Sunnyland Farms, Inc. v. Central New Mexico Electric Cooperative, Inc.

2011 NMCA 49, 2011 NMCA 049, 255 P.3d 324, 149 N.M. 746
New Mexico Court of Appeals·Decided March 24, 2011·No. 28,807·Published·Cited by 6 cases

Opinion

OPINION

SUTIN, Judge.

{1} Defendant Central New Mexico Electric Cooperative, Inc. appeals a judgment awarding substantial consequential and punitive damages to Plaintiff Sunnyland Farms, Inc. Plaintiff purchased a commercial greenhouse operation intending to hydroponically grow tomatoes. Its facilities were destroyed by fire before it was able to plant its first crop. Plaintiff sued Defendant on various theories including claims for breach of contract and negligence in failing to provide the required advance notice before disconnecting electric power to Plaintiffs facilities, and claiming that, as a result of the disconnect, Plaintiff could not access water necessary to quench the fire.

{2} District court determined that Plaintiff suffered approximately $21 million in consequential damages. The court compared fault on the negligence claim and determined that Plaintiff was 80% at fault and Defendant was 20% at fault. The court did not consider Plaintiffs fault on the breach of contract claim and awarded Plaintiff the full amount of damages, and permitted Plaintiff to elect its remedy after the time for appeal had expired. On appeal, Defendant attacks the allowance of consequential damages in contract, the award of punitive damages, and the amount of the consequential damages attributable to future lost profits. Plaintiff cross-appeals on issues involving prejudgment and post-judgment interest and a set-off. We hold that the district court erred in awarding consequential damages in contract and in awarding punitive damages. On the issue of the amount of the lost profits awarded on Plaintiffs negligence claim, we hold that Plaintiffs evidence lacked a reasonably certain basis as to future production levels on which the court based its award and therefore did not support the amount of the award. On the cross-appeal issues, we hold that the court did not err, and we affirm on those issues.

BACKGROUND

The Start of the Relationship

{3} Defendant is an electric cooperative that was owned and operated by its members who purchase and distribute electricity to themselves for their own benefit. Defendant and its members are bound by Defendant’s bylaws, rules, rate classifications, and rate schedules, including tariffs filed by Defendant with the New Mexico Public Regulatory Commission (PRC) (formerly the Public Utility Commission).

{4} One tariff, or “original rule,” states that if payment by a member using electricity is not paid within fifteen days from the date of a delinquent disconnect notice from Defendant, the member “will be subject to disconnect.” A PRC regulation to which Defendant was subject states that a cooperative can disconnect electricity for failure of a member “to fulfill his contractual obligations for services,” but that it “shall not constitute sufficient cause for discontinuing service to an existing [or] ... prospective customer ... for failure to pay the bill of another customer as guarantor thereof.”

{5} In June 2003 Plaintiff purchased a tomato farm from Agstar of New Mexico, Inc. (Agstar), agreed to pay Agstar’s debts, and told Defendant that Plaintiff would assume liability for Agstar’s delinquent obligations to Defendant. Electricity to the facilities had been turned off by Defendant for Agstar’s nonpayment. On July 10, 2003, Plaintiff opened four accounts in Plaintiffs name and paid Defendant a deposit of $10,750. Plaintiff also paid all amounts owed to Defendant by Agstar as of July 10, Agstar’s four accounts with Defendant were closed, Agstar was no longer using electricity, and Agstar’s existing deposit was added to Sunnyland’s deposit. Plaintiff received Defendant’s final bills for Agstar’s electricity accounts which were mailed by Defendant on July 17, 2003. These bills stated that they would become delinquent on August 5, 2003.

The Disconnect Notices and Ultimate Disconnect of Plaintiffs Electricity

{6} A saga followed of Defendant’s mixture of mistaken, ambiguous, and inappropriate billings and disconnect notices and procedures, which were the bases for the district court’s determinations of Defendant’s contract and tort liability in this case. That unfortunate saga was followed by Plaintiffs negligent actions and failures to act, which were the bases for the court’s determinations of Plaintiffs comparative fault.

{7} Defendant’s first billing to Plaintiff on August 9, 2003, to September 8, 2003, when Defendant disconnected electricity to one of Plaintiffs accounts, was replete with mistaken, confusing, and improper billings, and with improper electricity cut-off procedures and orders and disconnect notices that we need not detail. Plaintiff was not aware that Defendant had sent an employee to Plaintiffs operation on September 8, 2003, to disconnect the electricity. Once Plaintiff became aware on September 8 that its electricity had been disconnected to the tomato-growing facility, an employee of Plaintiff called Defendant to determine why the electricity had been disconnected and was told that all four of Agstar’s accounts were four months past due, although Agstar’s past due accounts had been paid up as of July 10, 2003. Plaintiffs employee was also told that, as a requirement of reconnect, Plaintiff had to pay all amounts owed including Plaintiffs most recent bills, that is, bills that were mailed out just two days before the date of the disconnect, and that Plaintiff also had to pay a reconnect fee for all four accounts.

{8} Plaintiff sent payment to Defendant via overnight mail on September 8, 2003, after conversing with Defendant as to why the electricity had been disconnected. The district court found that Plaintiff did not pay the amounts billed until 11:13 a.m. on September 9, 2003, which was when Defendant received Plaintiffs payment for the August 9, 2003, bills. In that regard, the district court also found that Plaintiff “failed to take any reasonable efforts to make payment to [Defendant] on September 8, 2003.” The district court further found that Defendant admitted that it disconnected the electricity for nonpayment of Agstar’s bills that were, in Defendant’s view, guaranteed by Plaintiff, and that Defendant did not disconnect the electricity to Plaintiffs operation for any amounts owed by Plaintiff for its electrical use.

The Unfortunate Aftermath

Free access — add to your briefcase to read the full text and ask questions with AI

Sunnyland Farms, Inc. v. Central New Mexico Electric Cooperative, Inc., 2011 NMCA 49, 2011 NMCA 049, 255 P.3d 324, 149 N.M. 746 (N.M. Ct. App. 2011).

2011 NMCA 49 (Sunnyland Farms, Inc. v. Central New Mexico Electric Cooperative, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson Living Trust v. Conocophillips Co.
952 F. Supp. 2d 979 (D. New Mexico, 2013)
AG New Mexico, FCS, ACA v. Borges (In re Borges)
485 B.R. 743 (D. New Mexico, 2012)
Associated Home & RV Sales, Inc. v. Bank of Belen
2013 NMCA 18 (New Mexico Court of Appeals, 2012)
Core-Mark Midcontinent, Inc. v. Sonitrol Corp.
2012 COA 120 (Colorado Court of Appeals, 2012)
Sunnyland Farms, Inc. v. CENT. NM ELEC. CO-OP. INC.
255 P.3d 324 (New Mexico Court of Appeals, 2011)