Summer v. State Highway Commission

141 S.E. 366, 143 S.C. 196, 1928 S.C. LEXIS 14
CourtSupreme Court of South Carolina
DecidedJanuary 10, 1928
Docket12353
StatusPublished
Cited by1 cases

This text of 141 S.E. 366 (Summer v. State Highway Commission) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summer v. State Highway Commission, 141 S.E. 366, 143 S.C. 196, 1928 S.C. LEXIS 14 (S.C. 1928).

Opinions

The opinion of the Court was delivered by

Mr. Justice Stabler.

This action was brought by certain taxpayers of New-berry County for the purpose of enjoining the State Highway Commission and the Newberry County Highway Commission from constructing a graded top-soiled road on a section of Route 2 from the intersection of Route 2 and the old state road to Clinton, approximately one mile south of Newberry, to the intersection of Routes 2 and 19, approximately one mile north of Newberry, a distance'of 3.39 miles, at an estimated cost of $20,000.00. On the summons and verified petition Judge C. C. Featherstone, on April 21, 1927, granted a temporary order of injunction and a rule to show cause why a permanent injunction should not be granted. Hearing was had on the rule on April 29, 1927, and Judge Featherstone subsequently issued an order discharging the rule and dissolving the temporary injunction. From this order the petitioners appeal.

The taxpayers’ petition, the return of the State Highway Commission, the return of the County Highway Commission, and the replies to both returns, will be incorporated in the report of the case. Exhibit I, showing a plat of the section of road involved, will also be included in the report.

*214 The State Highway designated as No. 2 in the Pay-As-You-Go Act passes from Lexington County, near Little Mountain, northwesterly by way of Prosperity through the Town of Newberry by way of Adelade Street, Glenn Street, Main Street, and College Street, and from thence to the Laurens County line by way of Kinards. So much of this highway as is necessary for the consideration of this case is shown on the plat.

During the year 1926, the State Highwajr Commission hard-surfaced Highway No. 2 from the Town of Prosperity to the corporate limits of the Town of Newberry. At its 1927 session the General Assembly passed an Act approved on March 14, 1927, authorizing the Treasurer of Newberry County and the Chairman of the Newberry County Highway Commission to borrow not exceeding $400,000.00 for the construction of certain highways or sections thereof, in Newberry County, and to pledge as security therefor, such reimbursement agreement or agreements as the Newberry County Highway Commission might make with the State Highway Commission. During the same month the State Highway Commission and the Newberry County Highway Commission entered into a reimbursement agreement by the terms of which a section of Highway No. 2 from the city limits of Newberry to the Laurens County line near Kinards, a distance of approximately 12.5 miles, is to be graded and hard-surfaced at an estimated cost of $365,-000.00. By the same reimbursement agreement the section of Route No. 2 in controversy is to be granted and top-soiled at an estimated cost of $20,000.00. This section is shown on the plat by line A-C-B.

The appellants contended that the proposed grading and top-soiling of this section of Highway No. 2 is not authorized by law and that the State and County Highway Commissions have no authority to enter into the reimbursement agreement for constructing, grading and top-soiling this section; and*that the construction, grading and top-soiling *215 of this section would be a useless, reckless and extravagant expenditure of the public funds without adequate recompense to the taxpayers and the traveling public and would divert travelers away from the Town of Newberry and thus be very detrimental to the citizens and taxpayers of the Town and County of Newberry and would be of practically no benefit to the citizens and taxpayers of Newberry County.

The respondent took issue with the appellants on these questions.

At the hearing, before Judge Featherstone, affidavits were submitted on both sides, and Judge Featherstone, as stated, refused to make the injunction permanent and dissolved the temporary injunction.

The questions involved in the appeal are thus stated by the appellant’s counsel:

“First. Did the State Highway Commission and the County Highway Commission have the authority under the Statute Daw of the State to construct the section of road in question ?
“(a) Was such authority given under the Act of 1927, which we will designate as the $400,000.00 Act? Acts of 1927, p. 990.
“(b) Did the Act of 1924, known as the ‘Pay-As-You-Go’ Act, authorize the construction of this section as a belt line? Acts of 1924, p. 1193.
“(c) Did the Act of 1927, which we will designate as Ratifying Act, ratify and confirm the addition of this section? Acts of 1927, p. 278.
“Second. Is the construction of this section an extravagant and unwarranted expenditure of money and detrimental to the citizens' and taxpayers of the Town and County of Newberry and, thus, an abuse of the discretion of the State Highway Commission?”

I. (b) As far as this case is concerned, the road designated in the Pay-As-You-Go Act of 1924 as Route No. 2 has been in part constructed and is in part in process of *216 construction and passes through the Town of Newberry, which is specifically mentioned in the Act as one of its control points. No .question is raised as to the construction of this highway along the designated route, and this case is-thus differentiated from Gaston v. State Highway Department, 134 S. C., 402; 132 S. E., 680, in which the question was raised whether the road proposed to be built by the State Highway Commission conformed to the route designated in the Act.

The decision of the point now under consideration revolves about the following provision of the Pay-As-You-Go Act:

“The State Highway Commission is hereby authorized to establish such belt lines not exceeding two miles in length as it deems proper and justifiable and to construct and maintain such belt lines from the funds herein provided.” Section 2.

The appellants contend that the section of road in controversy, being more than two miles in length, -is not authorized under this provision.

The respondents point out that Route No. 22, the road toWinnsboro, crosses the section in controversy (C on the plat) and divides it into two segments, 1.3 miles and 2 miles-in length, respectively, and contend that the section constitutes in reality two belt lines (A-C and C-B), each of which falls within the limitation of the Act as to length.

In 7 C. J., at page 1044, the following is given as a definition of “belt railroad”:

“A railroad encircling a city or other restricted territory,, intersected by other railroads, not having a common right of way into the territory for the purpose of transferring and', switching cars from one railroad to another with which it is not otherwise connected, or for transferring cars between such railroads and industrial plants located in the neighborhood of but not on such railroads.”

*217

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hedrick v. Graham
96 S.E.2d 129 (Supreme Court of North Carolina, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
141 S.E. 366, 143 S.C. 196, 1928 S.C. LEXIS 14, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summer-v-state-highway-commission-sc-1928.