Sumner, Admx. v. Lambert

121 N.E.2d 189, 96 Ohio App. 53, 54 Ohio Op. 173, 1953 Ohio App. LEXIS 651
CourtOhio Court of Appeals
DecidedDecember 8, 1953
Docket2224
StatusPublished
Cited by7 cases

This text of 121 N.E.2d 189 (Sumner, Admx. v. Lambert) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sumner, Admx. v. Lambert, 121 N.E.2d 189, 96 Ohio App. 53, 54 Ohio Op. 173, 1953 Ohio App. LEXIS 651 (Ohio Ct. App. 1953).

Opinion

Wiseman, P. J.

This is an appeal on questions of law from a judgment of the Common Pleas Court of Montgomery County, which directed a verdict in favor of defendants at the close of the plaintiff’s case in an action for wrongful death.

The Hoke Plumbing Company, the employer of plaintiff’s decedent, held the primary contract to do the plumbing work for Forsythe Homes, Inc., which was engaged in building a large number of residences. The Hoke Plumbing Company engaged C. D. Webb to dig the ditches from the main sewer to the basement wall. Webb in turn subcontracted this work to Lambert Brothers, a partnership, the defendants herein, who were in the excavating business. The defendants contracted to dig a straight ditch of the required depth and approximately 30 inches wide, from the main sewer to the basement walls. The defendants were not required under their contract to do any sloping, shoring or bracing of the ditch wall.

On May 22, 1948, the defendants dug four ditches. The employees of The Hoke Plumbing Company, one of whom was plaintiff’s decedent, followed closely behind the .defendants’ excavating equipment to lay the tile in the ditch and make the connection with the main sewer. No precautionary measures were taken by The Hoke Plumbing Company or its employees in sloping, shoring or bracing the ditch walls while laying the tile and making connection with the sewer. When the Lambert Brothers finished the digging of the fourth and last ditch on the day in question, they moved their excavating equipment some distance away and left the job. Their work, had been finished and the premises.. *56 were turned over to The Hoke Plumbing Company. Immediately the employees of The Hoke Plumbing-Company, who had completed the work of laying the tile in the other three ditches, began to lay tile in the fourth and last ditch. While other workmen of The Hoke Plumbing Company were laying tile in the ditch near the basement wall, the plaintiff’s decedent proceeded to make the connection with the main sewer. The ditch was approximately 50 feet long, extending in a northerly and southerly direction, and approximately four to five feet deep at the basement wall, being the north end, and from nine to 11 feet deep at the main sewer, being- the south end. The ditch was approximately 30 inches in width, with vertical sides. The earth was mostly sandy clay. The weather was fair and the earth was dry. The defendants excavated the ditch by the use of a steam shovel and piled the earth on the east side of the ditch. While the plaintiff’s decedent was in a crouched position in the south end of the ditch, and engaged in removing a small quantity of earth near the main sewer preparatory to making the connection, the wall on the east side of the ditch caved in and covered him with three feet of earth, causing his death by suffocation.

The case was presented to the jury on the second amended petition of the plaintiff, the amended answer of the defendants, and the reply of plaintiff.- Plaintiff’s claim was grounded on common-law negligence. Plaintiff alleged four specifications of negligence:

1. Failure to slope or step down the vertical sides of the ditch.

2. Failure to brace or shore the vertical sides of the ditch.

3. Undercutting the vertical sides of the ditch.

4. Piling the excavated earth so close to the edge of the ditch as to cause a cave-in, to wit, less than 18 .inches from the side of the ditch.

*57 The defendants in their amended answer set up four defenses. The first defense, after making certain admissions, was a general denial. In the second defense the defendants alleged that the cavé-in occurred after the defendants had completed their work of excavating the ditch and while the premises were under the sole and exclusive control of the employer of plaintiff’s decedent. In the third defense, the defendants pleaded contributory negligence and in the fourth defense they pleaded assumption of risk. The reply was in the nature of a general denial.

The evidence showed that the cave-in occurred approximately two hours after the defendants had finished the excavating and after they had moved their equipment some distance away and left the job. The defendants had excavated in a similar manner approximately 134 of such ditches in the project. The defendants were not required under their contract with Webb to slope, shore or brace the sides of the ditch. The defendants under their contract were required only to excavate a straight ditch of approximately 30 inches in width, the required depth, from basement wall to the main sewer, and leave it in this condition for other contractors and their workmen to perform their work. The evidence shows that the defendants performed their work as required by the contract. A short time before the cave-in, some earth near the water main, which was approximately 8 or 9 feet from the main sewer, fell into the ditch, whereupon the employees of The Hoke Plumbing Company shoveled such earth out of the ditch.

There is conflict in the evidence as to the location of the excavated earth. Some of the witnesses testified that the excavated earth was piled so close that fine particles of earth rolled into the ditch; other witnesses testified that there was space for the workmen to walk between the edge of the ditch and the pile of earth. At *58 the deep end of the ditch, where the cave-in occurred, and where a greater amount of earth had been excavated, the earth was piled four or five feet high. There is no evidence that the sides of the ditch had been undercut as alleged.

The plaintiff’s decedent was an apprentice plumber and had worked mostly indoors, but occasionally was assigned to work on this project, and he had previously assisted in the laying of tile and the making of connections with the main sewer. All the ditches excavated by the defendants on this project, numbering approximately 134, were excavated as straight ditches, without sloping, shoring or bracing. Furthermore, The Hoke Plumbing Company, the employer of plaintiff’s decedent, did nothing in the way of sloping, shoring or bracing the sides of any of these ditches to protect its employees.

At the close of plaintiff’s case the court directed a verdict for defendants, stating that there was no evidence that the sides of the ditch had been undercut; that the evidence shows that the sides of the ditch were vertical, without being sloped, shored or braced; and that there was considerable evidence indicating that the excavated earth was piled nearer than 18 inches from the side of the ditch. The court found that all four specifications of negligence coincided with specific safety requirements adopted by the Industrial Commission of Ohio. The court ruled that those requirements applied only to employers for the protection of their own employees and did not extend to plaintiff’s decedent, who.was not an employee of the defendants. The court ruled that plaintiff’s right of recovery was grounded on common-law negligence: that under the evidence, plaintiff’s decedent assumed the risk; and that, while there was a conflict in the evidence as to the location of the excavated earth, the evi *59 deuce left it to the conjecture of the jury as to the proximate cause of the cave-in.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peters v. Forster
804 N.E.2d 736 (Indiana Supreme Court, 2004)
Jackson v. City of Franklin
554 N.E.2d 932 (Ohio Court of Appeals, 1988)
Bush v. Albert D. Wardell Contractor, Inc.
528 P.2d 215 (Montana Supreme Court, 1974)
In Re Silver Bridge Disaster Litigation
381 F. Supp. 931 (S.D. West Virginia, 1974)
Patten v. Logemann Bros. Co.
283 A.2d 567 (Court of Appeals of Maryland, 1971)
McDonald v. Frontier Lanes, Inc.
272 N.E.2d 369 (Appellate Court of Illinois, 1971)
American States Ins. v. Hannan Constr. Co.
283 F. Supp. 988 (N.D. Ohio, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
121 N.E.2d 189, 96 Ohio App. 53, 54 Ohio Op. 173, 1953 Ohio App. LEXIS 651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sumner-admx-v-lambert-ohioctapp-1953.