and conclusions of law, which were reviewed by the court. Farr contended that the evidence presented at trial affirmatively established that Farr was not a partner of Bradley & Associates as alleged in the Church’s complaint and thus he could not be jointly liable with Bradley & Associates for the judgment that would be entered against it. After listening to the Church’s arguments in opposition, the court stated that the evidence presented at trial did not persuade it that there was a partnership between Farr and Bradley & Associates. Accordingly, the court would not hold Farr liable for the judgment entered against Bradley & Associates.

The court had difficulty in articulating a legal theory upon which Farr and A.R.C. would be directly liable to the Church for the defective work. The court was particularly concerned that there did not appear to be, in fact or by allegation, any privity between the Church and A.R.C. The Church contended that an owner may sue a subcontractor directly for any defective work, but did not cite any authority for this proposition or relate it to a particular legal theory. The court indicated that it would give this issue further consideration.

On January 21,1982, the court entered its Findings of Fact and Conclusions of Law. It found Bradley & Associates liable for all of the damages proven at trial and it further found Farr and A.R.C. additionally liable for the defective foundation work. On February 5, 1982, the court entered a judgment against Bradley & Associates for $38,-926.00 damages, plus costs, attorney’s fees and prejudgment interest, for a total judgment of $56,863.74. It entered a judgment against Farr and A.R.C. in the amount of approximately $2,000.00 for damages, $600.00 for prejudgment interest and $600.00 for costs.

Farr and A.R.C. moved to have the judgment reconsidered. The court indicated in its order that the matter was fully briefed by the parties, but no memoranda by counsel are part of the record before us. The court quashed its judgment against Farr and A.R.C., stating that the damages resulting from the defective workmanship on the foundation “are damages properly those of [Bradley and Associates].” The court then entered Amended Findings of Fact and Conclusions of Law, in which the conclusion that Farr and A.R.C. were liable to the Church for the defective work was omitted. The court also amended its judgment against Farr and A.R.C. to reflect that the Church recover nothing from them. The Church appeals from the Amended Judgment awarding it nothing against A.R.C. and Farr.

II. EFFECT OF DEFAULT

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haines v. Comfort Keepers, Inc.
393 P.3d 422 (Alaska Supreme Court, 2017)
Adam M v. Christina B
Alaska Supreme Court, 2013
Hicks v. Pleasants
158 P.3d 817 (Alaska Supreme Court, 2007)
Valley Hosp. Ass'n, Inc. v. Brauneis
141 P.3d 726 (Alaska Supreme Court, 2006)
Snyder v. American Legion Spenard Post No. 28
119 P.3d 996 (Alaska Supreme Court, 2005)
Linden v. Cascade Stone Company, Inc.
2005 WI 113 (Wisconsin Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
662 P.2d 109, 1983 Alas. LEXIS 404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/syndoulos-lutheran-church-of-fairbanks-v-arc-industries-inc-alaska-1983.