[547]*547Opinion op the Court by

Judge Thomas

Affirming.

On or about March 1, 1911, the plaintiff and appellee here, Gr. H. Hackstadt, was the owner of a pin-cylinder ¡organ used in connection with a merry-go-round, or flying Dutchman, in the operation of which plaintiff was engaged at that time. He entered into a contract with the predecessors in business of the appellant and defendant below, the Symphony Player Company, to convert the organ into a player-organ to play perforated 65-note music, the work to be completed, according to plaintiff’s testimony (which is undisputed) by April 15, 1911; it was further agreed that certain work should be done to the bellows of the organ, and that it should be painted, for all of which plaintiff was to pay $135.00.

Shortly after the contract the partnership with whom it was made became incorporated in the name of the Piano Player Manufacturing Company, which assumed all the obligations of the partnership, and the name of that company was afterwards changed to that of appellant, the Symphony Player Company. The place of business of the defendant at the date of the contract was in Cincinnati, Ohio, but a short while after the execution of the contract it moved its place of business to another part of the city, from which latter place it later removed its business to the city of Covington, Kentucky. Nothing appears to have been done under the contract for almost a year, except to tear the organ to pieces and perhaps saw off some of the pipes, but in the meantime plaintiff was making frequent demands that the contract be carried out and the work completed.

Eventually plaintiff was notified that his organ had been remodeled so as to play 44-note paper music instead of that called for by the contract; but even this much was not done for more than two years after the contract was entered into. When plaintiff learned what had been done to the organ in an alleged effort to carry out the contract, he at once repudiated it and declined to accept the organ thus remodeled because it failed to produce the volume of music which he desired for his business, and further because it was an entire failure even as a player of 44-note music, in that the sound was low and there was a great discord and a lack of harmony in its notes. About that time, or shortly afterward, defendant began preparations to move its business from [548]*548the city of Cincinnati, Ohio, to the city of Covington, Kentucky, and under the contention that it had complied with its contract it wrote a letter to plaintiff to the effect that his organ had been completed according to contract and offering to deliver it to him upon demand. That letter was written on July 16,1912, and on the 31st of the same month it again wrote him stating its intention to move, and that unless he called for the organ it would be compelled to leave it in the building defendant then occupied, subject to his Orders. On August 5th following, the defendant wrote him, saying: “We received your favor of the 31st inst. We have the organ now in as good a condition as can be made. We are moving our factory and would therefore like to get it out of the road.” The letters of plaintiff in response to those of defendant are not filed, but he testified that he was protesting in them all the while that the organ had not been completed according to the contract. When the move was made from Cincinnati to Covington the organ was taken along and stored in the basement of the building which defendant occupied in the latter city, where it remained for' more than a year without anything whatever being done to it, and when plaintiff went there to see about the organ, in response to a letter written "him by the defendant on May 17, 1913, the manager for defendant could not at first find the organ, but eventually located it in the basement, as above stated.

On June 10,1913, another letter was written by plaintiff to defendant saying: “Replying to your letter of June 3rd will state that we have found that it is going to be utterly impossible for us to repair the organ. We wish you would kindly call upon us as early as possible without any inconvenience to yourself, and we will endeavor to get together and straighten this matter out. Regretting our inability to make the repairs as you require them, we remain,” &c. Plaintiff replied to that letter on June 13, and next day defendant wrote him, say ■ ing: “Replying to your letter of June 13th, in reference to the organ, will state that we are compelled to advise you, much to our regret, that your organ can not be finished at any time. ’ ’ The letter then continues by stating that some of the pipes were gone and that defendant did not know whether they had ever been received or whether they had been lost.

[549]*549Notwithstanding all these .rebuffs the plaintiff continued to make heroic efforts to have his organ completed according to contract. But failing, he finally, some time in June, 1915, placed the matter in the hands of his attorney, which resulted in the filing of this suit to recover the value of the organ, upon the ground that defendant had so mutilated and abused it as to render it worthless. In the meantime defendant’s representatives suggested to plaintiff that he buy a new organ, since it appeared impossible for defendant to make the repairs according to contract. Plaintiff did buy a new one, but not with the intention of abandoning his contract with defendant, since he continued thereafter to insist upon its performance until it became evident that defendant had not only abandoned its contract, but had also rendered the organ worthless, as stated. The petition fixed the value of the organ at $700.00, and sought judgment for that amount.

The answer was a denial, with the affirmative allegation that there was no agreement to repair the organ for the price indicated but only one to undertake such repairs, with no guarantee that the work could be done. A denial of that plea constituted the issues, and at the close of the evidence the court peremptorily instructed the jury to find for plaintiff what it might reasonably believe from the evidence was the value of the organ at the time it was delivered to defendant under the contract. This was followed by a verdict in favor of plaintiff for $700.00, upon which judgment was rendered, and to reverse it the defendant prosecutes this appeal.

The principal argument made in behalf of defendant in this court is that the evidence failed to show a conversion of the organ by the defendant and that the court was in error in giving the above instruction to the jury. It is also insisted that the court erred in refusing to give instructions offered by the defendant, and that the verdict finding the value of the organ to be $700.00 is flagrantly against the evidence.

If the first error complained of be without merit, then the second one complained of would necessarily be so. But, postponing for the present the consideration of these questions, we will first dispose of the last error relied upon. A number of witnesses besides plaintiff, who, according to the testimony, were vessed in such [550]*550matters, Sfiid that plaintiff’s organ in the condition it was at the time it was delivered to defendant was reasonably worth $700.00 or $800.00, the plaintiff fixing its value at a still higher sum. Witnesses for defendant, perhaps equal in number to those who testified for plaintiff on this point, gave it as their opinion that the organ, at the time it was delivered to defendant was worth from $50.00' to $200.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winchell v. Alaska Airlines, Inc.
96 F. Supp. 339 (D. Alaska, 1951)
Howell v. Dodd