Susanna D. Smith v. Wells Concrete Products Co.

CourtCourt of Appeals of Minnesota
DecidedFebruary 2, 2015
DocketA14-644
StatusUnpublished

This text of Susanna D. Smith v. Wells Concrete Products Co. (Susanna D. Smith v. Wells Concrete Products Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Susanna D. Smith v. Wells Concrete Products Co., (Mich. Ct. App. 2015).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A14-0644

Susanna D. Smith, et al., Respondents,

vs.

Wells Concrete Products Co., Appellant.

Filed February 2, 2015 Reversed Reyes, Judge Dissenting, Chief Judge Cleary

Faribault County District Court File No. 22CV12299

Paul D. Peterson, Jason L. DePauw, Harper & Peterson, P.L.L.C., Woodbury, Minnesota (for respondents)

James T. Martin, Julian C. Janes, Gislason, Martin, Varpness & Janes, P.A., Edina, Minnesota (for appellant)

Considered and decided by Johnson, Presiding Judge; Cleary, Chief Judge; and

Reyes, Judge.

UNPUBLISHED OPINION

REYES, Judge

In this appeal from a judgment following a jury trial of respondents’ negligence

claims, which arose out of a construction workplace injury to an independent contractor,

appellant argues that (1) the district court erred by denying its motion for judgment as a matter of law because appellant did not owe a duty of care to respondent Susanna Smith,

an independent contractor hired by appellant; (2) a new trial is required because the

district court allowed evidence of remedial measures, instructed the jury on premises

liability and failed to instruct on primary assumption of the risk, and because the verdict

is against the great weight of the evidence; and (3) the district court erred by denying

appellant’s motion for a collateral-source offset. Because we agree with appellant that it

did not owe a duty of care to respondent Susanna Smith and that respondents failed to

prove causation, we reverse.

FACTS

This case arises from a worksite accident that occurred on December 19, 2008.

Respondent Susanna Smith (Smith)1 was a subcontractor hired by appellant Wells

Concrete Products Co. (Wells) to paint its new production facility. Smith fell from a

height of ten to twelve feet while she was painting and suffered substantial injuries.

Following a four-day trial, a jury found that Wells was negligent and that its negligence

was the direct cause of Smith’s accident. The jury also found Smith negligent. The jury

apportioned 60% of the fault to Wells and 40% to Smith.

The production facility where the accident took place is owned and operated by

Wells. Wells served as its own general contractor during the construction of its new

facility. Wells had its own employees working on the project and also hired various other

subcontractors to work on site. Smith was hired by Wells to paint the facility.

1 Respondent William Smith’s claim of loss of consortium is not at issue on appeal.

2 At the time Smith was hired by Wells, she had twelve years of experience as a

painter and was doing business as a sole proprietor. In the course of her career, Smith

regularly used a mechanized personnel lift, scaffolding equipment, paint-spraying

equipment, an extension ladder, and fall-protection devices such as a harness. Smith

received safety training from the Occupational and Safety Hazards Administration

(OSHA) regarding lifts and scaffolding equipment. Smith’s painting jobs were mostly

residential prior to her painting the Wells facility. Smith provided her own equipment for

the job at the Wells facility, with the exception of a scissor lift, which was provided by

Wells. Smith never requested any assistance from Wells nor did Smith ever request the

use of any other equipment. Smith felt she was qualified to do the paint job at the Wells

facility. Throughout the course of the job, Smith hired her brother and a few other people

to assist her.

Smith started painting the facility in November 2008. Smith was not required to

check in with anyone while she was at work. She was entirely free to do the work in any

way she thought appropriate; she was free to decide whether to hire others to assist her,

what equipment to use and when to use it, and when to start and end a workday. The

only requirement imposed by Wells was that there could be no individual working alone

at any time in the building in the event of an accident. Wells also provided guidelines as

to the type of paint, color of paint, and the dates for starting and completing different

phases of the job. Other than those provisions, Smith had discretion and authority to

complete the job the way she wanted. There was no supervision from Wells, and Smith

testified that she did not expect any supervision.

3 Smith began by painting the lunchroom area, bathroom, and the offices on the first

floor of the facility. Paul Nelson, a Wells employee, notified Smith when certain areas

were ready for her to start painting. Smith used the scissor lift provided to her by Wells

to paint some of these areas.

On December 18, Smith began painting the ceiling and walls above a narrow

corridor between the conference rooms and offices. Smith testified that she did not have

any discussions with Nelson regarding safety railings or any other safety-related issues

when she began painting these areas. The first floor rooms and the corridor were about

ten to twelve feet in height. The roof over the office area was covered in plywood to

form an “office deck,” so that people could stand on the plywood to work on the walls

and ceiling above the offices. Similarly, the roof area above the conference room was

also covered in plywood to form a “conference-room deck.” There were no railings

along the edges of the office deck or the conference-room deck overlooking the corridor.

The wall from the decks to the ceiling was an additional ten to twelve feet high. The

corridor below divided the conference-room deck and the office deck.

Smith did not believe that she could navigate the scissor lift, provided to her by

Wells, into the narrow part of that corridor. So instead, Smith decided to lay three planks

from her scaffolding set across the opening above the corridor. The scaffolding planks

made a makeshift bridge across the top of the corridor, connecting the conference-room

deck and office deck. Below the planks was a ten-foot drop to the ground that was

plainly visible. Despite testimony that the scissor lift could have been used in the

corridor, Smith maintains that the makeshift bridge was her only option to paint that area.

4 Smith testified that it appeared to her to be a “safe way to do the job.” Smith knew that,

when using scaffolding equipment, safety railings were required, even if she was just

using the planks from the scaffolding equipment. Smith did not put up any safety railings

on the makeshift bridge that she made out of her scaffolding planks. Smith testified that

at no point did she make a request to Wells for any kind of help or safety equipment.

On December 19, Smith, accompanied by her brother Jeremiah and her daughter

Christine, arrived at the facility to paint. Smith was still in the phase of her work that

required her to paint the roof deck areas above the office and conference room. The

accident happened soon after the three began painting. Jeremiah was spraying paint onto

the ceiling and walls, and Smith was rolling the paint onto the ceiling and the walls after

him. Christine had a small roller and was following behind Smith to roll the paint onto

the smaller areas when suddenly Christine heard a sound. She looked over and did not

see Smith. Christine was standing on the conference-room deck and observed that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schmanski v. Church of St. Casimir of Wells
67 N.W.2d 644 (Supreme Court of Minnesota, 1954)
Olson v. Hansen
216 N.W.2d 124 (Supreme Court of Minnesota, 1974)
Olmanson v. LeSueur County
693 N.W.2d 876 (Supreme Court of Minnesota, 2005)
Baber v. Dill
531 N.W.2d 493 (Supreme Court of Minnesota, 1995)
Sullivan v. Farmers & Merchants State Bank of New Ulm
398 N.W.2d 592 (Court of Appeals of Minnesota, 1986)
Sutherland v. Barton
570 N.W.2d 1 (Supreme Court of Minnesota, 1997)
Longbehn v. Schoenrock
727 N.W.2d 153 (Court of Appeals of Minnesota, 2007)
Balder v. Haley
399 N.W.2d 77 (Supreme Court of Minnesota, 1987)
Lamb v. Jordan
333 N.W.2d 852 (Supreme Court of Minnesota, 1983)
Kidwell v. Sybaritic, Inc.
749 N.W.2d 855 (Court of Appeals of Minnesota, 2008)
Jerry's Enterprises, Inc. v. Larkin, Hoffman, Daly & Lindgren, Ltd.
711 N.W.2d 811 (Supreme Court of Minnesota, 2006)
Schneider Ex Rel. Schneider v. Erickson
654 N.W.2d 144 (Court of Appeals of Minnesota, 2002)
Goodwin v. Legionville School Safety Patrol Training Center, Inc.
422 N.W.2d 46 (Court of Appeals of Minnesota, 1988)
Kidwell v. Sybaritic, Inc.
784 N.W.2d 220 (Supreme Court of Minnesota, 2010)
Conover v. Northern States Power Co.
313 N.W.2d 397 (Supreme Court of Minnesota, 1981)
Schweich v. Ziegler, Inc.
463 N.W.2d 722 (Supreme Court of Minnesota, 1990)
In Re Silicone Implant Insurance Coverage Litigation
667 N.W.2d 405 (Supreme Court of Minnesota, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Susanna D. Smith v. Wells Concrete Products Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/susanna-d-smith-v-wells-concrete-products-co-minnctapp-2015.