Swank v. Barnum

65 N.W. 722, 63 Minn. 447, 1896 Minn. LEXIS 22
CourtSupreme Court of Minnesota
DecidedJanuary 20, 1896
DocketNos. 9824-(163)
StatusPublished
Cited by1 cases

This text of 65 N.W. 722 (Swank v. Barnum) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swank v. Barnum, 65 N.W. 722, 63 Minn. 447, 1896 Minn. LEXIS 22 (Mich. 1896).

Opinion

START, C. J.

The original complaint alleged that, between November 1, 1898, and May 12, 1894, the plaintiff performed work, labor, and services for the defendant, at his request, of the reasonable value of $12,496.54, which he promised to pay, and that he has paid thereon $7,682.47. To recover the balance, $4,814.07, this action was brought. The answer put in issue the reasonable value of the work. The plaintiff, within 20 days next after the answer was served, was by order of the court permitted to, and did, amend his complaint by alleging three causes of action: First, for services performed between the dates named, upon an express promise to pay $6,000 therefor; second, for services between such dates, upon a like promise to pay therefor $998.40; third, for labor performed within the same dates, at the request of the defendant, of the reasonable value of $5,498.14. The amended complaint also alleged payments generally upon the several claims to the amount of $7,682.47, and demanded judgment for the balance, $4,814.07. The answer denied that the defendant agreed to pay any particular sum for any of the services and labor, or any sum, except what the same was reasonably worth, and put such reasonable value in issue. No claim was made in the answer that the work, or any part of it, was not done and completed according to contract. Verdict for the plaintiff for the full balance claimed, and the cause comes to this court on appeal from an order denying the defendant’s motion for a new trial.

1. The defendant’s first alleged error is that the amendment was not within the discretion of the. court, because its effect was to add two new causes of action. The amended complaint did not substantially change the claim of the plaintiff set forth in the original complaint, and demands judgment for the same balance alleged to be due to the plaintiff for work and services. The amendment simply subdivides the original claim, and alleges that for portions of the work the defendant promised to pay a specific sum and for the balance its reasonable value. The court was authorized, in its discretion, to allow the amendment, and the discretion was not abused. Again, the plaintiff was entitled to make the amendment as a matter of right, as it was made within 20 days after the answer wTas served. G-. S. 1894, § 5265. There could be no error [449]*449on the part of the court in permitting the plaintiff to do what he had a legal right to do without such permission.

2. The plaintiff's first cause of action, as shown by his bill of particulars and the evidence, related to the construction of a ditch from Lake Lambert to Lake Vadnais for the purpose of draining the former, and thereby improving the defendant's farm, which bordered upon and nearly surrounded Lake Lambert. There was an abandoned conduit between the lakes, and the defendant caused a survey and profile of the proposed ditch along this old conduit to be made. The profile indicated the original level of the bed of the old ditch or channel and the level of the bottom of the ditch to be excavated, and called for the construction of a ditch 5,963 feet in length, — 1,776 lineal feet thereof to be a covered one, or a sluiceway, 8 feet wide at the top and bottom. The balance was to be an open ditch, 8 feet in width at the bottom, with sloping sides. The plaintiff's evidence tended to show that the parties hereto entered into a verbal contract whereby the plaintiff agreed to construct the ditch according to the profile for $6,000, to be done under the supervision and direction of the defendant’s civil engineer; that he entered upon the execution of the work, and, as it progressed, springs and quicksand were encountered at points along the line of the open ditch, and it was agreed that a sluiceway should be substituted for the open ditch at such points, and the plaintiff was to be paid extra for such sluiceway at the same pro rata as under the' contract; and that the plaintiff did put in 1,970 lineal feet of such extra sluicing. The plaintiff claimed to recover under the first count in his complaint $6,000, the contract price for constructing the ditch, and under the third count thereof the reasonable value of constructing the extra sluiceway, $1 per lineal foot.

The plaintiff claimed upon the trial that it cost just as much to make the earth excavation for the sluiceway as it would have cost to have constructed the open ditch at the points where the extra sluiceway was put in, although only about one-half as many cubic yards of earth were removed, for the reason that the extra cost of making the sides of the ditch perpendicular for the sluice-way offset any gain made in removing a less quantity of earth. A witness was called as an expert, who gave testimony, on his direct examination, tending to support this claim of the plaintiff, and to [450]*450establish the fact that the plaintiff gained nothing in the cost of earth excavation by the substitution of the extra sluiceway for the open ditch, and that it was worth $1 a lineal foot to construct the sluiceway. On the cross-examination of this witness the defendant asked.this question: “Now, assuming that the amount of excavation called for under the original contract between these parties, that the open ditch was 16,406 cubic yards of earth excavation and 1,776 lineal feet of sluiceway, what percentage of the cost of doing that, making that same ditch as it was made, would, in your judgment, be added by making it with the sluice, instead of with the open ditch as originally contemplated? (Objected to as incompetent, immaterial, and not proper cross-examination.)” Two other questions of the same general character were asked the witness, to which the same objections were made. The court sustained the objections to each question, and defendant excepted. These rulings are the subject-matter of the defendant’s assignments of error 13 to 15, inclusive.

If it was competent for the defendant to show the percentage of the increase in the cost of constructing the ditch with the extra sluiceway substituted for the open ditch over the cost of constructing it as originally planned, for the purpose of showing the corresponding percentage of increase in the contract price to which the plaintiff would be entitled, still the defendant could not show this on the cross-examination of this witness. On the direct examination the witness was questioned as to the cost of excavating the open ditch where the extra sluiceway was put in, as compared with that required for the sluiceway, and as to the reasonable value of putting in the latter. This comparison of cost was limited to the part of the ditch where the extra sluiceway was put in. The de.fendant’s question included the entire length of the ditch, which the witness had not examined, and was not proper cross-examination; and, further, the witness was not shown to be competent to give an opinion as to the cost, comparative or otherwise, of the entire ditch. Again, the purpose of the question was not to show the percentage of increase of the contract price to which the plaintiff was entitled by reason of a corresponding percentage of increase in the cost of the work by reason of the change made in the plan of the same, — the only purpose for which the evidence was com[451]*451petent. The defendant denied that there was any existing express contract to pay $6,000, or any other sum, for the work, but claimed that the whole work was done under an implied contract to pay the reasonable value of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Todd v. Betttngen
113 N.W. 906 (Supreme Court of Minnesota, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
65 N.W. 722, 63 Minn. 447, 1896 Minn. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swank-v-barnum-minn-1896.