Sundstrom v. State

159 A.D. 241, 144 N.Y.S. 390, 1913 N.Y. App. Div. LEXIS 8140
CourtAppellate Division of the Supreme Court of the State of New York
DecidedNovember 26, 1913
StatusPublished
Cited by2 cases

This text of 159 A.D. 241 (Sundstrom v. State) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sundstrom v. State, 159 A.D. 241, 144 N.Y.S. 390, 1913 N.Y. App. Div. LEXIS 8140 (N.Y. Ct. App. 1913).

Opinion

Woodward, J.:

A judgment in this case was originally allowed by the Board of Claims on the 3d day of January, 1913, allowing certain items of a claim consisting of fifty-two different items. The State desired to appeal from only three of these items, and in order that the claimants might obtain their money on the others, and to save interest, a stipulation was entered into by which a new judgment, or judgments, were entered, dividing the original judgment into two parts or causes of action, known as determination No. 1 and detennination No. 2, the latter only being involved in this appeal. Determination No. 2 disallows all other items of the claim save items 46, 47 and 48. These three items all involve the same point, the claimants contending that they are entitled to recover the alleged increased cost of excavation due to the flow of water from the old Champlain canal in the sum of $38,444.34; for the increased cost of pumping, due to flow of water from the old Champlain canal, in the sum of $7,363.01, and for the cost of removal of slides, due to the [243]*243same cause, in the sum of $14,912.61. These have been allowed by the Board of Claims, and the State appeals from the judgment in so far as these items are concerned, and we are of the opinion that the Board of Claims is in error in making these allowances.

The theory upon which these claims have been allowed is that there was a material leakage from the old Champlain canal, which was in the immediate neighborhood of the barge canal, a section of such barge canal being the subject of the contract under which these claims arose, and that such leakage operated to increase the cost of the work to the contractors. There are cases, no doubt, where by the action of the owner or possessor of premises the cost of doing contract work is increased, and under proper circumstances 'the party causing the added cost may be called upon to compensate for the damages occasioned, but this is not such a case. The State of New York was called upon to construct about 450 miles of barge canal, involving an expenditure of at least $100,000,000, and to accomplish this work it was divided up into sections, and contracts were let from time to time for the work upon these various sections, among them being the contract now under consideration. Among the provisions of the particular contract we find that it was provided that “the estimate of quantities is to be accepted as approximate only, proposers being required to form their own judgment as to quantities and character of the work by personal examination upon the ground where the work is proposed to be done, and on the specifications and drawings relating thereto, or by such other means as they shall choose.” It was further provided that the “attention of persons intending to make proposals is specifically called to paragraph eight of the form of contract, which debars a contractor from pleading misunderstanding or deception because of estimates of quantities, character, location or other conditions surrounding the same.” Paragraph 8 of the contract provides: “ The contractor agrees that he has satisfied himself by his own investigation and research regarding all the conditions affecting the work to be done and labor and material needed, and that his conclusion to execute this contract is based on such investigation and [244]*244research, and not on the estimate of the quantities or other information prepared by the State Engineer, and that he shall make no claim against the State because any of the estimates, tests or representations of any kind affecting the work made by any officer or agent of the State may prove to be in any respect erroneous.” There are other provisions dealing more in detail, and enforcing this idea to a greater or less extent, but it seems to us entirely clear that the contractors in the present instance are fully estopped by the provisions already quoted, and that they have no possible claim against the State of Hew York because, after excavating to a considerable depth, they found water flowing into the prism of the barge canal which they claim came from the old Champlain canal in the near vicinity, and which added to the work and to the cost of the excavation.

The Champlain canal is one of the old canals of the State, and was situated partly upon and partly just east of the site of contract Ho. 3 (the one involved in this litigation), and at a higher elevation. From about the southerly gates of lock Ho. 6 on contract Ho. 3, about station 152, to station 164 the Champlain canal was within the lines of the prism of the barge canal, and a part of the work to be done under the contract was the construction of a temporary canal to take care of the traffic of the Champlain canal. From station 164 to the north the Champlain canal bears to the east, and at station 174 is about 300 feet distant from the easterly bank, and runs away to a distance of about 800 feet and then gradually returns until it practically intersects the barge canal at station 255. A portion of this intervening space was to be filled with the spoil taken from the prism of the barge canal, and it will be seen that it was practically upon the site of the contract, and it is idle to contend that this was not one of the conditions to be examined “ upon the ground where the work is proposed to be done ” by the contractor in making up his mind whether he wanted to take the contract. The fair reading of the contract requires the contractor to personally visit the site of the contract and to satisfy himself “by his own investigation and research regarding all the conditions affecting the work,” and he cannot be heard to say that he did not know of the presence [245]*245of the Champlain canal, or of the possibility of its leaking and causing the flow of water into the prism of the barge canal upon a lower level. This was one of the things the State had a right to contract for; it had a right to impose the risk of unlmown conditions upon individual contractors, who might personally investigate the special conditions, and the presumption is that the contractor took these risks into consideration and made his bid upon the basis of such risks. (Kinser Construction Co. v. State of New York, 204 N. Y. 381, 394.) It might be, of course, if the State had, after the work was under way, taken some affirmative action, such as cutting the banks of the Champlain canal and permitting the water to flow down into the prism, there would be cause for complaint, but where the State has simply contracted for certain work in a certain locality, and has stipulated that the contractor shall take the risks of quantities, conditions, etc., it is not the law that he can recover for alleged additional cost of doing the work which results from a condition which the State was not bound to know, and which the contractor had stipulated that he had taken into consideration, after a personal investigation, in making the contract. The reasoning in the case of Kinser Construction Co. v. State of New York (supra) seems to us conclusive upon this point, and the judgment, in so far as it is in favor of the claimants, should be reversed.

We come then to the claims which have been disallowed, and as to which the contractors appeal. Two claims, aggregating $261,621.73, are asserted for increased cost of performance of work, occasioned by delays due to acts, omissions and faults of the State and State officers, and for increased cost of pumping during increased time of performance, as occasioned by the wrongful acts, omissions or faults of the State. These are known as items 28 and 29.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman Co. v. County of Nassau
27 A.D.2d 936 (Appellate Division of the Supreme Court of New York, 1967)
New York State Construction Co. v. City of New York
163 A.D. 227 (Appellate Division of the Supreme Court of New York, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
159 A.D. 241, 144 N.Y.S. 390, 1913 N.Y. App. Div. LEXIS 8140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sundstrom-v-state-nyappdiv-1913.