Swartzlander v. United States

CourtUnited States Court of Federal Claims
DecidedMarch 29, 2019
Docket15-1567
StatusPublished

This text of Swartzlander v. United States (Swartzlander v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swartzlander v. United States, (uscfc 2019).

Opinion

In the United States Court of Federal Claims No. 15-1567L (Filed: March 29, 2019)

***************************** * Fifth Amendment Taking; MARY SWARTZLANDER, * Statute of Limitations; Accrual of * Plaintiff, * Cause of Action; Erosion; * Stabilization Doctrine; Accrual v. * Suspension Doctrine. * THE UNITED STATES, * * Defendant. * * * * * * * * * * * * * * * * * * * * * * * * ** * * * * *

Marianne Dugan, 259 East 5th Avenue, Suite 200-D, Eugene, OR 97401, for Plaintiff.

Jean E. Williams, Jeffrey H. Wood, and William J. Shapiro, U.S. Department of Justice, Environment and Natural Resources Division, 501 I Street, Room 9-700, Sacramento, CA 05814, and John P. Tustin, Emily M. Meeker, and Cullen Saint-Real Sherburn, United States Department of Justice, Environment and Natural Resources Division, P.O. Box 7611, Washington, D.C. 20044-7611, for Defendant. _________________________________________________

OPINION AND ORDER __________________________________________________

WILLIAMS, Senior Judge.

Plaintiff, Mary Swartzlander, claims that the Bonneville Power Administration (“BPA”) effected a taking of her property and seeks just compensation. Specifically, Plaintiff claims that the BPA, which owned property directly across the Chickahominy Creek from Plaintiff’s property, undertook a wetland restoration project on BPA’s side of the creek that deflected the creek flow towards Plaintiff’s bank, causing erosion on Plaintiff’s land. Defendant moved to dismiss this action as time-barred under the six-year statute of limitations in 28 U.S.C. § 2501, arguing that Plaintiff knew or should have known that this erosion was occurring and causing permanent harm more than six years before she filed suit on December 23, 2015.1 For the reasons stated below, Defendant’s motion is granted.

1 In the alternative, Defendant argues that the alleged impacts from its restoration project were not foreseeable, and that Oregon Revised Statute § 496.270(3) precludes liability for damages Findings of Fact2 The Wetland Restoration Project In 2001, BPA entered into a contract with the Siuslaw Soil and Water Conservation District (“Conservation District”), to complete a wetland restoration project along BPA’s creek banks. David Eisler, a project manager with the Conservation District, spearheaded the project, which included three primary elements: (1) digging an overflow channel and pond on the northern end of BPA’s property to reduce flows on the creek, (2) clearing shrubs and replanting native vegetation in an elk meadow on BPA’s property, and (3) planting native riparian plants along a small portion of the banks of BPA’s property to reduce erosion. Tr. 576-77. According to the wetland restoration project proposal, the purpose of the project was to restore “freshwater wetlands in the floodplain of Chickahominy Creek . . . through restoration of hydrological conditions, control of invading introduced plants . . . and reestablishment of native plant species,” as well as to “reduce sediment load in Chickahominy Creek by revegetation of eroding vertical banks, enhance habitat conditions for amphibians, and improve fish habitat in Chickahominy Creek.” Def.’s Mot. Ex. C-1, at 002152. In addition, the project entailed, in part, an initial excavation of BPA’s streambanks in order to “divert high water flows from Chickahominy Creek to an excavated basin . . . to create a seasonal wetland overflow area[,]” where “[t]he diversion channel [would] be planted with native vegetation in order to prevent erosion and downcutting.” Id. at 002153. The entrance to the referenced basin was located upstream of all riparian planting and revegetation, according to the proposal site plan diagram. Id. at 002156-58. A second excavation was to take place to reconnect an old stream channel to the creek enabling salmon to escape to the old stream channel. Id. at 002153. Moreover, “[l]arge woody debris [would] be placed in Chickahominy Creek at the upstream and downstream openings of the excavation to prevent erosion or blockage.” Id. Proposed riparian buffer tree planting and streambank revegetation included “[a]pproximately 500 feet of streambank on the west side of the creek . . . planted in conifer and deciduous trees” as well as “[w]illow cuttings and ninebark . . . planted on the eroding streambank.” Id. The local Siuslaw Conservation District undertook the project in cooperation with the Oregon Department of Fish and Wildlife (“ODFW”). George Westfall, a Natural Resource Specialist at ODFW, provided substantive feedback on the proposed project, which the project manager for the Water District incorporated into the final project design. Tr. 570-71. Mr. Westfall, on behalf of ODFW, concluded that the project would benefit Oregon’s wildlife resources by

resulting from a fish and wildlife habitat improvement project done in cooperation and consultation with the pertinent Oregon state authorities. Because the Court concludes that the action is time- barred, it does not address Defendant’s alternate grounds for dismissal. 2 These findings are derived from the record developed at an evidentiary hearing as well as from depositions and exhibits to the parties’ motion papers. Additional findings of fact are in the Discussion.

2 improving fish and wildlife habitats in Chickahominy Creek. Tr. 517. According to a local Siuslaw Conservation District monitoring report from November 2003, the wetland project as proposed was completed in September 2001, with additional plantings completed in February 2002, and replanting planned for February 2004. Def.’s Mot. Ex. A-1, at 000108. Erosion on Plaintiff’s Property On June 26, 2002, Plaintiff, a nurse, purchased 5.58 acres of property situated on the eastern bank of Chickahominy Creek opposite BPA’s property to use as her home, as well as a place for her animals, including llamas and goats, to live and graze. Def.’s Mot. Ex. D, at 000438-39; Def.’s Mot. Ex. G, at 001941; Tr. 74; Swartzlander Dep. 26. Chickahominy Creek runs along the entire western border of Plaintiff’s property. Prior to the purchase, Plaintiff visited the property in June 2002, and spoke with the then owner Rebecca Comer, who had lived on the property since 1994. Tr. 216-17; Swartzlander Dep. 17. When asked if Plaintiff had discussed erosion with the previous property owner, Plaintiff testified that at the time she did not know what the word erosion meant, but that Ms. Comer had informed her she had been throwing grass clippings into an area along the southern portion of the property to fill in the streambank. Tr. 156-58. During this 2002 visit, Plaintiff observed this southerly bank and “it looked like it was kind of a slope-down lower than . . . the bank north of that.” Swartzlander Dep. 27. Plaintiff testified that looking back at what Ms. Comer had told her and what she observed in 2002, it would be logical to conclude that Ms. Comer was taking steps to alleviate ongoing erosion. Id. at 28. At the time of purchase, Plaintiff was aware that the property was situated in a flood zone. Tr. 279. Plaintiff also understood that her property’s western border is legally defined as the center of Chickahominy Creek. The title report, which was prepared during Plaintiff’s acquisition of the property, included a title insurance policy that excluded from coverage: Any adverse claim based upon the assertion that some portion of said land has been removed from or brought within the boundaries thereof by an avulsive movement of the Chickahominy Creek or has been formed by the process of accretion or reliction or has been created by artificial means or has accreted to such portion so created. Tr. 155-56. Plaintiff did not understand this paragraph, but at some point, she wrote “creek line move?” on the document. Tr. 156.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young v. United States
529 F.3d 1380 (Federal Circuit, 2008)
MacLean Iii v. United States
454 F.3d 1334 (Federal Circuit, 2006)
Hopland Band of Pomo Indians v. The United States
855 F.2d 1573 (Federal Circuit, 1988)
Holmes v. United States
657 F.3d 1303 (Federal Circuit, 2011)
Cotton Land Co. v. United States
75 F. Supp. 232 (Court of Claims, 1948)
Mildenberger v. United States
643 F.3d 938 (Federal Circuit, 2011)
Banks v. United States
741 F.3d 1268 (Federal Circuit, 2014)
Fallini v. United States
56 F.3d 1378 (Federal Circuit, 1995)
Boling v. United States
220 F.3d 1365 (Federal Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Swartzlander v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swartzlander-v-united-states-uscfc-2019.