Swan v. Bern Mas Enterprises, Inc.

299 So. 2d 845, 1974 La. App. LEXIS 3202
CourtLouisiana Court of Appeal
DecidedAugust 1, 1974
DocketNo. 6277
StatusPublished
Cited by1 cases

This text of 299 So. 2d 845 (Swan v. Bern Mas Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swan v. Bern Mas Enterprises, Inc., 299 So. 2d 845, 1974 La. App. LEXIS 3202 (La. Ct. App. 1974).

Opinions

SCHOTT, Judge.

Pursuant to a contract entered into on December 3, 1969, between plaintiff as contractor and defendant Bern Mas as owner, plaintiff for the price of $56,994 was to furnish plumbing labor and materials at an apartment complex being constructed by Bern Mas. This litigation commenced with a petition in which plaintiff claimed damages of $5,207.60 on allegations that during construction, and while he was performing his contract, defendant caused heavy equipment to be driven over sewer and gas lines already installed by plaintiff, necessitating the reconstruction of the two lines at a cost to plaintiff of $1,095.38 for the sewerage line and $1,368.-77 for the gas line. Plaintiff also alleged that during the course of his performance of the contract and while the building was in the custody of defendant vandalism was perpetrated upon the premises which necessitated his replacement of copper pipe and various fittings at a cost of $2,743.25. Made a co-defendant as far as the foregoing claims are concerned was Aetna Insurance Company which had written a policy of builder’s risk insurance, protecting Bern Mas against the losses claimed.

On October 22, 1970, a supplemental petition was filed in which a balance of $6,149.40 was claimed on the original contract price, together with attorney’s fees as provided by the contract, on allegations that plaintiff had performed all of the work called for, that he had delivered to Bern Mas the necessary affidavit of completion and that he had not been paid the balance although the requisite delay of 31 days had run.

In response defendants denied liability for claims asserted in the original petition, and in response to the claim asserted in the supplemental petition Bern Mas alleged that plaintiff had performed his work improperly and had caused damage to defendant by delaying the entire project. Defendant alleged that it was required to “dig out and repair couplings on main water line at an expense of $400; remove and repair leaks in damaged sheetrock, caused by faulty installation of traps in bathrooms, $850,” and had incurred substantial expense in loss of water because of the defective couplings in the water main installed by plaintiff.

In the trial court the plaintiff was awarded a judgment against Bern Mas and Aetna for $1,056.49 on the claims in the original petition and for $5,289.69 with attorney’s fees of $1,057.92 against Bern Mas on the claim in the supplemental petition. This judgment followed the recommendation of the Commissioner of the Civil District Court for the Parish of Orleans before whom the case was tried and from whom the trial judge received an extended report of his findings.

From the judgment plaintiff alone has appealed.

In his report, the Commissioner treated the sewer and gas lines together and made the following disposition of this portion of plaintiff’s claim:

“Taking the sewer and gas lines together your commissioner is of the opinion that plaintiff failed to sustain the burden of proof in support of his contention that damage to these two lines was caused by the negligence of defendant or its employees. Plaintiff offered no corroborating evidence in support of his statements as to causation. And even assuming, for the sake of argument, that by a preponderance of evidence it could have been concluded that defendant was negligent, plaintiff has failed to substantiate the claims asserted by presentation of legal proof. The evidence presented was nothing more than self-serving documents which lacked necessary proof through the presentation of permanent records which were available but not produced.
“Your commissioner is of the opinion that plaintiff initially recognized these repairs as his obligation under the contract. He did in fact notify defendant, [848]*848in writing, of the amount that it cost his company to do the corrective work to the sewer line, and he requested of defendant to exert care in using heavy equipment over same. Also significant is the fact that some two months elapsed from the time that the corrective work was performed on the sewer and gas lines to the time when plaintiff billed defendant therefor on May 18, 1970. Your commissioner is of the opinion that when defendant questioned plaintiff’s bill dated May 12, 1970, which was submitted for the repairs caused by vandalism, plaintiff then decided to send bills for the sewer line and gas line rework.”

From our examination of the record we are convinced that the Commissioner fell into error in his considering the sewer and gas'lines as a common problem when the facts show that these items were completely independent with respect to cause as well as discovery and handling by the parties.

Plaintiff began his work on the contract on December 13, 1969, and on January 30, 1970, the sewer line was inspected and approved by the Sewerage & Water Board of New Orleans. On March 11, 1970, in a letter to defendant plaintiff discussed various complaints concerning the various plumbing facilities which had already been installed, and said the following:

“I would like to call your attention that this line was layed and installed to your specifications and grade lines were set by your superintendent.
* * * * *
“The heavy equipment that got bogged down on top of the main sewer ditch sunk the end of the line by the cabana U/2 inches. This line had to be removed and re layed.
“All the above work has been corrected by our company and re layed and inspected by your superintendent at a cost to our company of $589.00.
“I am going on record asking you to be extra careful with the sewer line and gas line when using heavy equipment, please use some precaution to protect the lines.
“If there is any more trouble of breaking or sinking of gas and sewer lines, this cost will have to be assumed by your company.”

Plaintiff’s records show that he had performed the work of replacing the sewer line between February 17 and February 27, 1970, and that the line was reinspected and approved by the Sewerage & Water Board on March 4.

Notwithstanding his letter of March 11, 1970, on May 18 plaintiff made his first demand for $1,095.58 for replacing this sewer line. His testimony, though vague, was to the general effect that after the sewerage line had been initially installed defendant had permitted heavy equipment to pass over the soft ground over the line causing the line to sink and to lose the proper grade even though line’s approval by the Sewerage & Water Board necessarily meant that it had been installed at the proper grade in the first instance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Livingston Roofing Co. v. E. E. Rabalais & Son, Inc.
401 So. 2d 1047 (Louisiana Court of Appeal, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
299 So. 2d 845, 1974 La. App. LEXIS 3202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swan-v-bern-mas-enterprises-inc-lactapp-1974.