Sunray Mid-Continent Oil Company v. Federal Power Commission, (Two Cases)

270 F.2d 404
CourtCourt of Appeals for the Tenth Circuit
DecidedSeptember 28, 1959
Docket6061_1
StatusPublished
Cited by28 cases

This text of 270 F.2d 404 (Sunray Mid-Continent Oil Company v. Federal Power Commission, (Two Cases)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunray Mid-Continent Oil Company v. Federal Power Commission, (Two Cases), 270 F.2d 404 (10th Cir. 1959).

Opinion

LEWIS, Circuit Judge.

These two cases were consolidated on review upon the representation that the determination of a single question of law would be dispositive of both cases, that question being: Can the Federal Power Commission impose conditions upon the grant of a temporary certificate of public convenience and necessity? Our study indicates that although the stated question is present in each case separate consideration of the cases is necessary because of factual differences of legal significance.

No. 6043. The petitioner, an independent producer of natural gas, in conjunction with applications for permanent certificates of convenience and necessity for the sale of gas, sought temporary authorization from the Commission to initiate such sales pending determination of the applications for permanent *406 certificates. The temporary authority was sought pursuant to the statutory authority granted the Commission by Section 7(c) of the Natural Gas Act, 15 U.S.C.A. § 717 et seq., and in full compliance with Commission regulation 157.28. 1 Authorization to begin temporary service was initially denied by the Commission but, after protest by Sunray, was granted by letter order dated January 30, 1958. The letter of authorization contained the following statement:

“This constitutes all requisite temporary authorization to commence the sale of gas, but such authorization and acceptance of the rate schedule are without prejudice to such final disposition of the certificate applications as the record may require and furthermore, once service is commenced under this authorization it may not be discontinued without permission of the Commission issued pursuant to the Natural Gas Act.” (Emphasis added.)

Sunray initiated deliveries upon receipt of the Commission letter order but informed the Commission by letter that:

“Accordingly, Sunray * * * will only ‘continue such sale * * * pending final Commission action under Sections 4 and 7 of the Natural Gas Act’ upon the respective applications for certificates of public convenience and necessity covering such sales. Sunray retains its right to accept or reject such certificates of public convenience and necessity as may be issued and to cease deliveries of gas in the event final action of the Commission on said applications for certificates of public convenience and necessity does not grant certificates of public convenience and necessity in accordance with the said, applications.”

After receipt of this letter from Sun-ray, the Commission rescinded its grant of temporary authority asserting that Sunray had evinced an unwillingness to comply with the Commission’s lawful authority. Thereafter, ex parte, the Commission reinstated the temporary authorization, this time stating as its reason that its order of rescission had' been premised upon the erroneous belief that Sunray had not initiated de~ *407 liveries so as to affect public convenience and necessity in such aspect. The reinstatement order reiterated the Commission’s earlier contention that Sunray could not terminate its service except by express permission of the Commission. It is in opposition to this contention that Sunray brings the cause to this court after unsuccessfully seeking a rehearing before the Commission.

The right of this court to review orders of the Federal Power Commission is limited by Sec. 19(b) of the Natural Gas Act to instances where the petitioner is presently aggrieved by the imposition of such orders. This compulsion leads us to hold that the present petition is premature. The able and comprehensive presentation of counsel, pointing to the complexities of right and duty that may ■occur if Sunray can lawfully be required to furnish service under a temporary .authorization extended beyond determination of its application for a permanent ■certificate (as the Commission apparently contends), or if Sunray can arbitrarily reject a permanent certificate and thereupon cease service under its temporary authorization and as a matter of right (as Sunray contends), considers but eventualities. Sunray is currently selling its gas and has made no affirmative ■effort to cease. The Commission has made no objection to the status quo. Regardless of Sunray’s present apprehension and the Commission’s present warnings it will take further administrative action to create an actual grievance. Under these circumstances, it is obvious that “the order sought to be reviewed does not of itself adversely affect complainant but only affects his rights adversely on the contingency of future administrative action,” Rochester Telephone Corp. v. United States, 307 U.S. 125, 59 S.Ct. 754, 757, 83 L.Ed. 1147, and hence is not reviewable under Sec. 19(b), 15 U.S.C.A. § 717r; see Federal Power Commission v. Hope Natural Gas Co., 320 U.S. 591, 64 S.Ct. 281, 88 L.Ed. 333. If, as Sunray contends the Commission has no power to condition temporary certificates or has imposed an unlawful condition, the actions have no present impact upon Sunray. For this reason, the appeal in Case No. 6043 is dismissed.

No. 6061. Here again Sunray applied to the Commission for temporary authorization to sell gas pending final determination of its application for a permanent certificate of public convenience and necessity. By letter order dated September 17, 1958, the application for temporary authority was accepted by the Commission:

“ * * * subject to the condition that the price received by Sunray for its interest in the production from the jointly owned lease here involved will be that ultimately found to be just and reasonable in the operator’s rate suspension proceedings, Docket Nos. G-11710 and G-14248. 2 In addition, Sunray shall submit a statement to this Commission as to its willingness to accept a permanent certificate of public convenience and necessity, in the subject, docket on the same basis and further conditioned to require the filing of an undertaking to assure refund to the purchaser of any portion of the increased rates found by the Commission in the aforementioned suspension proceedings not justified.” 3

Petitioner applied for rehearing which was denied, two commissioners dissenting. Thereafter on January 23, 1959, the Commission, sua sponte, modified its order denying rehearing by substituting, for the language cited above the following:

“Such acceptance shall be subject to any conditions with respect *408 to price which the Commission may lawfully impose in issuing a certificate of public convenience and necessity in this Docket No. G-16134.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tenneco Oil Company v. Federal Power Commission
442 F.2d 489 (Fifth Circuit, 1971)
Federal Power Commission v. Sunray DX Oil Co.
391 U.S. 9 (Supreme Court, 1968)
Continental Oil Co. v. Federal Power Commission
378 F.2d 510 (Fifth Circuit, 1967)
Sunray DX Oil Co. v. Federal Power Commission
370 F.2d 181 (Tenth Circuit, 1966)
United States Court of Appeals Tenth Circuit
370 F.2d 181 (Tenth Circuit, 1966)
Sunray Dx Oil Company v. Federal Power Commission
351 F.2d 395 (Tenth Circuit, 1965)
Hunt Oil Co. v. Federal Power Commission
334 F.2d 474 (Fifth Circuit, 1964)
Sun Oil Company v. Federal Power Commission
304 F.2d 290 (Fifth Circuit, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
270 F.2d 404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunray-mid-continent-oil-company-v-federal-power-commission-two-cases-ca10-1959.