Summit Contractors, Inc. v. General Heating & Air Conditioning, Inc.

595 S.E.2d 472, 358 S.C. 410, 2004 S.C. LEXIS 97
CourtSupreme Court of South Carolina
DecidedApril 19, 2004
DocketNo. 25805
StatusPublished
Cited by2 cases

This text of 595 S.E.2d 472 (Summit Contractors, Inc. v. General Heating & Air Conditioning, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summit Contractors, Inc. v. General Heating & Air Conditioning, Inc., 595 S.E.2d 472, 358 S.C. 410, 2004 S.C. LEXIS 97 (S.C. 2004).

Opinion

Justice MOORE.

Petitioner (Contractor) brought this action on behalf of its insurer, Crum & Forster (Insurer),1 asserting Insurer’s right to be subrogated to Contractor’s claim against respondent (Subcontractor) for fire damage to a construction site. Subcontractor asserted as a defense the waiver of subrogation clause found in its contract with Contractor. We granted a writ of certiorari to review the Court of Appeals’ unpublished opinion holding the waiver of subrogation clause valid. We affirm.

FACTS

Subcontractor’s employee/sub-subcontractor allegedly caused the fire by negligent soldering. For purposes of this appeal, Subcontractor’s liability is assumed. Insurer paid Contractor $935,0002 under its property loss policy. The trial judge granted Subcontractor a directed verdict based on the waiver of subrogation clause and the Court of Appeals affirmed.

[413]*413ISSUES

1. Are Schedules A and B of the contract controlling over other form provisions of the contract?

2. Is the contract ambiguous?

3. Is the waiver of subrogation clause ambiguous and against public policy?

DISCUSSION

1. Validity of form provisions

In the course of negotiating the contract with Contractor, Subcontractor submitted a standard form contract developed by the American Institute of Architects, hereinafter referred to as the “AIA form.” This form contains the waiver of subrogation provision at issue. In response, Contractor submitted Schedule A and Schedule B as additional contract terms. Subcontractor made some handwritten changes to these Schedules before agreeing. The AIA form and Schedules A and B together became the agreement between the parties.

Contractor argues that Schedules A and B of the contract control over the AIA form which includes the waiver of subrogation clause. Contractor relies on provisions in these Schedules that hold Subcontractor liable for damage caused by faulty workmanship and argues these provisions invalidate the waiver of subrogation clause.3

The Court of Appeals found the provisions of the Schedules do not override the provisions of the AIA form because these Schedules are themselves essentially boilerplate. We agree. Michael Rodgers, Contractor’s vice-president, testified Schedules A and B were Contractor’s “standard” agreement form used for subcontracting. Contractor is not relying on any of the handwritten changes made to these Schedules during the parties’ negotiations but points to provisions included in the standard form part of the Schedules. These standard form provisions do not control as a matter of law simply because they are not industry-wide forms like the AIA form. Cf. Riverside Bldg. Supply, Inc. v. Fed. Emergency Management [414]*414Agency, 723 F.2d 1159 (4th Cir.1983) (typewritten terms inserted in preprinted form reflect more exactly the agreement of the parties).

In any event, as discussed below, the waiver of subrogation clause found in the AIA form and the liability provisions of Schedules A and B are not inconsistent. Even if the provisions of the Schedules were to be given more weight, they would not invalidate the subrogation clause.

2. Whether the contract as a whole is ambiguous

Contractor contends the provisions of Schedules A and B conflict with the waiver of subrogation clause rendering the contract ambiguous. It argues because the contract is ambiguous, its terms must be determined by the fact-finder and a directed verdict was inappropriate. The Court of Appeals found the contract is not ambiguous and concluded the waiver of subrogation clause is enforceable. We agree.

The relevant provisions of the contract are as follows. Paragraph 13.5 of the AIA form provides:

13.5 Waivers of Subrogation. The Contractor and Subcontractor waive all rights against (1) each other ... for damages caused by fire ... to the extent covered by property insurance ... applicable to the Work.... The policies shall provide such waivers of subrogation by endorsement or otherwise. A waiver of subrogation shall be effective as to a person or entity even though that person or entity would otherwise have a duty of indemnification, contractual or otherwise, did not pay the insurance premium directly or indirectly, and whether or not the person or entity had an insurable interest in the property damaged.

Schedule A includes the following provisions:

4. SUBCONTRACTOR acknowledges and agrees that it has the sole responsibility for compliance with all of the requirements of the Occupational Safety and Health Act of 1970 and agrees to indemnify and hold harmless CONTRACTOR against any legal liability or loss which CONTRACTOR may incur due to SUBCONTRACTOR’S failure to comply with the above referenced Act.
7. SUBCONTRACTOR will be liable for any actions or damages caused by its material suppliers and sub-[415]*415subcontractors. SUBCONTRACTOR will be responsible for damages caused by SUBCONTRACTOR, its suppliers or sub-subcontractors to the work.
32. SUBCONTRACTOR shall be held responsible for all damages to the building or the work of others resulting from his negligence.
33. SUBCONTRACTOR is to maintain all amounts of insurance listed in Specifications for the duration of the project. If no requirement is listed in Specifications, SUBCONTRACTOR is to maintain the amounts of insurance required by law for the State in which the work is being performed.

Schedule B includes the following:

1. Before work commences, the SUBCONTRACTOR shall submit an original insurance certificate indicating General Liability Coverage and Limits and Worker’s Compensation Coverage....
5. SUBCONTRACTOR shall be held responsible for all damages to property or the Work of others resulting from his/her Work, including consequential damages resulting therefrom.
6. Where damages to buildings and/or furnishing occur due to faulty Workmanship or faulty materials, said damages will be backcharged to the SUBCONTRACTOR including any consequential damages resulting therefrom.

Contractor contends that Subcontractor’s agreement to be “held responsible” for damages and to carry liability insurance conflict with the waiver of subrogation clause. We find no conflict. Reading the contract as a whole, the waiver of subrogation clause provides that subrogation is waived to the extent damages are covered by property insurance. Under the provisions of Schedules A and B, Subcontractor remains liable for any excess damages not covered by property insurance. The requirement that Subcontractor carry liability insurance would apply to excess damages and other damages not covered by property insurance.

Since there is no ambiguity, the trial court properly directed a verdict based on the waiver of subrogation clause.

[416]*416 3. The waiver of subrogation clause

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wright v. Hiester Construction Co.
698 S.E.2d 822 (Court of Appeals of South Carolina, 2010)
Wright v. HIESTER CONST. CO., INC.
698 S.E.2d 822 (Court of Appeals of South Carolina, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
595 S.E.2d 472, 358 S.C. 410, 2004 S.C. LEXIS 97, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summit-contractors-inc-v-general-heating-air-conditioning-inc-sc-2004.