Summit Court, Inc. v. Northern States Power Co.

354 N.W.2d 13, 1984 Minn. LEXIS 1451
CourtSupreme Court of Minnesota
DecidedAugust 31, 1984
DocketCX-83-375
StatusPublished
Cited by20 cases

This text of 354 N.W.2d 13 (Summit Court, Inc. v. Northern States Power Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summit Court, Inc. v. Northern States Power Co., 354 N.W.2d 13, 1984 Minn. LEXIS 1451 (Mich. 1984).

Opinion

WAHL, Justice.

This appeal, by Summit Court, Inc., involves the propriety of awarding prejudgment interest on two separate damage awards arising out of the 1978 gas explosions and fire at the Commodore Hotel in St. Paul. We affirmed the jury’s award of property damages in In re Commodore Hotel Fire and Explosion Cases, 324 N.W.2d 245 (Minn.1982), and remanded the case for a determination of loss-of-use damages during the period of restoration Ramsey County District Court, in orders dated February 16, 1983, and March 1, 1983, denied prejudgment interest on both the property damages and the loss-of-use damages award. We affirm as to the property damages award and reverse as to the loss-of-use damages award.

I. PREJUDGMENT INTEREST ON PROPERTY DAMAGES AWARD.

Gas explosions on February 15, 1978, substantially damaged the Commodore Hotel and forced it to cease operation. Summit Court’s estimate of restoration damages was $1,373,824.61. Its insurance company estimated damages at $1,036,270.14. The two finally agreed on $1,140,000 as the cost of repairs and then subtracted $288,-889, the agreed upon figure representing “betterment” as the result of the repairs. The actual cash value loss agreed on was $851,721. Because the hotel was underin-sured, it recovered only $742,750 from the insurer, leaving $108,971 as a loss for Summit Court.

Summit Court then brought the original tort action against Northern States Power Company (NSP) who provided and Grudem Brothers who installed the gas service to the building. Uncompensated property damages and lost profits were sought. Although Summit Court tried to obtain a greater amount of property damages, the defendants were successful in using Summit Court’s agreement with its insurer to set the amount of damages, and the jury awarded the exact amount uncompensated by insurance benefits, $108,971.61. Summit Court appealed, and we affirmed. In re Commodore Hotel, 324 N.W.2d at 245. On October 8, 1982, NSP and Grudem Brothers sent Summit Court’s attorney two checks totaling $139,277.08, which represented the property damages award plus costs and postjudgment interest. On October 14, 1982, Summit Court’s attorney sent a Satisfaction of Judgment in the amount of $107,061.25 to the defendant’s attorney and cashed the checks. On February 1, 1983, just prior to the second trial to deter *15 mine loss-of-use damages, Summit Court presented a motion to the trial court requesting prejudgment interest on the property damages award that had been satisfied the previous October.

The first issue, then, is whether Summit Court was entitled to prejudgment interest on the property damages award. A preliminary issue, however, and one we find dis-positive, is whether, even if Summit Court was so entitled, it waived its right to any further amount based on the property damages award by negotiating the checks sent by defendants in satisfaction of the judgment and executing a release and satisfaction. Along with the checks, the defendants sent a release and satisfaction form to be signed by Summit Court’s appropriate officer. The accompanying letter stated, “We forward the checks with the understanding that they will not be released from your possession or presented for payment unless and until the release and satisfaction has been properly executed and returned to us.” The release and satisfaction finally executed by Summit Court stated that the judgment was thereby “acknowledged to be paid and satisfied in full.”

Summit Court argues that, because its claim for prejudgment interest was completely separate from its property damages claim, the release and satisfaction cannot function to bar its claim for interest. We do not agree. Prejudgment interest is bound up with the underlying damages award. It is part of the damages suffered by plaintiff where the defendant could have readily ascertained the damages and tendered them prior to trial. In this case, the litigation had spanned several years by the time the judgment was satisfied. If Summit Court thought that the damages amount was erroneous because it did not include prejudgment interest, the time to contest it was before accepting payment and executing the release and satisfaction. In Jones v. Atteberry, 77 Ill.App.3d 463, 471, 33 Ill.Dec. 28, 34, 396 N.E.2d 104, 110 (1979), the court held that where the record showed that the judgment had been satisfied and released, the plaintiffs were precluded from recovery of additional interest on the amount of the judgment, because the release barred further action in the case. Satisfaction of a judgment is the last act of a proceeding. As the Colorado Supreme Court noted, “It extinguishes the judgment for all purposes and thereby promotes the interests of certainty and repose.” Dooley v. Cal-Cut Pipe & Supply, Inc., 197 Colo. 362, 364, 593 P.2d 360, 362 (1979). We agree and hold that where a plaintiff accepts payment of a judgment in its favor and executes a release and satisfaction of that judgment, it may not later claim prejudgment interest on the damages award underlying the judgment.

II. PREJUDGMENT INTEREST ON LOSS-OF-USE DAMAGES.

Summit Court moved for prejudgment interest on the loss-of-use damages award just after the trial to determine those damages and prior to entry of judgment. At that trial, the parties stipulated to the amounts of monthly fixed, unabatable overhead costs for real estate taxes, mortgage interest, license fees and insurance premiums during the period of restoration. The final jury award included not only these amounts but also amounts for legal and accounting fees as well as other fixed costs. NSP had challenged the propriety of the inclusion of the legal and accounting fees. Summit Court sought prejudgment interest from the time that the building was restored and those costs had become verifiable bookkeeping items.

There were two issues at trial: (a) whether Summit Court would have had sufficient gross income to cover the fixed costs if the explosions had never occurred and (b) the length of time reasonably needed to restore the building. Both issues were extensively litigated. The jury found that Summit Court would have had sufficient income to cover the fixed costs and awarded $209,679 in loss-of-use damages, a figure approximately midway between Summit Court’s claim for $353,928 and NSP’s suggested amount of $41,237. The amount of the award was based on the number of months *16 the jury determined that it reasonably took for restoration.

A plaintiff is entitled to prejudgment interest on a final judgment where the damages claim is liquidated or, if unliq-uidated, “where the damages were readily ascertainable by computation or reference to generally recognized standards such as market value and not where the amount of damages depended upon contingencies or upon jury discretion (as in actions for personal injury or injury to reputation).” Potter v. Hartzell Propeller, Inc., 291 Minn. 513, 518, 189 N.W.2d 499, 504 (1971). 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duxbury v. Spex Feeds, Inc.
681 N.W.2d 380 (Court of Appeals of Minnesota, 2004)
Schwickert, Inc. v. Winnebago Seniors, Ltd.
680 N.W.2d 79 (Supreme Court of Minnesota, 2004)
Schwickert, Inc. v. Winnebago Seniors, Ltd.
661 N.W.2d 680 (Court of Appeals of Minnesota, 2003)
Rice Lake Contracting Corp. v. Rust Environment & Infrastructure, Inc.
616 N.W.2d 288 (Court of Appeals of Minnesota, 2000)
Pine Valley Meats, Inc. v. Canal Capital Corp.
566 N.W.2d 357 (Court of Appeals of Minnesota, 1997)
Skifstrom v. City of Coon Rapids
524 N.W.2d 294 (Court of Appeals of Minnesota, 1995)
Dear v. Minneapolis Fire Department Relief Ass'n
481 N.W.2d 69 (Court of Appeals of Minnesota, 1992)
Casey v. State Farm Mutual Automobile Insurance Co.
464 N.W.2d 736 (Court of Appeals of Minnesota, 1991)
Higgins v. J.C. Penney Casualty Insurance Co.
413 N.W.2d 189 (Court of Appeals of Minnesota, 1987)
Hogs Unlimited v. Farm Bureau Mutual Insurance Co.
401 N.W.2d 381 (Supreme Court of Minnesota, 1987)
Solid Gold Realty, Inc. v. Mondry
399 N.W.2d 681 (Court of Appeals of Minnesota, 1987)
Hogs Unlimited v. Farm Bureau Mutual Insurance Co.
390 N.W.2d 886 (Court of Appeals of Minnesota, 1986)
Acton Construction Co. v. State
383 N.W.2d 416 (Court of Appeals of Minnesota, 1986)
Summit Court, Inc. v. Northern States Power Co.
382 N.W.2d 560 (Court of Appeals of Minnesota, 1986)
Regents of the University of Minnesota v. Medical Inc.
382 N.W.2d 201 (Court of Appeals of Minnesota, 1986)
L.P. Medical Specialists, Ltd. v. St. Louis County
379 N.W.2d 104 (Court of Appeals of Minnesota, 1985)
Bilotta ex rel. Cutting v. Kelley Co.
358 N.W.2d 679 (Court of Appeals of Minnesota, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
354 N.W.2d 13, 1984 Minn. LEXIS 1451, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summit-court-inc-v-northern-states-power-co-minn-1984.