Sustar v. Bambrick Bros. Construction Co.

162 S.W. 730, 179 Mo. App. 495, 1913 Mo. App. LEXIS 273
CourtMissouri Court of Appeals
DecidedDecember 31, 1913
StatusPublished
Cited by3 cases

This text of 162 S.W. 730 (Sustar v. Bambrick Bros. Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sustar v. Bambrick Bros. Construction Co., 162 S.W. 730, 179 Mo. App. 495, 1913 Mo. App. LEXIS 273 (Mo. Ct. App. 1913).

Opinion

ALLEN, J.

This is an action by plaintiff to recover for personal injuries received by him, while engaged as a servant of defendant, alleged to have been sustained through the negligence of the latter. Plaintiff recovered and the defendant prosecutes the appeal.

On July 24, 1911, plaintiff was in the employ of ■defendant, assisting in the construction of a certain sewer in the city of St. Louis. At the time of his injury, he was working in a trench which was being dug ■by means of the operation of what is known as a sewer machine. The latter consisted of a certain “carriage” carrying buckets, and was operated upon wheels along an elevated track extending along and above the top of the sewer, some fifteen feet or more above plaintiff. This track was supported by a sort of trestle which stood upon timbers laid across the sewer. The trestle and track extended for some distance along the ■sewer; and the trench was dug by filling large buckets therein, which were hoisted and conveyed by the carriage along the elevated track and dumped. The rails of the elevated track were held in place by certain ■crossbeams, the upper edges -thereof being a little lower than the tops of the rails, in order that the flanges of the wheels of the carriage would not strike them.

On the day plaintiff received his injuries he was working at certain concrete work which was being placed in a portion of the sewer which had been dug. The trench was being dug, ahead of him, and the buckets containing the material hoisted therefrom were being carried along from time to time by the carriage [502]*502directly over the place where plaintiff was working. Upon the occasion in question the bottom of one of these buckets, containing a large rock weighing it is said some eighty or ninety pounds, was permitted to strike one of the crossbeams of the elevated track, causing this rock to fall from the bucket, and which, after striking one of the crossbeams, fell upon plaintiff while engaged in his work below, striking him upon the head and inflicting very serious and permanent injuries.

■To an understanding of the assignments of negligence upon which the case was tried some further explanation of the operation of the sewer machine is necessary. The carriage was operated along the elevated track, and the buckets were raised and lowered,, by an engine situated some distance’ down the track, and which performed both of these operations by means of cables running therefrom to the carriage. A signal man stood upon the platform of the carriage and gave signals-to the engineer with respect to the hoisting of the buckets, the stopping of the same at the proper height and the operation of the carriage along-the track. "When the buckets were filled in the. trench below, a signal was given to the engineer to raise them. When they had been raised to the proper height it was the duty of the signal man to signal the engineer in order to stop their upward movement. It seems that there was a ratchet arrangement provided,, to prevent the buckets ‘from being raised too high and likewise from falling back after they had been elevated. After the signal man had. signalled the engineer to-check the upward movement of the buckets, it was the duty'of the former to throw a lever to cause what is called the “dogs” to catch in the teeth of the ratchet wheels to prevent the buckets from ascending higher or from falling back. Then it was his duty to signal the-engineer to release a certain brake and convey the carriage along the track in order to dump the buckets.

[503]*503There was expert testimony to the effect that the total possible clearance that could be arranged to be had between the bottom of the buckets and the crossbeams was something like two feet; though there was testimony that as this particular machine was then “rigged up” and operated the largest possible clearance was a foot or fourteen inches. It appears that each of these large buckets had a bail, to which was welded a strip of iron with a holt in it to receive a hook which was fastened to the cable. It seems that defendant was using eight of these buckets, of almost exactly the same size, two of them being hoisted of lowered at a time, and the others being down in the trench to be filled. It appears that the hooks for lifting the buckets were attached to the cable by means of clamps and that the height to which the buckets might be raised, above the crossbeams depended somewhat upon the location of these clamps. There was also testimony, by an expert witness of defendant, that the ratchet arrangement above mentioned, to hold the buckets in place after they had been elevated, was such that if one of the “dogs” should just miss one “tooth” of the ratchet the bucket would drop back a distance of about eight inches before the “dog” would catch the next “tooth” and sustain it.

The cause was tried .upon three of the assignments of negligence charged in the petition, and it is unnecessary to notice the others therein contained.

One assignment of negligence is that the defendant negligently employed and retained an incompetent and unskilled signal man, whose duty it was to signal the engineer in lifting and conveying the buckets above mentioned. And it is charged that on the occasion in question the said signal man signalled the engineer to cause a bucket to be started along the track, before it had been elevated to its proper position to be so moved, and when it was hanging so low that it [504]*504would strike and come in contact with the crossbeams, whereby the rock was caused to fall and injure plaintiff. And it is charged that the signal man performing said duties at the time was not reasonably fit and qualified to perform the same; and that defendant negligently retained him in its employ, when defendant knew, or by the exercise of ordinary care would have known, of his unfitness and incompetency.

Another assignment of negligence is to the effect that the method or plan which defendant was pursuing at the time of plaintiff’s injury, in conveying the buckets along the track, and over the sewer, was not a reasonably safe one; and that it was not reasonably safe for plaintiff to work in the sewer while such buckets were being so conveyed along and over the same, for the reason that they, as so operated, were likely to tilt and swing violently and to strike á crossbeam and spill their contents. And that defendant knew, or by the exercise of ordinary care would have known that such plan was not reasonably safe.

A third assignment of negligence is that the conveying machine, above mentioned, then used and operated by defendant, “was so negligently constructed, arranged and used, and that the said crossbeams were so negligently fixed, placed and maintained by defendant, that the space between the bottom of said buckets and the said braces, when said buckets were conveyed along said track, was too small, so that there was great danger, in the swinging or tilting of said buckets, of the bottom or lower end of said buckets striking the said braces and spilling the contents and injuring plaintiff.” And it is charged that defendant knew, or by the exercise of ordinary care would have known, thereof.

The answer, after the court had sustained a motion directed to a part thereof, and as it stood when the cause went to trial, was a general denial.

[505]*505The evidence shows that at the time of plaintiff’s injury one Fred Fisher was acting as defendant’s signal man on the carriage above mentioned. Just how long he had been performing such duties is a question as to which the evidence is conflicting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. FW Woolworth Company
328 S.W.2d 684 (Supreme Court of Missouri, 1959)
Burns v. R. L. McDonald Manufacturing Co.
252 S.W. 984 (Missouri Court of Appeals, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
162 S.W. 730, 179 Mo. App. 495, 1913 Mo. App. LEXIS 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sustar-v-bambrick-bros-construction-co-moctapp-1913.