Superior Construction Company

CourtArmed Services Board of Contract Appeals
DecidedJuly 1, 2020
DocketASBCA No. 61468
StatusPublished

This text of Superior Construction Company (Superior Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Superior Construction Company, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Superior Construction Company ) ASBCA No. 61468 ) Under Contract No. H92237-11-C-0701 )

APPEARANCE FOR THE APPELLANT: Mr. Mahboobullah Atiqi Vice President

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Heather M. Mandelkehr, Esq. Maj Ryan P. Payne, USAF Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE WOODROW ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

This appeal involves a contractor’s demand for mobilization costs on a contract in Afghanistan that was suspended and never reinitiated. The government contends that appellant’s claim is untimely and has moved for summary judgment. We grant the motion and deny the appeal.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On May 11, 2011, the Combined Joint Special Operations Task Force – Afghanistan, now Special Operations Joint Task Force – Afghanistan (the government) awarded Contract No. H92237-11-C-0701 to Superior Construction Company SCC (SCC) 1 for the construction of a short take-off and landing zone (STOLZ project) on Forward Base Darvishan, Afghanistan (R4, tab 5). On the same day, the contracting officer (CO) provided a Notice to Proceed to SCC (R4, tabs 6-7).

2. SCC mobilized machinery and labor to begin the STOLZ project (R4, tab 8 at 2, tab 9 at 1-3). But upon arrival at the project site, a government representative explained to SCC personnel that the project could not begin because ongoing

1 Appellant uses various names throughout its correspondence with the government: Superior Construction Company; Women Superior Co.; Women Superior Construction Company; and Superior Construction Supply and Service Company. We will continue to use appellant’s name as captioned in this appeal. construction on a separate project prevented any work on the runway for the STOLZ project (R4, tab 9 at 2). On June 11, 2011, that government representative advised SCC by email that construction on the other project would likely not be complete until late July or early August, and until then, work on the STOLZ project would have to be suspended pending completion of the other (R4, tab 9 at 6; see tab 9 at 3-4). The record does not indicate that a new start date was ever provided or that work was ever done on the STOLZ project.

3. From July 18, 2011 until September 23, 2011, SCC and the government exchanged numerous emails regarding compensation for mobilization costs and the status of the new start date (R4, tabs 8-10). Throughout the email dialogue, SCC and the government never reached an agreement concerning the amount of reasonable compensation for costs expended by SCC for mobilization to the project site, with appellant seeking amounts ranging from $22,500 to $36,000, and the government proposing to pay amounts ranging from $3,000 to $5,000 (R4, tabs 8-10).

4. On August 8, 2017, SCC filed an appeal with the Board, which was docketed as ASBCA No. 61272. On September 12, 2017, the Board requested that SCC provide a copy of the claim it submitted to the CO prior to filing the appeal. In response, SCC indicated that it had not submitted a claim to a CO for a decision. On October 5, 2017, the Board dismissed ASBCA No. 61272 without prejudice to allow SCC to submit a claim to a CO. Superior Constr. Co., ASBCA No. 61272, 2017 WL 4736788 (Oct. 5, 2017).

5. Prior to the October 5, 2017 dismissal, on September 20, 2017, SCC submitted a claim to the CO for $40,900 in costs related to the STOLZ project (R4, tabs 2-4). The claim describes costs for mobilization with escort charges, machinery on-site, labor, and demobilization (R4, tab 4). The claim provides that machinery remained on the project site from May 18, 2011 until July 17, 2011 (R4, tab 3).

6. After receiving the claim, the government requested that SCC submit all related invoices (R4, tab 11 at 1). In response, SCC provided three invoices, which included costs for mobilization, demobilization, and equipment leasing for the dates of May 18, 2011 to July 17, 2011 (R4, tabs 11-14). Two of the invoices are dated May 16, 2011, and the third invoice is dated July 18, 2011 (R4, tabs 12-14). The invoices were later translated for accuracy by SOJTF-A linguists, which confirmed the English text within each document (R4, tab 18 at 4). Upon further request by the government for invoices submitted to the contracting officer’s representative in 2011, SCC provided two more invoices both dated July 4, 2011 (R4, tabs 15-17). These two invoices are entirely in English and also describe costs for mobilization, demobilization, and machinery (R4, tabs 16-17).

2 7. The CO issued a final decision, dated December 28, 2017, denying the claim based on the Contract Disputes Act’s (CDA’s) six-year statute of limitations for filing a claim (R4, tab 18). On January 1, 2018, SCC filed a timely appeal with the Board, which was docketed as ASBCA No. 61468 and is before us now.

8. On June 4, 2018, the government filed a motion for summary judgment describing the “single controlling issue” as the “claim outside of the six-year period” (gov’t mot. at 1). Attached as Exhibits G-1 and G-2 to the government’s motion are SCC’s responses to discovery. SCC’s two admission responses are directly quoted below:

Request for Admission No. 1. Admit that all costs related to this appeal and its underlying claim were accrued by 17 July 2011.

Response: Superior Co. admits that all costs related to this appeal were accrued by 17 July 2017

Request for Admission No. 2. Admit that the first and only claim related to the costs incurred under the Contract and are the subject of this appeal was filed on 20 September 2017.

Response: Superior co. Admits that the first and only claim was filed on 20 September 2017. [B]ut we asked for our expenditures through Email address to the contracting officer back on 2011.

(Gov’t mot., ex. G-1 at 9) (syntax in original)

9. Following those responses, the government emailed SCC to clarify the date on Admission No. 1 above. On May 31, 2018, SCC responded to the government’s email saying, “I apologize for the inconvenience, it is 17 July 2011.” (Gov’t mot., ex. G-2 at 1) Accordingly we find that SCC’s claim accrued on July 17, 2011.

10. On October 10, 2018, SCC responded, via email to the Board, to the government’s motion for summary judgment by submitting a self-described “Appeal Statement” without specifically addressing the government’s contention. SCC also attached three invoices “as an evidence to our Appeal.” (Bd. corr. ltr. dtd. October 10, 2018)

3 DECISION

Summary judgment is appropriate when there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48 (1986). When considering a motion for summary judgment, the Board’s function is not “to weigh the evidence and determine the truth of the matter but to determine whether there is a genuine issue for trial.” Id. at 249. We are required to view the record in the light most favorable to the nonmoving party, which in this case is SCC. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587-88 (1986) (citing United States v. Diebold, Inc., 369 U.S. 654, 655 (1962)).

The CDA provides that “[e]ach claim by a contractor against the Federal Government relating to a contract . . . shall be submitted within 6 years after the accrual of the claim.” 41 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Felder v. Johnson
204 F.3d 168 (Fifth Circuit, 2000)
United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Arctic Slope Native Association, Ltd. v. Sebelius
583 F.3d 785 (Federal Circuit, 2009)
Menominee Indian Tribe of Wis. v. United States
577 U.S. 250 (Supreme Court, 2016)
Levy v. United States
83 Fed. Cl. 67 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Superior Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/superior-construction-company-asbca-2020.