Sweet v. Breivogel

CourtSuperior Court of Maine
DecidedNovember 16, 2017
DocketHANcv-14-52
StatusUnpublished

This text of Sweet v. Breivogel (Sweet v. Breivogel) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sweet v. Breivogel, (Me. Super. Ct. 2017).

Opinion

STATE OF MAINE SUPERIOR COURT HANCOCK, SS. DOCKET NO. CV-14-52

John Sweet ) Plaintiff ) t ) FINDINGS, DECISION AND ' I

v. ) ) JUDGMENT . J •' Carl & Elizabeth Breivogel Defendants ) ) l FACTUAL FINDINGS

The plaintiff, John Sweet, is a sole proprietor engaged in the construction of traditional timber frame homes. Traditional timber frame construction is a unique form of construction that typically involves a significantly higher level oflabor, time and craftsmanship.

• The defendants had acquired land in Mt. Desert, and in the winter of 2013 { 1 began searching for potential homebuilders to construct a residence on their purchased land. In that regard, the defendants visited the plaintiffs website and made an initial inquiry on or about February 12, 2013 regarding "an enclosed, whether-tight timber frame home. 11 (Plaintiffs Ex. I).

The plaintiff responded to the defendants' inquiry and began a dialogue regarding the defendants' needs, and what services the plaintiff could provide. Those discussions led to a visit, in person, by the defendants to the plaintiffs residence, which was also the site of his business operations. Specifically, on March 18, 2013, the defendants viewed the plaintiffs own

1 28 x 30 traditional timber frame home which he had constructed. This visit occurred prior to any agreement reached between the parties regarding the construction of a home for the defendants.

During the visit at the plaintiffs home, the defendants were told by the plaintiff that it would cost $500,000 to build a home like the plaintiffs. During the same visit, the plaintiff also showed the defendants some other traditional timber frame homes he had constructed which were somewhat larger than his own home. One additional such home was a 32 x 32 house which cost $400,000 to construct to the level of being little more than weathertight.

After the defendants returned home from their visit with the plaintiff, the parties continued an exchange of emails. Specifically, in a series of emails which were shared March 26, 2013 the parties began to discuss costs associated with constructing a home for the defendants. This is also the point at which there began to be a divergence between the parties as to the nature and extent of the specific work to be perfonned for the dollar amounts which were being considered.

The defendants asked the plaintiff whether a salt box style temporary home could be constructed for about $275,000, not including the septic. The plaintiff responded that it was possible but it was difficult to say at that early stage. It is clear from the evidence at trial that the actual work being contemplated for the $275,000 price was different as between the parties. The plaintiff understood the work being requested was for the construction of an enclosed, weathertight timber frame home. This level of construction, t' I 2 ! which was also referred to as a "dried shell structure" would involve the following components: -excavation - eight or 10 inch foundation - placement of the timber frame structure on the foundation - enclosure of the frame with walls and roofs - insulation - roof covering with tarpaper and asphalt shingles - installation of Marvin Windows - Cedar shingles on the sidewalls - window and door flashings - full chimney installation.

The plaintiff did not understand this level of construction to include a fully completed home with all of the amenities finished and ready for ocupancy.

The defendants, however, were envisioning a fully completed home ready for occupancy with respect to their inquiry regarding the $275,000 budget. Each of the parties mistakenly proceeded under the assumption that the other party shared that party's understanding of the scope of the work to be performed for $275,000.

Thus, the defendants authorized the plaintiff to begin construction of their new home on or about April 13, 2013 at a cost not to exceed $275,000. The parties further agreed that the defendants would be billed for any labor performed at the rate of $32 per hour in addition to the materials utilized.

3 Despite inquiry from the defendants, the plaintiff refused to prepare a written contract regarding the work to be performed in constructing the defendants, home. The plaintiff told the defendants that he had never signed a written contract in over 30 years of construction work. The plaintiffs lack of adherence to fmmal written contracts was also consistent with his very informal approach to record-keeping, plan designing and general documentation. The plaintiff did, nonetheless, regularly communicate with the defendants by sharing progress photographs and providing invoicing on basically a biweekly basis.

Although the plaintift's testimony was somewhat inconsistent as to his status as a general contractor for this project, the court finds that the plaintiff was functioning in that capacity. The plaintiff made numerous recommendations regarding subcontractors, the billing for the subcontractors work went through the plaintiff, the plaintiff charged a markup to the defendants for the subcontractors work, and the plaintiff generally directed the timing of the subcontractors work on the project.

Throughout the summer and fall of 2013, the plaintiff proceeded to construct a "dried shell structure 11 (as defined above) on the defendant's property in Mt. Desert. Based upon the evidence presented through the photographs (plaintiffs Exhibit 101) and timesheet entries (Plaintiffs Exhibits 218, 219) the court concludes that the "dried shell structure" was not completed until December 14, 2013.

The amounts actually billed by the plaintiff through that date, December 14, 2013, totaled $312,257.79. (Defendants Exhibit 64). Despite the confusion

4 regarding the level of work which was to be performed for an amount not to exceed $275,000, as discussed above, there is no dispute that the parties understood that at least a "dried shell structure" should have been completed at a cost not to exceed $275,000. The court finds that the cost to perform that function did exceed the agreed to price by $37,257.79.

By early December, both parties understood that the plaintiff would continue to perform construction services beyond merely completing a "dried shell structure." Although the defendants did not inform the plaintiff of their specific plans, they intended to continue to utilize the plaintiffs services until a certificate of occupancy was obtained, and then proceed to initiate legal action to attempt to recover any funds paid to the plaintiff in excess of $275,000.

The plaintiff, and his subcontractors, continued to perform construction services for the defendants after December 14, 2013, the date the "dried shell structure" was completed. That additional work was billed at $32 per hour for all labor performed. In a similar manner as before, the plaintiff continued to invoice the defendants on basically a biweekly basis. The defendants continued to pay the plaintiff up until the invoice which was dated May 4, 2014. (Plaintiffs Exhibit 325). The certificate of occupancy for the defendants' home was issued on or about May 15, 2014.

The total amount billed to the defendants for labor and material performed after December 14, 2013 (the date the "dried shell structure" was completed) was $327,250.98.(Defendants' Exhibit 64). Without adjustment, as discussed below, the total amount the plaintiff would be entitled to for the

5 construction services performed would equal $602,250.98. ($327,250.98 + $275,000). The defendants have paid a total of $601,195.75 to either the plaintiff or direct payments to two of the plaintiffs subcontractors. (Defendants Exhibit 65).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paffhausen v. Balano
1998 ME 47 (Supreme Judicial Court of Maine, 1998)
Parker v. Ayre
612 A.2d 1283 (Supreme Judicial Court of Maine, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Sweet v. Breivogel, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sweet-v-breivogel-mesuperct-2017.