Swindell-Dressler Co. v. Commonwealth
This text of 413 A.2d 38 (Swindell-Dressler Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Opinion by
In Swindell Dressler Co. v. Department of Transportation, 42 Pa. Commonwealth Ct. 634, 401 A.2d 600 (1979), we ruled on a dispute between Swindell-Dressler Company (Swindell) and the Pennsylvania Department of Transportation (PennDOT) concerning whether Swindell’s fee for engineering and design services should be based on an estimate of construction costs or upon the bid submitted by the successful contractor. Our ruling, based on the provisions of the agreement between the parties and the facts of the case, was that Swindell’s fee must be based upon the approved estimated construction cost submitted with the plans and designs.
We further determined that the original project was complete on April 30,1969 and Swindell’s right to a specific fee became fixed 90 days thereafter. We remanded the case to the Board of Arbitration of Claims [466]*466(Board),1 with directions that judgment be entered in favor of Swindell and against PennDOT in an amount consistent with our opinion.
On remand, the Board awarded Swindell $39,-439.24,2 with simple interest from April 2, 1974, the date the Board determined Swindell’s cause of action accrued in these proceedings. Swindell filed this appeal which only challenges that portion of the Board’s order fixing the date from which interest is to be computed.
In Department of Transportation v. DePaul, 29 Pa. Commonwealth Ct. 447, 371 A.2d 261 (1977), involving a claim against the Commonwealth under a contract for the installation of new traffic signals, we adhered to our holding in Department of Property & Supplies v. Berger, 11 Pa. Commonwealth Ct. 332, 312 A.2d 100 (1973), that interest should be awarded from the date on which the Commonwealth’s obligation arose. In General State Authority v. Loffredo, 16 Pa. Commonwealth Ct. 237, 247, 328 A.2d 886, 893 (1974), we stated that “[i]t is axiomatic that when a contract is fully performed, the obligation to pay for that performance would arise on the date of completion absent contractual terms to the contrary. ”
Here the contractual terms were that, if the plans and designs were not advertised for bids within 90 days of their approval, the fee was to be determined by multiplying the estimated cost of construction by 3.25 percent. The project was not advertised for bids within the 90-day period and therefore on the 91st day [467]*467Swindell’s right to a specific fee became fixed and the obligation of PennDOT to pay Swindell’s fee arose.
Since the agreement in question here designated the “completed project” as “the delivery to PennDOT, and the approval and acceptance by the Secretary and the Chief Engineer, of the completed drawings of all plans and designs,” and the date of completion was determined in Swindell Dressler Co. v. Department of Transportation, supra, to be April 30, 1969, it follows that, by the terms of the contract, on the 91st day thereafter, bids not having been sought in the interim, the obligation of PennDOT to pay Swindell’s fee arose. That date was July 30, 1969 and is the date from which interest must be computed in this case.
In all cases of contract, interest is allowable from the time payment is withheld after it has become the duty of the debtor to make such payment. Palmgreen v. Palmer’s Garage, Inc., 383 Pa. 105, 117 A.2d 721 (1955). The due date for the payment of interest occurs upon the happening of a contingency when one is in contemplation of the parties or is part of their contract. Peyton v. Margiotti, 398 Pa. 86, 156 A.2d 865 (1959). In the instant case, the happening of the contingency was the expiration of 90 days, during which the project was not advertised for bids, following April 30,1969, which was the date the original project was completed. Accordingly, the date from which interest is to be computed on the $39,439.24 principal amount due Swindell is July 30,1969.
Order
And Now, this 11th day of April, 1980, the order of the Board of Claims, dated September 5, 1979 and finding in favor of Swindell-Dressler Company, is modified by substituting the date of July 30, 1969 for the date of April 2, 1974, and, as so modified, the said order is affirmed.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
413 A.2d 38, 50 Pa. Commw. 464, 1980 Pa. Commw. LEXIS 1280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swindell-dressler-co-v-commonwealth-pacommwct-1980.