Superior Silica Sands, LLC v. Herman Grant Company, Inc.

CourtCourt of Appeals of Wisconsin
DecidedJuly 28, 2020
Docket2018AP002437
StatusUnpublished

This text of Superior Silica Sands, LLC v. Herman Grant Company, Inc. (Superior Silica Sands, LLC v. Herman Grant Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Superior Silica Sands, LLC v. Herman Grant Company, Inc., (Wis. Ct. App. 2020).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. July 28, 2020 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2018AP2437 Cir. Ct. No. 2016CV192

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT III

SUPERIOR SILICA SANDS, LLC, INDIAN HARBOR INSURANCE COMPANY AND CERTAIN UNDERWRITERS AT LLOYD’S,

PLAINTIFFS-APPELLANTS,

V.

HERMAN GRANT COMPANY, INC., COLUMBIA NATIONAL INSURANCE COMPANY AND THE CINCINNATI INSURANCE COMPANY,

DEFENDANTS-THIRD-PARTY PLAINTIFFS-RESPONDENTS,

MARKET & JOHNSON, INC., THE PHOENIX INSURANCE COMPANY, JEFFERIES V. ALSTON JR. D/B/A ALSTON EQUIPMENT COMPANY, DEF INSURANCE COMPANY, ALSTON ENVIRONMENTAL COMPANY, INC. D/B/A ALSTON EQUIPMENT COMPANY, GHI INSURANCE COMPANY, LAMSTEX MATERIAL HANDLING, LLC AND JKL INSURANCE COMPANY,

THIRD-PARTY DEFENDANTS, No. 2018AP2437

STATE FARM FIRE AND CASUALTY COMPANY,

INTERVENOR.

APPEAL from a judgment of the circuit court for Barron County: JAMES C. BABLER, Judge. Affirmed.

Before Stark, P.J., Hruz and Seidl, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3).

¶1 PER CURIAM. Superior Silica Sands (Superior) contracted with Market & Johnson (M&J) to construct a dry sand processing plant in Barron, Wisconsin (the Barron Plant). The parties’ contract contained a limited remedy provision, which limited the damages Superior could recover from M&J and its subcontractors. M&J, in turn, contracted with Herman Grant Company, Inc., (Herman Grant) to build a sand dryer for the Barron Plant.

¶2 Superior deemed the sand dryer to be deficient in several respects, and it ultimately commenced this lawsuit against Herman Grant and its insurers. The circuit court granted Herman Grant’s motion for a declaratory judgment and entered an order stating that, by virtue of the limited remedy provision, Superior was barred from “recovering damages for lost profits, repair costs, and loss adjustment and professional fees.” Superior then voluntarily dismissed its contract and tort claims against Herman Grant.

¶3 Superior now appeals, arguing the circuit court erroneously exercised its discretion by granting Herman Grant’s declaratory judgment motion.

2 No. 2018AP2437

Herman Grant disagrees, and it also argues, in the alternative, that Superior’s argument is moot because Superior voluntarily dismissed its contract and tort claims after the court granted Herman Grant’s declaratory judgment motion. We reject Herman Grant’s mootness argument. We agree with Herman Grant, however, that the court properly granted its declaratory judgment motion. We therefore affirm.1

BACKGROUND

¶4 Superior is in the business of mining sand that is used in the hydraulic fracturing process (i.e., “fracking”) to extract underground natural gas. In 2012, Superior entered into a “Design/Build Contract” with M&J for construction of the Barron Plant.

¶5 The Design/Build Contract contained a number of provisions that are relevant to the issues raised in this appeal. For instance, the Design/Build Contract provided that M&J could “subcontract portions of the Work to any Person without further approval by Owner.”2 The Design/Build Contract further provided that M&J was “solely responsible for the Work” and had “complete and sole responsibility” for its agents and subcontractors.

1 In the alternative, Herman Grant argues the circuit court’s ultimate dismissal of Superior’s contract and tort claims should be affirmed because Herman Grant was entitled to summary judgment on those claims, for various reasons. We need not address this argument, as we affirm the circuit court’s judgment on other grounds. See Turner v. Taylor, 2003 WI App 256, ¶1 n.1, 268 Wis. 2d 628, 673 N.W.2d 716 (court of appeals need not address all issues raised by the parties if one is dispositive). 2 The Design/Build Contract defined the term “Work” to mean “the work and services required in connection with the engineering, design, procurement, dismantling, transportation, storage, refurbishment, construction, upgrade, installation, interconnection, commissioning, start-up, testing, permitting, training for operation, supervision, and project management of the Work” described in the contract, including any equipment and machinery “required for and related to the foregoing.” The term “Owner” was defined to mean Superior.

3 No. 2018AP2437

¶6 The Design/Build Contract also contained a warranty provision, by which M&J warranted that the work would be “performed in accordance with the terms and conditions of this Contract” and would be “free from defects in design and workmanship.” The warranty provision further stated that, for a period of one year following the substantial completion of the work, M&J would re-perform any defective work and would repair or replace any defective equipment or materials, as long as Superior “deliver[ed] notice of an alleged deficiency or defect within a reasonable time after actual discovery thereof.” Such notice was required to be in writing and to be delivered in one of four specified ways. The warranty provision in the Design/Build Contract also stated that M&J would “cause all Subcontractor warranties to be assignable to [Superior] upon the expiration of the Warranty Period.”

¶7 The Design/Build Contract also contained a limitation of remedies provision, which stated the remedies set forth in the contract were “the sole and exclusive remedies of the Parties to this Contract for the liabilities of such Parties arising out of or in connection with the Work or this Contract, notwithstanding any remedy otherwise available at law or in equity.” The limitation of remedies provision further stated that neither M&J nor any subcontractor would be “liable for indirect, special, incidental, consequential or exemplary damages, including but not limited to, the loss of profits or revenue.”

¶8 M&J subcontracted with Herman Grant to design and build a sand dryer that was to be incorporated into the Barron Plant.3 In a Purchase Order Agreement dated June 1, 2012, Herman Grant agreed to perform its work “in

3 It is undisputed that Herman Grant qualifies as a subcontractor under the Design/Build Contract’s definition of that term.

4 No. 2018AP2437

accordance with the Prime Contract between [M&J] and [Superior] and all Plans, Drawings and Specifications including General and Special Conditions and Addenda.” It is undisputed that no direct contract exists between Herman Grant and Superior. It is further undisputed that the Purchase Order Agreement contains no warranties and that Herman Grant did not elsewhere provide any warranty regarding its work to either M&J or Superior.

¶9 Work on the Barron Plant was substantially completed in January 2013. The parties agree that Superior began having problems with the sand dryer almost immediately thereafter, but they disagree about the cause of the problems. Superior contends that the sand dryer was defective in multiple ways and failed to meet the performance requirements set forth in the Design/Build Contract. Herman Grant, in turn, asserts that Superior operated the sand dryer in ways that were contrary to the dryer’s specifications.

¶10 Superior contends that it provided Herman Grant with notice of the problems with the sand dryer long before the one-year warranty period set forth in the Design/Build Contract expired in January 2014.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daanen & Janssen, Inc. v. Cedarapids, Inc.
573 N.W.2d 842 (Wisconsin Supreme Court, 1998)
Ash Park, LLC v. Alexander & Bishop, Ltd.
2010 WI 44 (Wisconsin Supreme Court, 2010)
Gulmire v. St. Paul Fire & Marine Insurance
2004 WI App 18 (Court of Appeals of Wisconsin, 2003)
Turner v. Taylor
2003 WI App 256 (Court of Appeals of Wisconsin, 2003)
Olson v. Town of Cottage Grove
2008 WI 51 (Wisconsin Supreme Court, 2008)
Daniel Marx v. Richard L. Morris
2019 WI 34 (Wisconsin Supreme Court, 2019)
Kramer v. Board of Education of the School District of the Menomonie Area
2001 WI App 244 (Court of Appeals of Wisconsin, 2001)
Champion Companies of Wisconsin, Inc. v. Stafford Development, LLC
2011 WI App 8 (Court of Appeals of Wisconsin, 2010)
Estate of Kriefall v. Sizzler USA Franchise, Inc.
2012 WI 70 (Wisconsin Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Superior Silica Sands, LLC v. Herman Grant Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/superior-silica-sands-llc-v-herman-grant-company-inc-wisctapp-2020.