Superior Farming Co. v. Agricultural Labor Relations Board

151 Cal. App. 3d 100, 198 Cal. Rptr. 608, 1984 Cal. App. LEXIS 1532
CourtCalifornia Court of Appeal
DecidedJanuary 24, 1984
DocketCiv. No. 6872
StatusPublished
Cited by8 cases

This text of 151 Cal. App. 3d 100 (Superior Farming Co. v. Agricultural Labor Relations Board) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Superior Farming Co. v. Agricultural Labor Relations Board, 151 Cal. App. 3d 100, 198 Cal. Rptr. 608, 1984 Cal. App. LEXIS 1532 (Cal. Ct. App. 1984).

Opinion

Opinion

HAMLIN, J.

Superior Farming Company, Inc. (Superior) petitions for review of a decision of the Agricultural Labor Relations Board (Board) that Superior committed an unfair labor practice in violation of section 1153, subdivision (a), of the Agricultural Labor Relations Act of 1975 (ALRA or Act) (Lab. Code, § 1140 et seq.)1 by discharging members of a harvesting crew because of their protest against Superior’s wage rates.

Guadalupe Gutierrez Zacarías filed the unfair labor practice charge with the Board on June 12, 1979. Following an investigation, the Board’s Fresno regional director issued a complaint against Superior, alleging Superior violated section 1153, subdivision (a), by discharging Zacarías and his harvesting crew because they had engaged in protected concerted activity. An administrative law officer (ALO) heard the complaint and recommended findings that the crew had not been terminated and that, because Zacarías was not a “supervisor” within the meaning of the Act, his actions were not imputable to Superior. The Board’s general counsel filed exceptions and the Board affirmed the ALO’s rulings and conclusions as modified. Specifically, although the Board agreed with the ALO’s decisions on witness credibility, the Board concluded that a discharge had occurred and that Zacarías’ action in so informing the crew, though mistaken, was imputable to Superior. The Board ordered reinstatement, backpay, and make-whole relief, but determined that in the absence of retaliatory intent and in view of the “uniqueness of the situation,” posting, mailing and reading of the Board’s “stan[107]*107dard notice” were not required. Further, the Board adopted the ALO’s recommendation and dismissed the allegations of the complaint which asserted the discharge of Zacarías was an unfair labor practice.

Superior’s petition for review requires us to decide, among other things, whether the action of a crew leader in mistakenly informing members of his crew they (including him) were fired, when the employer had not so ordered or authorized, is imputable to the employer. Under the circumstances of this case we will conclude that such action must be imputed to the employer under the rationale of Vista Verde Farms v. Agricultural Labor Relations Bd. (1981) 29 Cal.3d 307 [172 Cal.Rptr. 720, 625 P.2d 263],

Superior’s contentions present additional issues which we similarly resolve against Superior. Therefore, we will enforce the Board’s order.

The Facts

Superior is an agricultural employer engaged in, among other things, the cultivation and harvesting of various types of “stone fruit,” including peaches, apricots and plums. The events at issue took place during the 1979 plum harvest at a Superior farm in Kern County. Zacarías, real party herein and one of the alleged dischargees, was hired as a fieldworker for Superior in late 1978. The following March, Superior made Zacarías a foreman of an apricot-thinning crew and directed him to hire the crew members. When the labor supervisor, Aurelio Menchaca, became aware that the crew Zacarías had purported to hire was inexperienced in thinning stone fruit, Menchaca declined to hire the crew members as Superior employees. Instead, he had them assigned to the payroll of labor contractor Jose Rodriguez.

As crew leader Zacarías was directly responsible to the ranch supervisor. He regularly translated the supervisor’s instructions into Spanish for the crew and the crew’s complaints into English to the supervisor. At times Zacarías was directed to lay off workers who did not meet Superior’s productivity standards but never did so without instructions from the supervisor. Zacarías also supplied contractor Rodriguez with daily crew lists.

The crew worked at a piece rate. Superior had a policy of guaranteeing an hourly minimum wage of $3.25 to workers supplied by a labor contractor whose production was insufficient to earn that minimum at the piece rate. However, that policy was never communicated to Zacarías.

On May 28 the crew began thinning plums. The plum harvest was directed by Martin Veiss, a Superior supervisor. When Veiss arrived at the plum [108]*108orchard on May 28, he instructed Zacarías about the correct size and color of plums to be picked and had Zacarías pass around a sample so the crew could “get the feel of it.” Veiss informed Zacarías the piece rate would be 70 cents per bucket, but did not mention the hourly minimum. Zacarías called the workers together and explained the pay rate and the way the work was to be done.

The crew experienced problems on the first day of picking. Veiss returned later and found that the crew was leaving ripe fruit on the trees. This prompted Veiss to instruct Zacarías several times during the day to have the crew redo trees already picked so ripe fruit would not be left behind. When Veiss asked Zacarías why the crew was having problems, Zacarías explained that 70 to 80 percent of the crew had never before picked stone fruit. On the first day no worker in the crew picked enough fruit to exceed the guaranteed hourly minimum of $3.25 and each was paid the minimum rate. Over the next two days the crew’s production increased. The “first pick,” i.e., the initial harvest of plums from the trees, was completed the morning of May 31. Veiss informed Zacarías the crew would repeat the process on the same trees in a “second pick” and that the piece rate for the second pick would be lowered from 70 cents to 60 cents per bucket. Veiss stated that the rate was changed because there would be more fruit to pick the second time around, and picking would not have to be as selective.

The “second pick” began in the late morning of May 31. At the close of work that day, two crew members complained to Veiss about the 60-cent rate and asked him if the 70-cent rate could be reinstated. Veiss told one worker he could not change the rate but would “ask the boss,” that is, harvest coordinator Binardi, if something could be done. Veiss testified he spoke to Binardi that evening, but to no avail. Binardi in essence said the 60-cent rate was fair.

On the next day, June 1, the crew began working at the regular time— about 6:30 a.m. After the crew had worked over an hour, Veiss visited the crew at the picking site. He immediately saw that many of the plums were too small for harvesting and showed the undersized fruit to Zacarías. Zacarías then gathered the crew at the bin and demonstrated the problem of undersized fruit by passing some of the fruit through a sizing ring. After that he passed a plum of minimum acceptable size among the crew members for them to “get the feel of it.”

After the demonstration, a crew worker asked Veiss if he had obtained a rate raise for the crew. Veiss answered he had not. Another worker asked [109]*109Veiss if he could raise the rate to the 70-cent level of the first pick. Veiss replied he could not set the rates and that the matter was out of his hands.

The crew appeared to Veiss to be “not too happy.” After about 10 minutes and further discussions, Veiss felt unsure whether they were willing to return to work at the 60-cent rate. He called Zacarías aside and told him, “Well, the price is set, and the crew either has to go in to work or they would [sic] have to go home.” At the time Veiss made this statement, he angrily threw some plums to the ground and told the workers to take the ladders out of the trees or they would not be paid for the day.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gevargeza v. Walgreens Co. CA2/7
California Court of Appeal, 2025
Boling v. Public Employment Relations Bd.
California Court of Appeal, 2019
Boling v. Pub. Emp't Relations Bd.
245 Cal. Rptr. 3d 78 (California Court of Appeals, 5th District, 2019)
Gerawan Farming, Inc. v. Agric. Labor Relations Bd.
234 Cal. Rptr. 3d 88 (California Court of Appeals, 5th District, 2018)
Boling v. Public Employment Relations Board
10 Cal. App. 5th 853 (California Court of Appeal, 2017)
Philip v. Garcia
111 Cal. App. 4th 140 (California Court of Appeal, 2003)
Franchise Tax Board v. Superior Court
168 Cal. App. 3d 970 (California Court of Appeal, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
151 Cal. App. 3d 100, 198 Cal. Rptr. 608, 1984 Cal. App. LEXIS 1532, Counsel Stack Legal Research, https://law.counselstack.com/opinion/superior-farming-co-v-agricultural-labor-relations-board-calctapp-1984.