Sutherland v. Troy & Boston Railroad

8 N.Y.S. 83, 28 N.Y. St. Rep. 201, 54 Hun 639, 1889 N.Y. Misc. LEXIS 2182
New York Supreme Court·Decided December 11, 1889·Published·Cited by 1 cases

Opinion

Landon, J.

The movement of trains upon the defendant’s railroad was controlled by the train dispatcher at Troy by means of telegrams sent to the operators at the several stations. The train dispatcher performed the service of the master. Johnson was the defendant’s operator at Petersburgh Junction. He performed a servant’s service, and was a fellow-servant of Sutherland, the plaintiff’s intestate. Sutherland was the engineer in charge of the locomotive drawing train Ho. 1 from Troy easterly, successively past stations Hoosick Falls, Hoosick, Petersburgh Junction, towards Hortli Pownall and" stations further east. Train Ho. 1, an express freight train, was two hours behind its schedule time. It readied and passed Petersburgh Junction at 8: JO A. M. At 6:55 A. m., Johnson, the defendant’s operator at Petersburgh Junction, received from the train dispatcher the following order: “Flag and hold train 1 for orders.” Johnson, as was his duty, thereupon put out a red flag. Ho train is permitted to pass a red flag. Johnson, at his instrument, next heard an order to train Ho. 2 to meet train Ho. 1 at Peters-burgh Junction. Train 2 was at or beyond some station east of Petersburgh Junction, and was moving west. At 7:19 A. M. train Ho. 2 reached Peters-burgh Junction, and stopped. Hext Johnson received from the train dispatcher an order for train 2 to meet train 1 at Hoosick, a station one and a half miles westof Petersburgh Junction. The like order was sent by the train dispatcher to the operator at Hoosick Falls, the station next west of Hoosick, for train Ho. 1. , Johnson thereupon took down the red flag at Petersburgh Junction, and train Ho. 2 moved on west, and took the side track at Hoosick, and stopped. Train Ho. 1 next reached Hoosick, and, as there was no signal for it to stop, it passed the station and train Ho. 2 without stopping. Johnson did not replace the red flag at Petersburgh Junction. He supposed that the order to “flag and hold Ho. 1 for orders” was for the purpose of enabling Hos. 1 and 2 to pass each other at Petersburgh Junction, and, since those trains had subsequently been ordered to pass each other at Hoosick, he assumed that the order had been superseded by the later order, and be therefore did not replace the red flag. At least, such is the finding of the jury upon evidence sufficient to support it.

[85] We held, upon a former appeal, that it was a question for the jury, upon the evidence, whether the defendant was guilty of any omission of duty in not taking additional precautions to bring the knowledge of its order to the engineer of train Ho. 1. 46 Hun, 372. The evidence upon the retrial is in this respect unchanged, and we adhere to the ruling. Train Ho. 1 was stopped by the dispatcher’s order at Hoosick Falls. The dispatcher might there have told the engineer where to meet Ho. 6, or where next to stop for ■orders. It was about 7:25 A. m. when train Ho. 2 passed Petersburgh Junction, westerly, to meet train Ho. 1 at Hoosick. Train Ho. 1 did not reach Petersburgh Junction until 8:30 following, having-been delayed, as the dispatcher knew, by the inability of the locomotive to haul the entire train over and up grade there, and thus was compelled to separate it in two divisions.

The defendant contends that Sutherland, the engineer, oughtto have stopped at Petersburgh Junction, notwithstanding "the absence of the red flag. This contention is based upon the fact that, acbording to the regular schedule, passenger train Ho. 33, moving east, and freight train Ho. 6, moving west, were appointed to meet each other at Petersburgh Junction at 8:52 a. m., and that Sutherland knew this. The answer, the sufficiency of which it was for the jury to consider, is that, notwithstanding the schedule, the movement of all these trains was controlled by the train dispatcher at Troy. He knew where trains Ho. 33 and Ho. 6 were, whether on or behind time, and it was his duty to give to every train the proper orders. For Sutherland to stop at Petersburgh Junction without orders was for him to interfere with the dispatcher’s business and directions.

The defendant further urges that Sutherland ran train Ho. 1 from Hoosick Falls, past Hoosick and Petersburgh, at a rate of speed forbidden by a rule of the company. The rule relied upon is: “The speed of freight trains must not exceed fifteen miles per hour, exclusive of stops, except in cases where schedules are run faster than 15 miles an hour.” This means that no more than 15 miles shall be run in an hour of actual running time,—not that at no time within the hour shall the highest speed exceed 15 miles an hour. From Hoosick Falls to the place of collision is 7-| miles. Sutherland ran train Ho. 1 faster than at the rate of 15 miles an hour after he made a successful start from Hoosick Falls. It is plain that, in starting the train and in approaching its stop, the train must run much less than at the rate of 15 miles an hour, and therefore to make 15 miles in an hour it must run faster than at that rate some portion of the distance between stops. The testimony showed that it was well understood that, when a freight train was running down grade, it would run faster than at that rate. From Hoosick Falls to the place of the collision it is both up and down grade, with a considerable portion nearly level. Sutherland probably availed himself of favorable grades to make up for some of the time he had lost at Hoosick Falls. As the collision occurred before the 15 miles east of Hoosick Falls were completed, we cannot know whether this rule was violated.

Free access — add to your briefcase to read the full text and ask questions with AI

Sutherland v. Troy & Boston Railroad, 8 N.Y.S. 83, 28 N.Y. St. Rep. 201, 54 Hun 639, 1889 N.Y. Misc. LEXIS 2182 (N.Y. Super. Ct. 1889).

8 N.Y.S. 83 (Sutherland v. Troy & Boston Railroad) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McChesney v. Panama Railroad
21 N.Y.S. 207 (New York Supreme Court, 1892)