Sunland Construction Co. v. Wilbur Smith, Inc.

387 F. App'x 361
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 6, 2010
Docket09-1642
StatusUnpublished

This text of 387 F. App'x 361 (Sunland Construction Co. v. Wilbur Smith, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunland Construction Co. v. Wilbur Smith, Inc., 387 F. App'x 361 (4th Cir. 2010).

Opinion

Affirmed by unpublished PER CURIAM opinion.

Unpublished opinions are not binding precedent in this circuit.

PER CURIAM:

Sunland Construction Company, Inc. (“Sunland”) filed suit against the City of Myrtle Beach, South Carolina (the “City”) alleging breach of contract after the City terminated its contract with Sunland for the installation, by horizontal direct drilling (“HDD”), of three 42-inch pipes to carry rainwater under Myrtle Beach and approximately 1000 feet out to sea. The termination of the contract was based on Sunland’s failure or refusal to complete the project. Sunland sought approximately $3 million in costs it allegedly incurred while attempting to perform under the contract based on what it alleged were defective specifications. Sunland also sued the City’s design engineer, Wilbur Smith Associates (“WSA”), for breach of its implied warranty of the suitability of the design specifications.

The City counterclaimed against Sun-land for breach of contract, seeking to recover approximately $400,000 from Sun-land and/or its surety in excess re-procurement costs it incurred by having the project completed by another contractor, using the alternative, and less risky, “open trench” method. The City also sued WSA for negligence and breach of contract.

Following an eight-day bench trial, the district court concluded that Sunland could not recover against the City for breach of contract because there was no meeting of the minds as to the allocation of risk for adverse subsurface conditions, and that the City could not recover against Sunland for the same reason. The court also found WSA was not liable to Sunland for negligence; however, it found that WSA was liable to the City. The ultimate finding of liability was based on the following subsidiary findings: (1) WSA negligently recommended that the contract be awarded to Sunland, inasmuch as; (2) Sunland’s bid was dramatically lower than the other HDD bids; (3) WSA had not adequately investigated Sunland’s bid prior to recommending it; and (4) WSA, which was not *363 independently qualified to render a recommendation, had fired its HDD consultant prior to making its recommendation to the City, a fact that WSA had withheld from the City at the time it made its recommendation. The district court awarded damages in the amount of $459,769.00 plus costs and attorney’s fees in favor of the City against WSA, rejected all other claims, and denied WSA’s motion for reconsideration.

Neither Sunland nor the City has appealed the district court’s orders; however, WSA noted an appeal alleging that the district court erred by:

(1) finding that WSA’s negligence was the proximate cause of the City’s damages; and
(2) concluding that there was no meeting of the minds between Sunland and the City regarding allocation of the risks for adverse subsurface conditions.

Following a trial, this court views the record in a light most favorable to the party prevailing below. See Sec. Exch. Comm’n v. Pirate Investor LLC, 580 F.3d 233, 237 n. 2 (4th Cir.2009); ePlus Tech., Inc. v. Aboud, 313 F.3d 166, 171 n. 1 (4th Cir.2002). The court reviews a district court’s conclusions of law de novo and its factual findings for clear error. Roanoke Cement Co. v. Falk Corp., 413 F.3d 431, 433 (4th Cir.2005). “A finding is ‘clearly erroneous’ when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” United States v. U.S. Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 92 L.Ed. 746 (1948); but see Fed.R.Civ.P. 52(a)(6) (due regard must be given “to the trial court’s opportunity to judge the witnesses’ credibility”).

I. Proximate Cause

It is well settled that issues of negligence, including proximate cause, “are generally treated as findings of fact reviewable under Fed.R.Civ.P. 52(a).” See Bonds v. Mortensen and Lange, 717 F.2d 123, 125 (4th Cir.1983) (citing Scheel v. Conboy, 551 F.2d 41, 43 (4th Cir.1977); Lane v. United States, 529 F.2d 175, 180 (4th Cir.1975)).

Under South Carolina law, “[p]roximate cause requires proof of both causation in fact and legal cause.” See Mellen v. Lane, 377 S.C. 261, 278, 659 S.E.2d 236 (Ct.App.2008) (citations omitted). “Causation in fact is proven by establishing the plaintiff’s injury would not have occurred ‘but for’ the defendant’s action,” whereas legal causation “is proved by establishing foreseeability” of harm to the plaintiff. Id. (citations omitted). WSA argues that its negligence was neither the “cause in fact” nor the “legal” cause of the City’s injuries. We address each contention in turn.

WSA argues that its negligence was not the “but for” cause of the City’s injuries because, even in the absence of its negligent recommendation that the contract be awarded to Sunland, the City “may still have contracted with Sunland.” In support of this contention, WSA points to the testimony of a superintendent with the City’s Public Works Department, which, WSA maintains, acknowledged that “even if the City had been aware during the bid process that the HDD method carried more risks that [sic] the trench method, the City may possibly have still awarded the project to Sunland.” WSA also argues that the City may have opened itself up to public criticism and lawsuits, if the City had not selected Sunland, which had been the lowest bidder for the project.

However, based on the entire record, when viewed in the light most favorable to the City, we find that the district court did *364 not clearly err in finding that WSA was the cause in fact of the City’s injuries (i.e., that but for WSA’s recommendation, the City. would not have chosen Sunland). There is substantial evidence to support the City’s contentions that the City was not required to award the contract to the lowest bidder and that it was persuaded to hire Sunland based on WSA’s representations. Further, WSA has offered nothing more than mere speculation concerning what the City “may possibly” have done in its attempt to show that the district court clearly erred on this point.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. United States Gypsum Co.
333 U.S. 364 (Supreme Court, 1948)
Willard H. Lane v. United States
529 F.2d 175 (Fourth Circuit, 1975)
Rose-Marie Scheel v. Joseph L. Conboy
551 F.2d 41 (Fourth Circuit, 1977)
Baggerly v. CSX Transportation, Inc.
635 S.E.2d 97 (Supreme Court of South Carolina, 2006)
Matthews v. Porter
124 S.E.2d 321 (Supreme Court of South Carolina, 1962)
Mellen v. Lane
659 S.E.2d 236 (Court of Appeals of South Carolina, 2008)
Whitlaw v. the Kroger Co.
410 S.E.2d 251 (Supreme Court of South Carolina, 1991)
R.J. Griffin & Co. v. Beach Club II Homeowners Ass'n
384 F.3d 157 (Fourth Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
387 F. App'x 361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunland-construction-co-v-wilbur-smith-inc-ca4-2010.