Appeal of -- ) ) Symetrics Industries, LLC ) ASBCA No. 59297 ) Under Contract No. W58RGZ-07-C-0204 )

APPEARANCES FOR THE APPELLANT: David Z. Bodenheimer, Esq. Jason C. Lynch, Esq. Crowell & Moring LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney Robert B. Neill, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

INTRODUCTION

Appellant timely appeals from a contracting officer's final decision claiming $121,824 plus interest accrued from the date of payment, for alleged defective pricing under a contract for modem units. The parties have elected to waive a hearing and submit their cases upon the record pursuant to Board Rule 11. We sustain the appeal.

FINDINGS OF FACT

On 30 August 2007, the Department of the Army awarded a letter contract, Contract No. W58RGZ-07-C-0204, to appellant, Symetrics Industries, LLC, for the production of295 Improved Data Modem (IDM) 304 units, (Joint Statement of Stipulated Facts (stip. 6)). Symetrics submitted a firm-fixed-price proposal (FFP) to procuring contracting officer (PCO) Hanford Jones on 7 December 2007 (stip. 9). PCO Jones negotiated the contract price on behalf of the Army, with the assistance of contract specialist Johnny Coleman (stip. 43). The Defense Contract Audit Agency (DCAA) assisted PCO Jones in the evaluation of the price proposal by conducting an audit of the proposal (see stip. 14). DCAA Auditor Sherry Hepfuer conducted that audit (stip. 14).

Earlier, on 12 July 2007, the Defense Contract Management Agency (DCMA) had approved an overhead rate of 179.20% and a General and Administrative (G&A) rate of 25 .60% for Symetrics's contractor fiscal year (CFY) 2007 (stip. 45). On 7 January 2008, Symetrics submitted a Forward Pricing Rate Proposal (FPRP) to DCMA (stip. 47). On 23 January 2008, Symetrics submitted to PCO Jones a revised price proposal for the 295 IDM 304 units (stip. 13). The price proposal identified a direct labor overhead rate of 182.45% for CFY 2008, a direct labor overhead rate of 186.47% for CFY 2009, and G&A rates of 18.24% for CFY 2008 and CFY 2009 (id.).

On 4 February 2008, DCAA informed Symetrics that DCAA had been requested to audit the FPRP, and that DCAA had to complete the audit by 24 February 2008, "for [the price] proposal being audited by Sherry Hepfner" (stip . 51 ). On 7 February 2008, Symetrics sent DCAA the FPRP (stip. 54). The FPRP proposed overhead rates of 170 .3 8% and G&A rates of 17 .13 % for CFY 2008 and CFY 2009 (stip. 54), lower than the rates identified in the price proposal (stip. 13).

DCAA Auditor Hepfner audited Symetrics's price proposal for the 295 IDM 304 units (stip. 14). By 21February2008, Auditor Hepfner was aware of the 7 February 2008 FPRP, was aware that the FPRP contained new overhead and G&A rates (new, at least, since the approval of the CFY 2007 rates) (see stip. 27), and was aware that the FPRP would likely lead to lower forward pricing rates (stips. 26, 27; gov't br. at 13). Indeed, on 21February2008, Auditor Hepfner wrote to ACO Gilmore:

We are currently auditing the subject proposal for a quantity of 295 Improved Data Modem [IDM] 304. This is to advise you that on February 7, 2008, Symetrics submitted a new Forward Pricing Rate Proposal (FPRP), for CFYs 2008 and 2009. Symetrics priced the proposal with the new Overhead and General and Administrative (G&A rates). We have not audited the FPRP. Therefore, we recommend that a clause be included in the FFP contract, which will provide for a downward only adjustment for any savings that may result from the adjustment of the proposed rates after completion of our audit of the Symetrics FPRP for CFYs 2008 and 2009, direct labor and indirect rates and factors.

(Stip. 27) According to the government, that statement "plainly documents Ms. Hepfner's mistaken belief at the time that the IDM 304 'proposal' that she was then auditing was priced using [Symetrics' s] newly updated overhead and G&A rates" (gov't reply at 9).

Similar to Auditor Hepfner' s message to ACO Gilmore, on 25 February 2008, DCAA issued an audit report (Auditor Hepfner is listed as a primary contact for the report (R4, tab 22 at 11)) on the price proposal that noted that:

2 On February 7, 2008, Symetrics submitted a new Forward Pricing Rate Proposal (FPRP), for CFY s 2008 and 2009. Symetrics priced this proposal with the new overhead (OH) and G&A rates. Therefore, ... we recommend that a clause be included in the FFP contract, which will provide for a downward only adjustment for any savings that may result from the adjustment of the proposed rates after completion of our audit of the Symetrics FPRP for CFYs 2008 and 2009, direct labor and indirect rates and factors.

(Stips. 28, 29) DCAA's report identified rates of 182.45% for CFY 2008 and 186.47% for CFY 2009, and G&A rates of 18.24% for CFY 2008 and CFY 2009 (R4, tab 22 at 6).

On 27 March 2008, the day that negotiations to definitize the contract price commenced (stip. 37), Symetrics submitted its final price proposal revision to the PCO (stip. 33). Like the 23 January 2008 price proposal and the DCAA audit report, the 27 March 2008 price proposal identified direct labor overhead rates of 182.45% for CFY 2008 and 186.47% for CFY 2009, and G&A rates of 18.24% for CFY 2008 and CFY 2009 (stips. 13, 33; R4, tab 22 at 6). Also on 27 March 2008, PCO Jones and Contract Specialist Coleman memorialized their prenegotiation object"ive (R4, tab 34 at 1). Their prenegotiation memorandum expressly references both the 7 February 2008 FPRP and the DCAA audit report regarding overhead and G&A, but identifies the overhead and G&A rates that appear in the price proposal (R4, tab 34 at 7). The prenegotiation memorandum reflects that PCO Jones and Contract Specialist Coleman erroneously believed that the price proposal used the FPRP rates:

The contractor proposed the CFY 2008 and CFY 2009 OH and G&A rates recently submitted in its FPRP, dated February 7, 2008.

...DCAA compared the proposed indirect rates to the FPRP (as shown in the table below. [sic] DCAA also compared actual CFY 2007 OH and G&A rates ...to the indirect rates in the contractor's current FPRP and calculated the percent increases. No significant variances were noted in the evaluation. The results of the analysis of the contractor's proposed CFY 2008 to CFY 2009 indirect rates are presented in the table below.

3 (R4, tab 34 at 7) (Emphasis added) The table referenced in the quotation depicts the higher overhead and G&A rates for CFY 2008 and CFY 2009 that appear in the price proposal, not the lower rates for those years that appear in the FPRP (compare R4, tab 34 at 7 with stip. 54).

Four days later, on 1 April 2008, the parties agreed to a price of $7,284,435 for the 295 IDM 304 units (stip. 39). As of that date, Symetrics had not revised its price proposal to reflect the FPRP overhead and G&A rates, nor had it transmitted those rates directly to PCO Jones or Contract Specialist Coleman (stips. 41, 43). On 2 April 2008, Symetrics certified in a Certificate of Current Cost or Pricing data that:

[T]he cost or pricing data ... submitted ... to the Contracting Officer or to the Contracting Officer's representative in support of Contract No. W58RGZ-07-C-0204 are accurate, complete, and current as of 01 April 2008. This certification includes the cost or pricing data supporting any advance agreements and forward pricing rate agreements between the offeror and the Government that are part of the proposal.

(Stip. 40)

On 15 May 2008, the parties entered into Modification No. PZ0007, definitizing the $7,284,435 price for the 295 IDM units (stip. 44).

Free access — add to your briefcase to read the full text and ask questions with AI

Symetrics Industries, LLC, (asbca 2015).

Symetrics Industries, LLC (Symetrics Industries, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

§ 2306
10 U.S.C. § 2306(a)