Summit Texas Clean Energy, LLC v. United States

CourtUnited States Court of Federal Claims
DecidedAugust 20, 2018
Docket17-1138
StatusPublished

This text of Summit Texas Clean Energy, LLC v. United States (Summit Texas Clean Energy, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summit Texas Clean Energy, LLC v. United States, (uscfc 2018).

Opinion

In the United States Court of Federal Claims No. 17-1138C (Filed: August 20, 2018)

*************************

SUMMIT POWER GROUP, LLC, and Contracts; declaratory CCM TCEP, LLC, judgment; 28 U.S.C. § 1491(a)(1) (2012); Plaintiffs, guaranty agreement; debt cancellation; v. cooperative agreement. THE UNITED STATES,

Defendant.

Stanley R. Soya, Washington, DC, with whom was Ellen M. Lynch for plaintiffs.

Adam E. Lyons, United States Department of Justice, Civil Division, Commercial Litigation Branch, Washington, DC, for defendant.

OPINION BRUGGINK, Judge.

The United States, acting through the Department of Energy’s National Energy Technology Laboratory (“DOE”), entered into Cooperative Agreement DE-FE0002650 with Summit Texas Clean Energy, LLC (“STCE”) on January 29, 2010. Plaintiffs, Summit Power Group, LLC and CCM TCEP, LLC (“SPG” and “CCM,” collectively “the guarantors”) guaranteed $13.8 million that DOE paid to STCE under the cooperative agreement. After DOE terminated the cooperative agreement, plaintiffs sued, seeking a declaration that they have no obligation to pay DOE the guaranteed sum because either DOE has not met the conditions stated in their payment agreements or DOE materially breached the implied duty of good faith and fair dealing, precluding DOE from terminating for STCE’s failure to reach financial close.

Pending is defendant’s motion to dismiss plaintiffs’ amended complaint for lack of subject-matter jurisdiction or failure to state a claim. The motion is fully briefed and we held oral argument on August 9, 2018. Because the remedy that plaintiffs seek is purely declaratory, lacking any claim for actual, presently due money damages from the United States, we grant defendant’s motion to dismiss for lack of subject-matter jurisdiction.

BACKGROUND

The United States, acting through DOE, established the Clean Coal Power Initiative in 2002 with the objective of promoting investment in efficient, environmentally-friendly coal power projects.1 In furtherance of this initiative, DOE entered into Cooperative Agreement DE-FE0002650 with STCE on January 29, 2010. By constructing and operating the Texas Clean Energy Project (“TCEP”), STCE hoped to integrate a commercial electric power plant with carbon dioxide capture and sequestration. DOE agreed to provide financial support as well as oversight and collaboration in the process of designing and constructing the TCEP.

The project would proceed in four phases: project definition, design, construction, and demonstration. STCE and DOE were to share all costs incurred on an “‘as-expended’, dollar-for-dollar basis” by applying the cost share ratios in the cooperative agreement. Def.’s Mot. to Dismiss App. 14. DOE was not obligated to provide funding beyond its cost share and had sole discretion to decide the availability of funds, whether STCE had made substantial progress, and whether continuing the agreement was advantageous to DOE. At the conclusion of each phase, the cooperative agreement obligated STCE to submit to DOE a Decision Point Application that demonstrated progress, provided a budget for the next phase, and described next steps in the project. If DOE did not approve the Decision Point Application, DOE’s

1 The Energy Policy Act of 2005, Pub. L. No. 109–58 § 401–405, 119 Stat. 749–753 (2005) (codified at 42 U.S.C. § 15961–15965 (2012)), and the American Recovery and Reinvestment Act of 2009, Pub. L. No. 111–5, 123 Stat. 115 (2009) set forth technical requirements and funded the Clean Coal Power Initiative.

2 maximum liability was the funding approved for the current phase. DOE also reserved the right to retain funds approved for a phase in the event that STCE failed to meet certain milestones.

The parties projected that the total project cost would be $1.72 billion; DOE initially anticipated its contribution would be $350 million but later increased that figure to $450 million. At the outset, DOE obligated $215 million for the project. Only $15 million was “available for work performed by [STCE] during Phase I of the Project . . . . The remainder of these funds [$200 million] will be available contingent upon the submission by [STCE] of a Decision Point Application and written approval of the Decision Point Application by the DOE Contracting Officer.” Id. at 20.

Phase 1 began February 1, 2010, and was set to conclude December 31, 2010. During Phase 1, STCE was to secure commitments from investors and lenders to provide all non-federal funding needed to construct the TCEP. STCE would match DOE’s $15 million contribution to Phase 1. STCE did not secure the necessary funding by the deadline, however. Instead, DOE repeatedly extended Phase 1, divided Phase 1 into a series of four sub-phases, and provided accelerated payments to assist STCE in securing financing.

To receive accelerated payments, STCE agreed to a modified cost sharing provision. DOE agreed to reimburse STCE at a higher rate in Phase 1 in exchange for reimbursing STCE at a lower rate during later phases. STCE agreed that it was “liable for the percentage of total allowable project costs . . . even if the project is terminated early or is not funded to completion.” Pls.’ Am. Compl. App. Ex. 4 at 4. If STCE did not achieve its applicable cost share by the time of project termination or discontinuance, it agreed to “refund sufficient funds to DOE in order to achieve its required cost share of total project costs accrued at the point of the project’s termination or discontinuance.” Id. STCE and DOE also modified the cooperative agreement to provide “that DOE may, at its discretion, allow [STCE] to invoice the DOE at an accelerated rate of up to 80% of the total allowable costs on an invoice-by-invoice basis from the time of award until all . . . funds obligated to this award ($211,097,445) have been expended.” Pls.’ Ex. 5 at 5.

DOE requested that STCE provide security for some of the accelerated payments. On February 15, 2012, Modification 14 “recognize[d] and incorporate[d] certain tranches of security” for a portion of $16.2 million in accelerated payments to STCE. Pls.’ Ex. 2 at 3. SPG guaranteed $6.8 million of the $16.2 million. Assuming STCE had insufficient funds, SPG would be 3 required to repay DOE if the cooperative agreement was “terminated by STCE; terminated by DOE for material noncompliance; discontinued by STCE; or discontinued by DOE pursuant to the Decision Point Application process for failure to achieve the technical objectives for Phase 1.” Id. at 5. SPG would pay a portion of the guaranteed amount immediately and the rest in installment payments.

Modification 15 incorporated into the cooperative agreement CCM’s payment agreement as well as an amended payment agreement increasing SPG’s guaranty by $1 million. CCM agreed to deposit $6 million in a segregated deposit account, which it would maintain in the event that STCE was obligated to repay the accelerated payment and failed to do so. If STCE failed to repay, CCM would release to DOE the $6 million if STCE terminated or discontinued the cooperative agreement or if DOE terminated the agreement for material noncompliance or discontinued the agreement pursuant to the Decision Point Application Process for failure to achieve the technical objectives of Phase 1. In sum, SPG guaranteed STCE’s repayment up to $7.8 million and CCM guaranteed up to $6 million, totaling $13.8 million.

By December 2015, DOE had provided STCE with $117.9 million for Phase 1, more than one hundred million in excess of its original commitment to Phase 1. In late 2015, STCE requested additional funding to complete Phase 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McNutt v. General Motors Acceptance Corp.
298 U.S. 178 (Supreme Court, 1936)
United States v. King
395 U.S. 1 (Supreme Court, 1969)
United States v. Testan
424 U.S. 392 (Supreme Court, 1976)
Rick's Mishroom Service, Inc. v. United States
521 F.3d 1338 (Federal Circuit, 2008)
Holmes v. United States
657 F.3d 1303 (Federal Circuit, 2011)
Trusted Integration, Inc. v. United States
659 F.3d 1159 (Federal Circuit, 2011)
St. Bernard Parish Government v. United States
134 Fed. Cl. 730 (Federal Claims, 2017)
Moore v. United States
48 Fed. Cl. 394 (Federal Claims, 2000)
Katz v. Cisneros
16 F.3d 1204 (Federal Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Summit Texas Clean Energy, LLC v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summit-texas-clean-energy-llc-v-united-states-uscfc-2018.