Synchronized Construction Services, Inc. v. Prav Lodging, L.L.C.

86 Va. Cir. 235, 2013 Va. Cir. LEXIS 128
CourtCircuit Court of the 9th Judicial Circuit of Florida, Orange County
DecidedFebruary 6, 2013
DocketCase No. CL10-220
StatusPublished

This text of 86 Va. Cir. 235 (Synchronized Construction Services, Inc. v. Prav Lodging, L.L.C.) is published on Counsel Stack Legal Research, covering Circuit Court of the 9th Judicial Circuit of Florida, Orange County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Synchronized Construction Services, Inc. v. Prav Lodging, L.L.C., 86 Va. Cir. 235, 2013 Va. Cir. LEXIS 128 (Fla. Super. Ct. 2013).

Opinion

By Judge Daniel R. Bouton

The court has had an opportunity to give further study to the arguments pertaining to Virginia Community Bank’s motion to dismiss. The court has also reviewed the authority cited by counsel, along with Virginia’s statutory scheme for the filing and the enforcement of mechanics’ liens. The court concludes that the general contractor, Paris Development Group, L.L.C. (Paris) is a necessary party to the case. Since Paris is no longer a defendant in the case, the motion to dismiss will be granted. The rationale for the court’s decision is set forth below.

The case before the court is one in which the mechanics’ lien has been bonded off under § 43-70 of the Code of Virginia. This statute allows “any party in interest” to file a bond after the litigation has commenced. When this occurs, the status of the case is changed because the bond then replaces the real property as the collateral for the lien. As a result, the lien against the owner’s land is released, and the title to the property is no longer encumbered by an exception for a mechanics’ lien. Since such a bond has been filed in the present case, the court must determine whether the general contractor remains a necessary party.

To begin the analysis, who is and who is not a necessaiy party in a suit to enforce a mechanics’ lien can he different depending on whether or not a bond has been filed. The Supreme Court of Virginia made this clear in [236]*236George W. Kane, Inc. v. NuScope, Inc., 243 Va. 503 (1992). There, the court determined that, once the lien had been bonded off, the owner, the trustee under a construction loan deed of trust, and the beneficiary of the deed of trust were no longer necessary parties. In the present case, the plaintiff relies primarily on the reasoning of George W. Kane to support his position. He asserts that Paris, the general contractor, is not a necessary party to the litigation because of the bond. The crux of the argument is that the general contractor has no further “actual enjoyment of the subject matter, or... an interest in it, either in possession of expectancy....” Id., at 509.

Nevertheless, the court is not persuaded that the holding in George W. Kane is dispositive. To begin with, it must be stressed that the filing of the bond in no way changes what title plaintiff must prove in the suit to enforce the lien. The court acknowledged this precise point in George W. Kane. There, the court said that, even in a “bond enforcement suit, the party plaintiff has the burden of proving the same elements of his claim that he would have had to prove in a suit to enforce the lien released by that bond.” Id., at 509. Thus, even with the bond, the disputed issues in the case are no different. In order to succeed, the plaintiff must file a valid lien. The plaintiff must then file suit to enforce the lien. At trial, the plaintiff must prove the total amount that he is entitled to recover. Moreover, to prove any such amount, the plaintiff must satisfy a number of requirements set forth in Virginia’s statutoiy scheme for mechanics’ liens and in several decided cases. Finally, if the plaintiff successfully proves his claim, the amount can then be enforced against the bond. As set forth in § 43-70, the bond stands for the “payment of such judgment adjudicating the lien or liens to be valid and determining the amount for which the same would have been enforceable against the real estate as may be rendered by the court, upon the hearing of the case on its merits____” (Emphasis added.)

In this context, what is significant is that the filing of the bond has no impact on whatthe plaintiff must prove with respect to the general contractor. It also does not eliminate or change the interests of the general contractor in the subject matter of the litigation. The court must still hear the case on its merits. In the court’s view, this explains why George W. Kane does not support the position of the plaintiff. There, the critical factor for the court was that the owner, the trustee, and the deed of trust beneficiary all had an interest in the title to the real property that was the subject of the filed lien. Once the bond replaced the lien, these parties were no longer exposed to the possibility that the property might be sold to enforce the mechanics’ lien. In other words, at least some of the subject matter of the suit changed because of the bond. In turn, the respective interests of some of the parties in the subject matter of the suit also changed. The specific change was that their property was not encumbered by a lien and was no longer at any further risk of being sold. Therefore, while they would be proper parties to the case, the Supreme Court explained that they were no longer necessary.

[237]*237This reasoning, however, would have no application to the general contractor. That is because the general contractor in George W. Kane had no interest in the title to the real property. Similarly, the general contractor here has no interest in the title to the real property. Therefore, the plaintiff’s reliance on the George W. Kane case is misplaced because the bond does not modify the interests of the general contractor in any of the disputed issues. The bond will have no impact on how the case is tried. The bond does not change what the plaintiff must prove about the obligations of the general contractor and the obligations of the owner.

Plaintiff also argues that the provisions of § 43-22 support his position. He points out that the statute does not identify the general contractor as a necessary party and it does not require that the general contractor be named in the suit to enforce the lien. This argument fails to persuade the court for two reasons. First, the language of the statute is limited in scope; it only discusses certain aspects of a suit to enforce a lien. Most important, the legislature never addressed the question of necessary parties in any of the statutory provisions for mechanics’ liens. On this point, the main focus of the statutory scheme is on the perfection of the lien. Yet, there are procedural and substantive distinctions between the perfection of the lien and the suit to enforce it. They are two entirely different proceedings. With regard to a suit to enforce a lien, the statutory scheme only refers to a number of filing requirements; it also contains a statute of limitations. No statutory provision, however, defines the subject matter of the suit or lists all of the necessary parties. Second, the case of Walt Robbins, Inc. v. Damon Corp., 232 Va. 43 (1986), makes it clear that § 43-22 does not limit or define the issue of which parties are necessary in a suit to enforce a lien.

As a result, the court finds that the plaintiff’s arguments regarding George W. Kane and Virginia’s statutory scheme do not eliminate the general contractor as a necessary party. Nevertheless, this does not end the inquiry, and it does not mean that Virginia Community Bank should prevail on the motion to dismiss. Rather, in order to decide whether the general contractor is a necessary party, the court must first identify the entire subject matter of the case. The court must then examine how the Supreme Court of Virginia has defined a necessary party. Finally, the court must decide whether the general contractor meets the definition of a necessary party in this particular case.

To begin with, the filing of the bond has resulted in at least some change to the subject matter of the case before the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atkisson v. Wexford Associates
493 S.E.2d 524 (Supreme Court of Virginia, 1997)
Mendenhall v. Douglas L. Cooper, Inc.
387 S.E.2d 468 (Supreme Court of Virginia, 1990)
George W. Kane, Inc. v. Nuscope, Inc.
416 S.E.2d 701 (Supreme Court of Virginia, 1992)
Walt Robbins, Inc. v. Damon Corporation
348 S.E.2d 223 (Supreme Court of Virginia, 1986)
Taylor v. Netherwood
20 S.E. 888 (Supreme Court of Virginia, 1895)
Johnston & Grommett Bros. v. Bunn & Monteiro
62 S.E. 341 (Supreme Court of Virginia, 1908)
John T. Wilson Co. v. McManus
173 S.E. 361 (Supreme Court of Virginia, 1934)
Raney v. Four Thirty Seven Land Co.
357 S.E.2d 733 (Supreme Court of Virginia, 1987)
Asch v. Friends of the Community of Mount Vernon Yacht Club
465 S.E.2d 817 (Supreme Court of Virginia, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
86 Va. Cir. 235, 2013 Va. Cir. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/synchronized-construction-services-inc-v-prav-lodging-llc-flacirct9ora-2013.