Sunrise Equipment & Excavation, Inc. v. Construction Management & Builders, Inc.

CourtMassachusetts Appeals Court
DecidedSeptember 5, 2024
Docket23-P-594
StatusPublished

This text of Sunrise Equipment & Excavation, Inc. v. Construction Management & Builders, Inc. (Sunrise Equipment & Excavation, Inc. v. Construction Management & Builders, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunrise Equipment & Excavation, Inc. v. Construction Management & Builders, Inc., (Mass. Ct. App. 2024).

Opinion

APPEALS COURT

SUNRISE EQUIPMENT & EXCAVATION, INC. vs. CONSTRUCTION MANAGEMENT & BUILDERS, INC.

Docket: 23-P-594
Dates: March 1, 2024 – September 5, 2024
Present: Rubin, Englander, & D'Angelo, JJ.
County: Plymouth
Keywords: Attorney at Law, Contingent fee agreement, Lien. Contract, Contingent fee agreement, Construction of contract. Lien. Practice, Civil, Attorney's fees.

      Civil action commenced in the Superior Court Department on July 18, 2014.

      Following review by this court, 99 Mass. App. Ct. 1113 (2021), a motion to enforce an attorney's lien was heard by William F. Sullivan, J.

      Robert L. Hamer for the plaintiff.

      Joseph K. Curran, Jr., pro se.

      ENGLANDER, J.  At issue is whether the plaintiff, Sunrise Equipment & Excavation, Inc. (Sunrise), must pay a contingent attorney's fee to its trial counsel in this case, Joseph K. Curran, Jr.  Sunrise won a jury verdict of $400,000 in this breach of contract and G. L. c. 93A case in May of 2017.  Curran represented Sunrise up to and through trial and posttrial proceedings.  After the matter was appealed to this court, however, Sunrise replaced Curran as counsel.  This court affirmed the judgment, which (after adding attorney's fees and pre- and postjudgment interest) totaled over $800,000. 

      Curran claims that he performed the work for Sunrise pursuant to a contingent fee agreement; this appeal arises from Curran's efforts to collect that one-third contingency fee.  In 2021, after the appeal had been resolved, Sunrise and the defendant in the underlying case agreed to a payment of $812,000 in full satisfaction of the judgment, and thereafter, the judge addressed Curran's motion to enforce his attorney's lien, which Curran had previously filed.  Sunrise opposed the payment of a contingent fee, claiming that under Mass. R. Prof. C. 1.5 (c), as amended, 480 Mass. 1315 (2018), it did not have an enforceable contingent fee agreement with Curran, and that in any event, Curran was not entitled to a contingent fee because he had been replaced as counsel before the appeal had been resolved and Sunrise had been paid.  After an evidentiary hearing, the motion judge found that Curran and Sunrise had entered into an enforceable contingent fee agreement, and that Curran had satisfied the agreement's contingency by successfully handling the case in the trial court.  We now affirm the order enforcing the contingent fee agreement and determining and enforcing the attorney's lien.

      Background.  We draw our facts from the judge's findings as supplemented by undisputed facts.  In the spring of 2014, Curran met with Sunrise's general operations manager, Joseph Kerrissey, and agreed to represent Kerrissey and his businesses, including Sunrise, in five legal matters.  One of those legal matters was the instant litigation, a breach of contract and G. L. c. 93A action against Construction Management & Builders, Inc. (CMB).  Curran testified that as to this action, he and Kerrissey agreed that Curran would be compensated by (1) a small retainer, and (2) a contingent fee arrangement.[1]  Curran presented a copy of the contingent fee agreement at the evidentiary hearing; the agreement, dated July 7, 2014, bore signatures of both Curran, on behalf of his law firm, and Kerrissey, on behalf of Sunrise.  The agreement provided that the Law Office of Curran & Desharnais, P.C. would "render legal services . . . in connection with [Sunrise's] claims against [CMB]" (agreement or CMB agreement).  The agreement established two categories of compensation:  (1) an hourly billing arrangement of a rate of $190, up to a maximum of $5,000, and (2) payment in the amount of "one third . . . of any gross payment or any lump sum settlement [Sunrise] receive[d] by way of judgment, settlement, arbitration award or otherwise."  Importantly, the agreement contemplated "additional compensation" if there was an appeal, stating, "In the event of an appeal to the Appeals Court . . . , additional compensation will be payable for work performed, at the rate of $350.00 per hour."

      Although Curran testified that he kept a signed original copy of the agreement, he could not locate the original and instead a copy was admitted in evidence.  Kerrissey denied signing the agreement, but the motion judge expressly did not credit Kerrissey's testimony and found, to the contrary, that Kerrissey signed the agreement and also received an original of the agreement upon its execution.  Curran testified, and the judge found, that Curran also mailed a copy of the executed agreement to Kerrissey, but Curran did not maintain proof of this mailing.

      Curran began working on Sunrise's claims against CMB following the execution of the agreement.  The case required significant pretrial discovery and motion practice.  Curran represented Sunrise during the four-day jury trial in May of 2017, which resulted in a favorable verdict of $400,000 against CMB.  Curran continued to represent Sunrise throughout substantial posttrial proceedings; Curran successfully defended against motions, among others, for judgment notwithstanding the verdict and for a new trial, and he secured awards, postjudgment, of G. L. c. 93A attorney's fees ($73,965), and postjudgment security.  CMB appealed from the judgment in August of 2018.[2]  Following CMB's appeal, Curran also filed pleadings, which were ultimately unsuccessful, seeking to have the appeal dismissed on procedural grounds.

      While the appeal was pending the relationship between Kerrissey and Curran disintegrated.  Kerrissey was under financial pressure, and was seeking payment of the judgment as soon as possible.  Curran, who at that point had received roughly $1,200 in capped hourly compensation for his work on the case (spanning five years),[3] became concerned about being paid the contingency fee, and filed an attorney's lien in September of 2019.  Curran's action in filing the lien led to Kerrissey asking Curran to withdraw, which Curran did in November of 2019.  Successor counsel took over the appeal.

      This court decided the appeal in March of 2021, and affirmed the judgment.  See Sunrise Equip. & Excavation, Inc. v. Construction Mgt. & Bldrs., Inc., 99 Mass. App. Ct. 1113 (2021).  In June of 2021 Sunrise and CMB resolved the case for a lump sum payment of $812,000 to Sunrise.  The parties placed $270,000 in escrow pending the resolution of Curran's motion to enforce his attorney's lien.  Sunrise opposed Curran's motion, raising a variety of arguments, including (1) that there was no contingent fee agreement, (2) alternatively, that Curran was not entitled to the contingent fee because his representation ended before the case was concluded and Sunrise received payment, and (3) that the agreement Curran presented was unenforceable due to violations of Mass. R. Prof. C. 1.5 (c) (governing contingent fee agreements) -- for example, that Curran failed to maintain either an original signed agreement or proof that a duplicate copy had been delivered to his client, Sunrise.  Rather than pay a contingent fee, Sunrise's position was that Curran was entitled only to the $73,965 in fees awarded under G. L. c. 93A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. United States Gypsum Co.
333 U.S. 364 (Supreme Court, 1948)
Opert v. Mellios
614 N.E.2d 996 (Massachusetts Supreme Judicial Court, 1993)
Marlow v. City of New Bedford
340 N.E.2d 494 (Massachusetts Supreme Judicial Court, 1976)
Smith v. Consalvo
638 N.E.2d 501 (Massachusetts Appeals Court, 1994)
DeMayo v. Quinn
25 N.E.3d 903 (Massachusetts Appeals Court, 2015)
Halstrom v. Dube
116 N.E.3d 626 (Massachusetts Supreme Judicial Court, 2019)
New York Central Railroad v. New England Merchants National Bank
183 N.E.2d 852 (Massachusetts Supreme Judicial Court, 1962)
Young v. Southgate Development Corp.
399 N.E.2d 27 (Massachusetts Supreme Judicial Court, 1980)
Salem Realty Co. v. Matera
426 N.E.2d 1160 (Massachusetts Supreme Judicial Court, 1981)
Cambridge Trust Co. v. Hanify & King Professional Corp.
430 Mass. 472 (Massachusetts Supreme Judicial Court, 1999)
Situation Management Systems, Inc. v. Malouf, Inc.
724 N.E.2d 699 (Massachusetts Supreme Judicial Court, 2000)
Commonwealth v. Ocasio
746 N.E.2d 469 (Massachusetts Supreme Judicial Court, 2001)
Seaco Insurance v. Barbosa
435 Mass. 772 (Massachusetts Supreme Judicial Court, 2002)
Malonis v. Harrington
816 N.E.2d 115 (Massachusetts Supreme Judicial Court, 2004)
Twin Fires Investment, LLC v. Morgan Stanley Dean Witter & Co.
445 Mass. 411 (Massachusetts Supreme Judicial Court, 2005)
Saggese v. Kelley
837 N.E.2d 699 (Massachusetts Supreme Judicial Court, 2005)
In re the Discipline of an Attorney
884 N.E.2d 450 (Massachusetts Supreme Judicial Court, 2008)
Craft v. Kane
747 N.E.2d 748 (Massachusetts Appeals Court, 2001)
R.W. Granger & Sons, Inc. v. J & S Insulation, Inc.
807 N.E.2d 211 (Massachusetts Appeals Court, 2004)
Kingstown Corp. v. Black Cat Cranberry Corp.
839 N.E.2d 333 (Massachusetts Appeals Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Sunrise Equipment & Excavation, Inc. v. Construction Management & Builders, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunrise-equipment-excavation-inc-v-construction-management-builders-massappct-2024.