Sunrise of Coral Gables PropCo, LLC v. Current Builders,Inc.

District Court, S.D. Florida·Decided September 5, 2023·No. 1:22-cv-21456·Unknown

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA MIAMI DIVISION CASE NO. 1:22-CV-21456-MORENO/GOODMAN

SUNRISE OF CORAL GABLES PROPCO, LLC,

Plaintiff, v.

CURRENT BUILDERS, INC.,

Defendant. ______________________________________/

ORDER ON PLAINTIFF’S MOTION TO STRIKE DEFENDANT’S ERRATA SHEET

In this breach of contract case, Plaintiff Sunrise of Coral Gables Propco, LLC (“Plaintiff”) filed a motion to strike Current Builders Inc.’s (“Defendant”) errata sheet (“the Motion”). [ECF No. 27]. United States District Judge Federico A. Moreno referred to the Undersigned any and all pretrial matters. [ECF No. 40].1 The Motion seeks to strike Defendant’s errata sheet for the Rule 30(b)(6) deposition given by its corporate designee.

1 Judge Moreno’s referral Order specifically requires the Undersigned's ruling to be consistent with 28 U.S.C. § 636(b)(1)(A) and Rule 1(c) of the Local Magistrate Judge Rules, both of which apply to non-dispositive motions. This, in turn, means that the Undersigned needs to issue an Order, rather than a Report and Recommendations (which would be for dispositive matters). Defendant filed a response [ECF No. 32], and Plaintiff filed an optional reply [ECF No. 38].

For the reasons discussed below, the Undersigned denies Plaintiff’s motion. I. Background Plaintiff owns a six-story assisted living facility. [ECF No. 20]. As the owner of the

facility, Plaintiff entered into a Guaranteed Maximum Price Construction Agreement. The Agreement set forth the parties' respective rights and obligations, including claim and dispute procedures. In it, Defendant agreed that in the event of a dispute between

the parties, it would continue working on the project subject to its right to submit a claim. The Agreement contemplated a Limited Notice to Proceed in June 2021 and a full Notice to Proceed in December 2021. Following the Limited Notice, Plaintiff alleges that Defendant failed to timely pursue subcontractor and vendor awards. In December 2021,

Plaintiff did not issue the Notice to Proceed because of the delay in receiving the necessary building permit from the City of Coral Gables. The following month, Defendant sent Plaintiff a letter regarding escalating costs

on the project. The discussions on costs led Defendant to terminate the Agreement. Plaintiff claims that Defendant unlawfully terminated the Agreement based on the included language. On February 8, 2022, Plaintiff issued a seven-day notice to cure, as set forth in the Agreement. Defendant failed to cure and did not return to work on the

project. About a week later, Plaintiff terminated Defendant for cause. There are many disputes regarding the Agreement but the one at issue here is related to Section 14.1.2. [ECF No. 27]. Section 14.1.2 permitted Defendant to terminate the Agreement under

limited circumstances where, through no fault of Defendant: (i) repeated suspensions, delays or interruptions (ii) of the “entire Work” (iii) by Plaintiff “as described in § 14.3” (iv) constitute 120 days in any 365-day period. Id. The parties contest whether the "entire

Work" was suspended for 120 days. On June 28, 2023, the parties conducted the deposition of Defendant's corporate designee, President, and Chief Executive Officer, Michael Taylor ("Taylor"). On August

1, 2023, Defendant submitted an errata sheet, amending some of Taylor's responses (related to a subcontractor) from affirmative to negative. Defendant argues that Plaintiff's questions related to the subcontractor, All Webbs, confused Taylor because, while Defendant had a contract with All Webbs to drill dewatering wells, All Webbs also

performed test drilling directly for the Plaintiff that was outside the scope of its work or its subcontract with Defendant. [ECF No. 32]. Plaintiff contends that Defendant's errata sheet materially alters Taylor's

deposition testimony and requests for it to be stricken. It contends that the changes “fundamentally alter” Taylor’s testimony “in a blatant attempt to escape the reality” of its performance under the contract and “are offered without good cause.” [ECF No. 7-1, p. 1]. Moreover, the motion to strike brands the changes listed in the errata sheet as

“patently false” and claims they are “belied by numerous” documents. Id. at 2. As noted, Taylor’s explanation for the changes is that he was confused. The specific grounds for the confusion are slightly different for each of the changed answers. [ECF

No. 27-4, p. 3 (p. 377 of the transcript)]. In addition to signing the errata sheet under penalty of perjury, Taylor also signed an affidavit after the motion to strike was filed. [ECF No. 32-1]. The affidavit explains that

he was confused with questions because a subcontractor did some work under the contract but did other work directly for Plaintiff which was not part of its subcontract. Taylor also explained that he reviewed Plaintiff’s motion to strike and believes that the

exhibits do not contradict his corrected testimony. In fact, he says that Plaintiff “mischaracterized” his corrections in its memorandum. Moreover, he contends that other documents confirm the accuracy of his corrections, and he pinpoints them as exhibits filed in support of a pending summary judgment motion.

Not surprisingly, in its Reply, Plaintiff argues that Taylor’s explanations do not establish a “good reason” for the substantive changes in the deposition testimony. II. Legal Standard

The Court, either on its own or on a motion made by a party, is permitted to strike from a pleading "an insufficient defense or any redundant, immaterial, impertinent, or scandalous matter." Fed. R. Civ. P. 12(f)(1)-(2). Plaintiff's Motion requests we strike Defendant's errata sheet for the reasons discussed in the following section. Rule 30(e)(1) of the Federal Rules of Civil Procedure governs errata sheets and provides that:

On request by the deponent or a party before the deposition is completed, the deponent must be allowed 30 days after being notified by the officer that the transcript or recording is available in which:

(A) to review the transcript or recording; and

(B) if there are changes in form or substance, to sign a statement listing the changes and the reasons for making them.

The plain language of Rule 30(e) contemplates "changes in form or substance." Id. In Norelus v. Denny's, Inc., the Eleventh Circuit Court of Appeals found that the errata sheet at issue was problematic because of its length and that, making a slew of material changes to their client's deposition testimony was improper. (citing Hambleton Bros. Lumber Co. v. Balkin Enters., Inc., 397 F.3d 1217, 1225 (9th Cir. 2005) (upholding a district court's judgment to strike an errata sheet listing twenty-seven changes, noting that “Rule 30(e) is to be used for corrective, and not contradictory, changes”); Garcia v. Pueblo Country Club, 299 F.3d 1233, 1242 n. 5 (10th Cir. 2002) (“We do not condone counsel's allowing for material changes to deposition testimony and certainly do not approve of the use of such altered testimony that is controverted by the original testimony.”); Thorn v. Sundstrand Aerospace Corp., 207 F.3d 383, 388–89 (7th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Sunrise of Coral Gables PropCo, LLC v. Current Builders,Inc., (S.D. Fla. 2023).

Sunrise of Coral Gables PropCo, LLC v. Current Builders,Inc. (Sunrise of Coral Gables PropCo, LLC v. Current Builders,Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

EBC, Inc. v. Clark Building System, Inc.
618 F.3d 253 (Third Circuit, 2010)
Norelus v. Denny's, Inc.
628 F.3d 1270 (Eleventh Circuit, 2010)
Walter Usiak v. New York Tank Barge Company, Inc.
299 F.2d 808 (Second Circuit, 1962)
Fox v. Acadia State Bank
937 F.2d 1566 (Eleventh Circuit, 1991)
Arcenio E. Garcia v. Pueblo Country Club
299 F.3d 1233 (Tenth Circuit, 2002)
Janet Feliciano v. City of Miami Beach
707 F.3d 1244 (Eleventh Circuit, 2013)
Reynolds v. International Business MacHines Corp.
320 F. Supp. 2d 1290 (M.D. Florida, 2004)
Podell v. Citicorp Diners Club, Inc.
112 F.3d 98 (Second Circuit, 1997)
State of Georgia v. President of the United States
46 F.4th 1283 (Eleventh Circuit, 2022)
Maharaj v. Geico Casualty Co.
996 F. Supp. 2d 1303 (S.D. Florida, 2014)
Foutz v. Town of Vinton
211 F.R.D. 293 (W.D. Virginia, 2002)
Reilly v. Txu Corp.
230 F.R.D. 486 (N.D. Texas, 2005)
Cultivos Yadran S.A. v. Rodriguez
258 F.R.D. 530 (S.D. Florida, 2009)
Lugtig v. Thomas
89 F.R.D. 639 (N.D. Illinois, 1981)
Greenway v. International Paper Co.
144 F.R.D. 322 (W.D. Louisiana, 1992)